Contract, Specification & Quantity Survey
Contract, Specification & Quantity Survey
Specification &
Quantity Survey
MeU, FoET, Dep't: CoTM, Lecturer: Ayansa K. (MSc. In Construction Engineering & Management) 2
4.1 Introduction
Project Cost estimation is the process of valuing on monetary
expression, including the cost of all possible entrants necessary
for the:
planning,
implementing and
monitoring stages of the proposed project under consideration.
MeU, FoET, Dep't: CoTM, Lecturer: Ayansa K. (MSc. In Construction Engineering & Management) 3
Introduction Ctd…
Project Cost includes:
Preliminary investigation (project appraisal costs);
Design and supervision (consultancy cost);
Construction works (contractor’s cost);
Land owning cost, and
Monitoring costs.
MeU, FoET, Dep't: CoTM, Lecturer: Ayansa K. (MSc. In Construction Engineering & Management) 4
Introduction Ctd…
An estimate serves a number of different functions,
depending on the stage of the project, as shown below :
Feasibility: Initially feasibility of the project need to be
determined Feasibility Estimate (Conceptual).
Schematic Design (Conceptual design): Sketches are prepared. Major
elements are defined. Use a preliminary method to estimate cost. Cost of
each element is established (cost plan).
Design Development: Progressively the scope of the project is defined. A
series of preliminary estimates are done during this phase to assure
adherence to cost plan.
MeU, FoET, Dep't: CoTM, Lecturer: Ayansa K. (MSc. In Construction Engineering & Management) 5
Introduction Ctd…
Contract Document: Finalize drawings and Specifications: Designer’s
estimate to anticipate and check contractor’s bid prices.
Bidding Phase: Contractors prepare detailed estimate to submit bids.
Construction Phase: Estimates are prepared for cost control and for change
order evaluations.
MeU, FoET, Dep't: CoTM, Lecturer: Ayansa K. (MSc. In Construction Engineering & Management) 6
Introduction Ctd…
Bidding environment;
Proper management;
Land charges (lease); and
Nature of subsurface condition.
MeU, FoET, Dep't: CoTM, Lecturer: Ayansa K. (MSc. In Construction Engineering & Management) 7
Introduction Ctd…
Estimation can be broadly classified as preliminary
(approximate) and detailed.
MeU, FoET, Dep't: CoTM, Lecturer: Ayansa K. (MSc. In Construction Engineering & Management) 9
Preliminary /approximate costing
Ctd…
MeU, FoET, Dep't: CoTM, Lecturer: Ayansa K. (MSc. In Construction Engineering & Management) 10
C. Cubical Content method – cost per m3
Based on cubical contents of various buildings,
MeU, FoET, Dep't: CoTM, Lecturer: Ayansa K. (MSc. In Construction Engineering & Management) 12
Analysis of the different rates for the quantities
prepared.
MeU, FoET, Dep't: CoTM, Lecturer: Ayansa K. (MSc. In Construction Engineering & Management) 13
2.1 Unit Rate Analysis
MeU, FoET, Dep't: CoTM, Lecturer: Ayansa K. (MSc. In Construction Engineering & Management) 14
2.1.1 Direct Material Unit Cost
(E)
MeU, FoET, Dep't: CoTM, Lecturer: Ayansa K. (MSc. In Construction Engineering & Management) 15
Direct Material Unit Cost Ctd…
MeU, FoET, Dep't: CoTM, Lecturer: Ayansa K. (MSc. In Construction Engineering & Management) 18
Direct Material Unit Cost Ctd…
MeU, FoET, Dep't: CoTM, Lecturer: Ayansa K. (MSc. In Construction Engineering & Management) 19
Direct Material Unit Cost Ctd…
MeU, FoET, Dep't: CoTM, Lecturer: Ayansa K. (MSc. In Construction Engineering & Management) 20
2.1.2 Direct Labor Unit Cost (F)
Labor index from his previous records and the labor market.
