Sub Structure Construction
Sub Structure Construction
Sub Structure Construction
Foundation
• Sub - Structure or Foundation is the lower most portion of
the building, usually located below the ground level, which
transmits the load of super structure to the supporting soil.
• A foundation is therefore that part of the structure which is
in direct contact with the ground to which the load are
transmitted.
Purpose of foundation
• To distribute the total load coming on the structure on a
larger area.
• To Reduce the load Intensity
• To support the structures.
• To give enough stability to the structures against various
disturbing forces, such as wind and rain.
• To prepare a level surface for concreting and masonry
work.
• For the Lateral Stability.
Types of foundation
1. Open Foundation.
2. Shallow Foundation
•Wall footing ,
•Reinforced concrete footing
•Column footing
1. Isolated
2. Combined
3. Raft foundation.
3. Deep foundation
•Pile foundation ,
•Well foundation,
•Coffer dams.
1.Open Foundation
• This is simply a layer of foundation concrete provided at the
base of a column, pedestal or wall.
• This type of foundation is provided when hard stratum is
available at very shallow depth or the work is unimportant e.g.
Compound wall, pillars for barbed wire fencing etc.
• As the name suggests, open foundations refer to those
foundations constructed by carrying out excavations up to
founding level in the open conditions. When suitable founding
strata or rock exposed in bed or hard strata are available at
shallow depths, the excavations may by done entirely in the dry
condition.
2.Shallow Foundation
• When the foundation is placed immediately below the
lowermost part of structure it is called as Shallow foundation.
• It can also be defined as, when the depth of foundation is less
than or less than equal to the width;, the foundation is called
as Shallow Foundation
Purpose:
The purpose of shallow foundation is to distribute the
structural load over considerable horizontal area
Limitation:
The load carrying is considerably less as compared with deep
foundation. Can not be used under marshy land, made up of
ground water or water logged area.
Stepped Foundations
• Stepped foundations: In this case , the base of the
foundation is made wider to distribute the load on wider
area .
A)Wall footing :
1. It can be achieved by constructing several courses of
bricks widening the base, the lowest course is usually
twice the breadth of the wall.
2. The sectional elevation of brick wall footing is shown.
B) Reinforced Concrete Footing :- When the bearing capacity
of the soil on which the wall footing is to rest is very low and
when the walls are subjected to heavy loading , under such
circumstances, the reinforced concrete footing is used
C) Column footing:
1. Isolated : It is provided under a column or other similar
member for the distribution of concentrated load in the form of
uniformly distributed load on the soil below. The shape may
be square, rectangular or circular in plan . It may be
constructed either in brick masonry , stone masonry or R.C.C.
steel grillage etc.
2. Combined Footing:
•Combined column footing is provided as a common footing
for two or more columns.
•This type of column helps in reducing the depth of foundation
and unequal settlement can be avoided.
•In this type of footing, a common P.C.C bed is provided on
which two or more column rest.
•Combined footing is also provided when column are very
near to each other and isolated column will over lap each
other.
•Shear force calculation is
important in combined footing
D) Raft Foundation :-
•When bearing capacity of the supporting soil is very low and
heavy concentrated structural loads are to be supported in case
of marshy land or made of soft clay.
•It proves to be economical under water logged area.
•Raft is acting as a floor consisting of thick reinforcement
concrete slab covering the entire area of the bottom of the
structure.
3. Deep foundation
• When the depth of foundation is more than its width the
foundation is called as DEEP foundation.
• It can also be defined as , if the depth of foundation is more
than 2.00 m, it called as deep foundation.
Types of Deep foundation
1) Piles
a). Depending upon the function :-
•1. Bearing piles
•2.Friction piles
•3.Sheet piles
•4.Anchor piles
•5.Batter piles
•6.Fender piles
•7.Compaction piles
1. Bearing Piles: These are driven into the ground until a hard
stratum, directly supported on hard base and pile act as pillar
to transmit the load.
1.Timber pile
• Economical for supporting light structures
• Timber from sal, deodar , babul , khair, is used .
• the pile cap of iron ring of about 25 mm is provided to prevent
the pile head from brooming .
• The lower end of the pile is provided with a cast iron conical
shoe.
