GTCL Foundation Training
GTCL Foundation Training
Pipeline Design
Pipeline Construction Process
Welding inspection and Quality Control
Overview of Gas Industry in Bangladesh
Upstream : Exploration and Production of Natural Gas
National: BAPEX, BGFCL, SGFL
IOC: Chevron, Tullow, Santos(Cairn Energy)
Midstream : Transmission of Natural Gas
GTCL
Downstream: Distribution of Natural Gas
TGTDCL (Dhaka area)
BGSL (Commilla Area)
KGDCL (Chittagong area)
JGTDCL (Sylhet area)
PGCL( West zone)
Sundarban Gas Co. Ltd. (Khulna)
Pipeline Design
Many intricacies are involved in designing a modern
pipeline system.
Amount of FLOW that must flow through the pipeline
is one of the first items of information required.
BUT
Future capacity requirements are difficult to estimate.
Pipeline Design (contd.)
1. Market survey- Present & Future demand
2. Design Pressure & MAOP ( 1050 Psig )
3. Select pipeline route (L)
4. Pipe Size (D)
5. Wall thickness (t)
. 6. Pipe specification / grade
7. Bill of materials
8. Total cost estimate
Pipeline design ( contd.)
1. Load consideration:
Amount of FLOW that must flow through the pipeline
is one of the first items of information required. BUT
Future capacity requirements are difficult to estimate.
In earlier days , pipeline design was done considering
the present load and 15 to 30% increment of load.
Now-a-days, the use of natural gas increased
tremendously. As a result the concept of pipeline
design has also changed.
Presently pipeline design is being done considering the
present load as well as the assumed gas load of the that
particular area for the next 20 years ( effective life of
the pipeline)
General Guideline for Pipeline Routing
Panhandle B equation-
Q= 737 (Tb /Pb)1.02 * ((P12-P22)/ (G0.961 * Tavg * Z*L )) 0.51 * D2.53
where , Q =Flow in SCFD
P1=Upstream pressure, PSIA
P2=Downstream pressure, PSIA
d =Inside pipe dia , inch
Basic Flow Equation (contd.)
t= DP/(2YFL JT)
where,
t=Pipe wall thickness in inch
D=Outside dia of pipe in inch
P=design pressure ,psig
Y=minimum yield strength, psig
F=design factor
L= Location factor based on class location
J= Joint factor
T=Temp. derating factor
Line Pipe: API 5LX , (Y factor)
Grade Minimum yield
strength( Psi)
A 35,000
B 40,000
X42 42,000
X46 46,000
X52 52,000
X56 56,000
X60 60,000
X65 65,000
X70 70,000
X80 80,000
Design Factor (F)
ERW 1
SAW 1
Up to 250 1.00
251-300 0.97
301-400 0.93
401-450 0.91
Up to 250 1.00
251-300 0.97
301-400 0.93
401-450 0.91
.
Pipeline design problem # 02
Suppose, a new gas field is discovered in Rangpur district
through 3D seismic survey by the national Exploration
Company BAPEX. The proven reserve of the field is 1 TCF. It
takes approximately 2 years to develop the field. Now, the
Govt. has decided to create a gas supply facility for the people of
energy hungry Khulna Division. Design a pipeline based on the
above information .
.
Pipeline design problem # 02
A new gas field is discovered in Rangpur district through 3D
seismic survey by the national Exploration Company BAPEX.
The proven reserve of the field is 1 TCF. It takes approximately
2 years to develop the field. Now, the Govt. has decided to
create a gas supply facility for the people of energy hungry
Khulna Division. Design a pipeline to transport gas from
Rangpur to Khulna .
( Hints: Distance from Rangpur to Khulna is 250 Km.
Assume 90 % of the proven reserves is recoverable . Again,
assume within 20 years all the recoverable reserves will be
produced. MAOP of the transmission pipeline is 1050 Psig.
Assume, outlet of the process plant is equal to the MAOP.
Assume , frictional loss along the pipeline is 1 psig/km
Qmmscfd = 1 * 1,000,000 * .90 /(20 * 365 ) MMSCFD= 123 MMSCFD )
Pipeline Construction Process
PDPP
DPP
Route selection
Land acquisition & Requisition
Tender Document Preparation
Tender Floating
Evaluation
Contract Award
Procurement/ Construction
Pre construction (Contd.)
Radiography Test
Equipment
Method
Source
Method
Source
Weld examination
Common welding defects
Porosity
Cluster porosity
Slag inclusion
Lack of fusion
Lack of penetration
Internal concavity
Burn through
Crack
UNDERCUT
POROSITY
INCOMPLETE FUSION
SPATTER
EXCESSIVE CONCAVITY
EXCESSIVE WELD REINFORCEMENT
INCOMPLETE PENETRATION & EXCESSIVE PENETRATION
Tie-in welds (contd.)
3LPE coating
-Apply adhesive on clean pipe surface
-Epoxy paint ( 40-100 micron)
-Polyethylene coating
Joint coating (contd.)
Heat shrink sleeves
-Approx. 14 inch length and dia larger than pipe dia.
-Shrink on applying heat and fitted to the pipe.
Joint Coating (contd.)
1. Write down the name of two equipments that are used in Clearing the
ROW.
2. Write down the name of two equipments that are used during welding.
3 . Write the name of two inspection tools that are used during coating
inspection.
4. Write down the name of two weld inspection tools.
5. Write down the name of 3 equipments/ tools that are used during
hydrostatic testing.
6. Write down the name of 3 common welding defects.
7. When Pull throw is done during pipeline construction process? Why it is
done ?
8. Elaborate the term ROW.
9. The term Holiday inspection is related to NDT / welding/coating/
Hydrotest.
Thanks for the patience !