Technology Management Tools: S-Curve
Technology Management Tools: S-Curve
management tools
S-CURVE
TM Tools S-Curve
Introduction
An S Curve is graphed on an X-Y graph with the XX axix representing time, and Y axis
representing a quantity, usually man hours or costs. The three basic types of SS-Curves include
here are
S- Curve quantities
Each of the previous S Curves may include one or both of the following quantities on
the quantity (Y) axis:
Main hours
Costs
S- Curve quantity units
In addition, each of the above S Curve may use one of the following units for the
values of the quantity (Y) axis:
Absolute values for man hours and/ or costs
Percentage values for man hours and / or costs
The Baseline S Curve
The cut of date is the date on which the tasks were physically inspected to
determine their percentage complete values. For example, if the task were
inspected on Thursday the 3rd of may 2012, the production schedule was updated
on Friday the 4th of may 2012, and the actual S Curve was generated on Saturday
the 5th of may 2012, the Cut Off date should be set to Thursday the 3 rd of may
2010.
At the completion of the project, with all tasks 100% complete, the Actual S
Curve will terminate at the project completion date, and be identical to the Target
S Curve. The Actual S Curve will usually change over the duration of the project
due to changes to task start and finish dates, man hours and / or costs, and
percentage complete to date.
Changing the cut off date after the production
schedule has been updated
If the Actual S Curve is to be accurate, the cut off date must be set to the date the
project’s tasks were physically inspected. In the following figure, the project's
tasks were physically inspected on the 3rd of may 2012. This is the cut off date
that should be used when generated the Actual S Curve.
The Man hours verses Time S Curve
The man hours verses time S Curve is appropriate for projects that are labor
intensive. It shows cumulative man hours expended over time for the duration of
the project. As man hours are a product of man power and working hours, these
may be adjusted together or individually in an attempt to keep the project on
track. Projects may require additional man hours to finish on time due to low
productivity, weather or other delays and disruptions, rework, variations, change
of scope, etc.
The Costs verses Time S Curve
The costs verses time S Curve is appropriate for the projects that contain labor
and non-labor (e.g. material supply / hire / subcontract) tasks. It shows cumulative
costs expended over time for the duration of the project, and may be used to assist
in the calculation of the project’s cash flows, and cost to complete.
Types of the Costs verses Time S Curve
Value S Curves
Value S curves are useful for determining the project’s man hours or costs expanded
to date, and man hours or costs to complete.
Why use S Curve?
S Curves are an important project management tool. They allow the progress of a
project to be tracked visually over time, and from a historical record of what has
happened to date. Analysis of S Curves allows project manager to quickly
identify:
Project progress
Project growth or contraction (Man hours and / or costs, Duration)
Project start and / or finish slippage
Determining project progress
Comparison of the Target S Curve and Actual Curve reveals the progress of the
project over time. In most cases, the Actual S Curve will sit below the Target S
Curve for the majority of the project, due to many factors.
Only towards the end of the project will the curves converge and finally meet.
Although the Actual S Curve may sit above the Target S Curve for a period during
the project, it can never finish above the Target S Curve at project completion.
Determining Slippage
Slippage is defined as “the amount of time a task has been delayed from its
original baseline schedule. The Slippage is the difference between the schedule
start or finish date for a task and the base line start or finish date. Slippage can
occur when baseline plan is set and the actual dates subsequently entered for tasks
are later than the baseline dates or the actual durations are longer than the baseline
schedule durations”.
Start Slippage
Start slippage occurs when thee estimated / actual start date of the project / task is
later than the baseline start date. In other words, the project / task has started later
than planned.
Finish Slippage
Finish Slippage occurs when the estimated / actual finish date of the project / task
is later than the baseline finish date. In other words, the project / task will finish /
has finished later than planned.