Annual leave;
MeU, FoET, Dep't: CoTM, Lecturer: Ayansa K. (MSc. In Construction Engineering & Management) 22
Direct Labor Unit Cost ctd…
MeU, FoET, Dep't: CoTM, Lecturer: Ayansa K. (MSc. In Construction Engineering & Management) 23
Direct Labor Unit Cost ctd…
MeU, FoET, Dep't: CoTM, Lecturer: Ayansa K. (MSc. In Construction Engineering & Management) 24
Direct Labor Unit Cost
Ctd…
MeU, FoET, Dep't: CoTM, Lecturer: Ayansa K. (MSc. In Construction Engineering & Management) 25
2.1.3 Direct Equipment Unit Cost (G)
MeU, FoET, Dep't: CoTM, Lecturer: Ayansa K. (MSc. In Construction Engineering & Management) 26
Direct Equipment Unit Cost
ctd…
MeU, FoET, Dep't: CoTM, Lecturer: Ayansa K. (MSc. In Construction Engineering & Management) 27
Direct Equipment Unit Cost
ctd…
MeU, FoET, Dep't: CoTM, Lecturer: Ayansa K. (MSc. In Construction Engineering & Management) 28
Direct Equipment Unit Cost
ctd…
MeU, FoET, Dep't: CoTM, Lecturer: Ayansa K. (MSc. In Construction Engineering & Management) 29
Direct Equipment Unit Cost
ctd…
MeU, FoET, Dep't: CoTM, Lecturer: Ayansa K. (MSc. In Construction Engineering & Management) 30
2.1.4 Site Overhead Cost (I)
MeU, FoET, Dep't: CoTM, Lecturer: Ayansa K. (MSc. In Construction Engineering & Management) 31
2.1.5 Head Office Overhead Cost
(J)
MeU, FoET, Dep't: CoTM, Lecturer: Ayansa K. (MSc. In Construction Engineering & Management) 32
2.1.6 Risk Allowance (L)
MeU, FoET, Dep't: CoTM, Lecturer: Ayansa K. (MSc. In Construction Engineering & Management) 33
2.1.8 Total Unit Price without VAT (N)
MeU, FoET, Dep't: CoTM, Lecturer: Ayansa K. (MSc. In Construction Engineering & Management) 34
2.1.9 Total Unit Price with VAT
MeU, FoET, Dep't: CoTM, Lecturer: Ayansa K. (MSc. In Construction Engineering & Management) 35
MeU, FoET, Dep't: CoTM, Lecturer: Ayansa K. (MSc. In Construction Engineering & Management) 36
Examples
MeU, FoET, Dep't: CoTM, Lecturer: Ayansa K. (MSc. In Construction Engineering & Management) 37
Examples Ctd…
MeU, FoET, Dep't: CoTM, Lecturer: Ayansa K. (MSc. In Construction Engineering & Management) 38
Examples Ctd…
MeU, FoET, Dep't: CoTM, Lecturer: Ayansa K. (MSc. In Construction Engineering & Management) 39
Examples Ctd…
MeU, FoET, Dep't: CoTM, Lecturer: Ayansa K. (MSc. In Construction Engineering & Management) 40
Examples Ctd…
MeU, FoET, Dep't: CoTM, Lecturer: Ayansa K. (MSc. In Construction Engineering & Management) 41
Examples Ctd…
MeU, FoET, Dep't: CoTM, Lecturer: Ayansa K. (MSc. In Construction Engineering & Management) 42
MeU, FoET, Dep't: CoTM, Lecturer: Ayansa K. (MSc. In Construction Engineering & Management) 43
MeU, FoET, Dep't: CoTM, Lecturer: Ayansa K. (MSc. In Construction Engineering & Management) 44
4.2 Risk Analysis for Cost
Estimation
MeU, FoET, Dep't: CoTM, Lecturer: Ayansa K. (MSc. In Construction Engineering & Management) 46
4.2.1 Inherent Risk in Construction
A) Inherent Risk
Inherent (range) Risk in the measured items (that have a 100%
likelihood of occurring) included within the various components
(direct costs, indirect costs, margin and owner’s costs ) of the
Base Estimate (such as Rates, Quantities, Assumptions, etc).
B) Contingent Risk
Contingent Risk being the risk attached to items outside the Base
Estimate (that have a less than 100% likelihood of occurring).
MeU, FoET, Dep't: CoTM, Lecturer: Ayansa K. (MSc. In Construction Engineering & Management) 47
Contingent Risk Ctd…
industrial issues,
safety, planning approval conditions,
design development,
owner requirements,
Risk Analysis:
MeU, FoET, Dep't: CoTM, Lecturer: Ayansa K. (MSc. In Construction Engineering & Management) 51
4.2.1 Why Risk Analysis in Cost
Estimates?
MeU, FoET, Dep't: CoTM, Lecturer: Ayansa K. (MSc. In Construction Engineering & Management) 53
4.3 Valuation
MeU, FoET, Dep't: CoTM, Lecturer: Ayansa K. (MSc. In Construction Engineering & Management) 54
4.3 Valuation
MeU, FoET, Dep't: CoTM, Lecturer: Ayansa K. (MSc. In Construction Engineering & Management) 56
4.3.2 Concept of Valuation
Value = Function/Cost
MeU, FoET, Dep't: CoTM, Lecturer: Ayansa K. (MSc. In Construction Engineering & Management) 57
4.3.2 Stages in Valuation
Planning:
Design:
- This is the stage that most VE participants are used to becoming involved,
when the design has at least made it to the schematic stage.
Construction:
- During this phase value engineering is still possible through the use of
Value Engineering Change Proposals (VECP).
- Contractors can be provided monetary incentives to propose solutions that
offer enhanced value to the owner, and share in the financial benefits
realized.
MeU, FoET, Dep't: CoTM, Lecturer: Ayansa K. (MSc. In Construction Engineering & Management) 59
Thank
You!
MeU, FoET, Dep't: CoTM, Lecturer: Ayansa K. (MSc. In Construction Engineering & Management) 60