Material Requirement Planning
Material Requirement Planning
Planning
Dr. Anurag Tiwari
IIM Rohtak
Hierarchy of Production Decisions
Forecast of Future
Demand
Aggregate Planning
For any product, all components of that product are dependent demand items.
Given a quantity for the product, the demand for all parts and components can be
calculated.
MRP
The logic for determining the number of parts, component, and material needed to produce
a product.
MRP has been installed almost universally in manufacturing firms.
The reason is that MRP is a logical, easily understandable approach to the problem of
determining the number of parts, components and materials needed to produce each end
item.
MRP also provides the schedule specifying when each of these items should be ordered or
produced.
What is Material Requirement Planning
MRP is most valuable in industries where a number of products are made in batches using
the same productivity equipment.
MRP is most valuable to companies involved in assembly operations and least valuable to
those in make to order fabrication.
MRP does not work well in companies that produce a low number of unit annually.
What is Material Requirement Planning
Time-phased plan specifying how many and when the company plans to produce each end
item
Aggregate Plan
(Product Groups)
MPS
(Specific End Items)
Master Production Schedule (MPS)
Before it is executed, MPS must be tested for feasibility (Capacity Requirements Planning)
Master Production Schedule (MPS)
Week
Master Production 1 2 3 4 5 6 7 8
Schedule for mattress
models Model 200 400 200 100
327
Model 100 100 150 100
538
8 15 26
Weeks
Management defines time fences as period of time having some specified level of opportunity
for the customer to make changes.
Material Requirement Planning System
Structure
The material requirement planning of manufacturing activities most closely interacts with
Master Schedule
Bill of Materials File
Inventory Record File
Output Reports
Material Requirement Planning System
Structure
Forecast of
Demand from
customers
Aggregate
Firm orders
from Production Plan
customers
Engineering Inventory
Master
Design Transaction
Change
Production
Schedule (MPS)
Material
Bill of materials Planning(MRP Inventory
file Computer record file
Program )
Product demand for end items comes from two main sources
Customers who have placed specific orders (Such as those generated by sales personnel or
independent transactions)
These orders usually carry promised delivery dates
The second source is the aggregate production plan
The aggregate plan reflects the firms strategy for meeting demand in future
Bill of Material
The bill of materials (BOM) file contains the complete product description, listing the
materials parts and component; the quality of each item and also the sequence in which
product is created.
The bill of Management file is often called the product structure file or product tree
because it shows how a product is put together.
It contains the information to identify each item and the quantity used per unit of the item
which it is a part.
Bill of Material
B(2) C(3)
A modular bill of material is the term for a buildable item that can be produced and
stocked as a subassembly
Many end items that are large and expensive are better schedule subassembly modules
when the same subassemblies appears in different end items.
A super bill of material includes items with fractional options.
Assembly Diagram and
Product Structure Tree
BOM Example (Determine requirements for all components to
satisfy demand for 50 Awesome Speaker Kits)
Amp-booster
Amp-booster
Schedule receipts
Projected available
balance
Planned order release
Order details
Counters
Keeping tracck
Example
X
B(2) C
Components On Hand
B 4
E(4) C 10
D 8
E 60
Use the information presented in figure to do following:
1. Determine the quantities of B,C,D,E and F needed to assemble one X
2. Determine the quantities of these components that will be required to assemble 10Xs taking into account
that quantities on hand (i,.e in inventory) of various components;
MRP Computer Program
MRP programs operates using information from the inventory record, the MPS, and BOM.
The process of calculating the exact requirements for each item managed by the system is
often referred to as the explosion process.
General Description of the MRP explosion
Process:
1. The requirement for level 0 items, typically referred to as end items, are retrieved from the master
schedule.
These requirement are referred to as gross requirements by the MRP program. Typically, the gross
requirements are scheduled in weekly time buckets.
2. The program uses the current on-hand balance together with the schedule of orders that will be
received in the future to calculate the net requirements.
3.Using the requirement, the program calculates when order should be received to meet these net
requirements.
4. Since there is typically a lead time associated with each order, the next step is to find a schedule
for when orders are actually released.
Offsetting the planned-order receipts by the required lead times does this, This schedule is referred to
as the planned-order release.
General Description of the MRP explosion
Process:
5. After those four steps have been completed for al the level zero items, the program moves to
level 1 items.
6.The gross requirement for each level 1 items are calculated from the planned-order release
schedule for the parents of each level 1 item
Any additional independent demand also needs to be included in the gross requirement.
7.After the gross requirement have been determined, net requirements, planned-order receipts,
and planned-order release are calculated as described in step 2 and 4.
8. This process is then repeated for each level in the bill-of material.
Example MRP
An Example Using MRP
Amper Inc. Produces a line of electric meters installed in residential buildings by electric
utility companies to measure power consumption.
Meter Used on a single-family homes are two basic types for different voltage and
amperage ranges.
In addition to complete meters some subassemblies are sold separately for repair or for
change overs to a different voltage or power load.
The problem for the MRP system is to determine a production schedule to identify each
item,
The period when it is needed and the appropriate quantities.
The Schedule is then checked for feasibility and the schedule is modified.
Forecast Demand
Future Requirements for meters A and B and Subassembly D stemming from specific
customer orders and from forecast.
Week
9 10 11 12 13 14 15 16 17
Meter A 1250 850 550
Meter B 470 360 560
Subassembly 270 250 320
D
Bill of Material Structure
A B
C(1)
C(1)
D(1)
D(2)
D(2)
Meter A Meter B
A B
D(1) C(1)
C(1) D(2)
D(2)
Inventory Calculation
Number of Units on hand and lead time data that would appear on the inventory record file
Lot sizes are the part quantities issued in the planned order receipt and planned order
release section of an MRP schedule.
For part produce in-house, lot sizes are the production quantities of batch sizes.
In an attempt to save setup cost, the inventory generated with the larger lot sizes needs to
be stored.
The lot-sizing techniques presented are lot-for-lot(L4L), economic order quantity(EOQ),
least total cost(LTC), least unit cost(LUC).
Example
Consider the following MRP lot-sizing problem; the net requirements are shown for eight
scheduling weeks
Cost per item $10.00
Order or setup cost $47.00
Inventory Carrying Cost/Week 0.5%
Weekly Net Requirement
1 2 3 4 5 6 7 8
50 60 70 60 95 75 60 55
Lot for Lot
(week) Net Production Ending Holding Cost Setup Cost Total Cost
Requirement Quantity Inventory
1 50 50 0 0 $47.00 $47.00
2 60 60 0 0 47.00 94
3 70 70 0 0 47.00 141
4 60 60 0 0 47.00 188
5 95 95 0 0 47.00 235
6 75 75 0 0 47.00 282
7 60 60 0 0 47.00 329
8 55 55 0 0 47.00 376
Economic Order Quantity
(week) Net Production Ending Holding Cost Setup Cost Total Cost
Requirement Quantity Inventory