Week 5 - Production Smoothing
Week 5 - Production Smoothing
Tran Van Ly
Industrial Engineering & Management
International University
Email: [email protected]
21/04/08 Room: A2-504 1
Recall previous week
Cycle time, Flow time, Setup/Changeover time
1.Determine takt time
2
Recall previous week
Calculate the following items:
Required run time/day: part A: = 250x40/60
=167min, part B=263min
Time required to meet demand: 167+263 =
430min
Available time for changeovers: 7.5x60x2 –
430-40 = 430 min
Number of changeover per day = 430/50 =8.6 =
8 or 9
(Calculating available time for changeover time
for individual product, it may underestimate)
3
Learning Objectives
Methods to minimize quantity variance in a
production line
Leveling
Batch Sizing
Sequencing
4
Why production smoothing?
Production smoothing: Minimize quantity variance
in a production line
Most important condition for JIT production
Production is promptly adaptable to demand
changes
quantity
1. Smoothing of Total Production
Quantity
To produce the same amount of products
every period
Allow daily production volumes to remain
constant despite demand varying (level the
total output in a month)
Have per month quantitative production
schedule based on demand forecast
divided by the number of operating days in
the month to get a daily production volume
Ex: Master production plan
divided into two-week intervals
Date 1 2 3 … 14 15 16 17 18 . 30 31
Production 250 245 245 … 250 250 205 200 200 . 205 205
quantity
Total no. of 54 54 54 54 54 44 44 44 . 44 44
workers
Cycle time 120 120 120 .. 121 121 140 144 144 . 140 140
What-if
If the quantity of demand within a month is not
constant?
The shorter the period of a master production plan,
the better for executing smoothing of the total
production quantity
However, time span of the master production plan
also cannot be too short, else smoothing of the total
production quantity will disappear
Adapting to increased demand
Use early attendance & overtime
Improvements within each process also produce extra
time
Adapt operation according to monthly schedule for
average daily production
Example:
Load on machine ordinarily is set 90% of its full capacity,
each multifunctional worker handle 10 machines
When demand increases, temporary workers are hired,
each handles less than 10 machine, utilizing 100%
machine capacity
Adapting to decreased demand
• In parts manufacturing processes, the number of machines
handled by each worker increase
• On the assembly line, cycle time will increase due to reduce
demand quantity
• Developing standardized work in advance for different takt
scenarios
• Let extra workers involve other activities than to produce
unnecessary stock
Activities may be organized
during a slack period
Transfer workers to other lines for which demand
increases
Decrease overtime
Use a paid holiday
Conduct quality control circle meetings
Practice set-up actions
Conduct maintenance and repair of machines
Manufacture improved tools and instruments
Conduct plant maintenance and upkeep
Manufacture pars previously purchased form
suppliers
2. Smoothing each model’s
production quantity
What would happen if the final assembly line
produced one type of product all day long?
Volume: Takt time
Style?
Example - Leveling
1824 units/month; 16 work days/month
One shift per day (6am-4:30pm) 30
minutes lunch, 2x15 minutes break
1824/16 = 114 units/work day
10.5*60-60 = 570 minutes/work day
Takt time = 570/114 = 5 minutes
If there are three styles A, B and C (56,
29 & 29 respectively per day)
If build in complete batches
Production Sequence:
A1 to A56 then B1 to B29 then C1 to C29
And then ship out product
Inventory! Finished goods and WIP!
Where is the waste
If cycle time of A, B, C is 10. 20 & 40 minutes
Extra Unit(s) F FG FG FG K
Exercise 2: Batch size
1. Total 1-shift production time available (excluding break time) is 7.5 hours.
There are 2 shifts per day. Average downtime per day (not included change
over time) is 40 minutes. Determine the available time for changeovers per day
and the desirable number of changeovers per day
B 350 45 50
Determine best batch sizes
Exercise 3: Batch sequence
B 4,800 120 4’
C 2,400 60 8’
Units
Ideal parts consumption
Production sequence
Supporting smoothed production
Flexible machinery
Flexible manufacturing system (FMS)
Why production leveling/
smoothing?
- Shorter lead time
- Smaller finished goods & WIP inventory
- Balance use of labor and machines
- Help determine personnel, equipment,
material needs
- Smoothed demand on upstream
process & suppliers
HEIJUNKA
(Load smoothing)
Objective:
Low WIP small batch size more number of
batches more number of setups
(Heijunka requires scrambling of parts)
Determine:
Time
Working time No. of shifts per No. of machine Total working time Total available time
Time per shift day allocated per day (min)
Efficiency
per day (min)
AC B C B C AC B C B C AC B C B C etc…
Objective : Maximize nA+nB+nC
Constraints:
(SACut* nA) + (SBcut* nB) + (SCCut* nC ) Total
setup time available for Cut
(SAMold* nA) + (SBMold* nB) + (SCMold* nC ) Total
setup time available for Mold
(SAAssembly* nA) + (SBAssembly* nB) + (SCAssembly* nC )
Total setup time available for Assembly