• The load transfer mechanism is by skin friction hence there
should a minimum distance of about 60 cm center to center
ADVANTAGES:
• Economical.
• Can be driven rapidly hence saves time.
• Due to its elasticity it is recommended in region
where the piles are likely to be subjected to lateral
forces
• Heavy machinery and skill supervision is not required.
DISADVANTAGES:
• Should be cut of above ground water table to prevent
decaying.
• Timber cannot be driven in filled up ground.
• Likely to decay by salt water or insect.
• Restricted length .
2. Concrete Pile
Concrete piles are classified as :-
1.Pre-cast piles.
2.Cast in – situ pile.
3.Pre-stressed concrete pile
1.PRE-CAST CONCRETE PILE:
•Precast piles are those which are manufactured in the factory or at
a place away from the construction site and then driven to the
ground at the place required.
•Pre cast pile may be square ,octagonal, or round in cross section
or may be tapering or parallel in longitudinally. The size of these
piles varies from 30cm to 50cm in cross sectional dimension and
up to 30m in length .
•Precast pile are useful in carrying fairly heavy loads through
soft material to firm strata .
2. CAST IN – SITU PILE :
•The piles which are cast in position on site inside the ground , it
may be reinforced when pile act as column and when subjected to
lateral force.
•Normally the cast in situ piles are constructed with an enlarged
bulband corrugated stem.
•A steel tube having internal diameter equal to the diameter of the
pile and 20mm thickness is driven into the ground
•when the has been driven up to the desired depth a charge of
concrete is poured and the tube is gradually withdrawn and thus
alternate pouring and withdrawing of tube , the pile is constructed to
the full length.
•In case the pile is to be reinforced , the reinforcement cage is
lowered in the steel tube before pouring the concrete.
3. PRE – STRESSED CONCRETE PILES :
Pre stressed piles are stronger than the normal reinforced pile .
Therefore , because of the reduction in cross sectional, they are lighter
and more easily handled.
Advantages of concrete piles :
• It has greater ability to withstand extremely hard driving.
• It more durable in sea water because of the crack.
• It has great column
• It has lesser handling cost because of light weight.
• It has much lager moment of inertia then the
• conventional pile of the same dimension .
Disadvantages of Concrete piles :
• These piles cannot be driven rapidly.
• It requires skilled technical supervision heavy driving
machinery.
• To withstand handling stresses, reinforcement is essential.
3.Steel Pile
• A steel pile may be a rolled section , a fabricated shape or
a piece of sheet piles
• Metal piles have been used in from of cast iron
pipes or solid wrought iron shaft .
• These piles are excepted to penetrate through hard rock.
• Types of steel pile are H-piles, Pipe-pile, Screw Pile, Disc
Pile.
• The pipes is normally filled with concrete and the
diameter varies from 25cm to 125 cm and the depth is
30m or more.
2.Well foundation
Caisson is a foundation which comes under the type of well
foundation.
•The caisson is a structure used for the purpose of placing
foundation in correct position under water.
•It is Permanent in nature.
•Used to pump out water in under water concreting work.
1. Open Caisson
• Open caisson is a box of timber, metal, reinforced concrete
or masonry
• Open at both end (top and bottom)
• Whenever consideration for scour or bearing capacity
required foundation being taken to depth of more than 5 to
7m
• Costly and uneconomical (heavy timbering required)
• Due to greater earthwork, the progress of work is very slow
2.Box Caisson
• A box caisson opened at top and closed at bottom.
• It is Made up of timber, concrete or steel.
• Built on land and floated to pier site where it is sunk
in position
• Used where bearing stratum is available and loads
are not heavy
3. Pneumatic caisson
A pneumatic caisson is a watertight box or cylinder-like
structure that is closed at the top and open at the bottom, resting on
the bed of the waterbody. They are used for underwater
construction of foundations for bridge piers, abutments in rivers,
and foundations for large multi-story buildings
4. Floating caisson
Floating caissons are also known as floating docks and are
prefabricated boxes that have cylindrical cavities
This type of caisson often is used in the construction of
bridge piers. The caisson is constructed on land of concrete, steel,
wood, or some other material and floated to its intended position in
a river, lake, or other body of water. The caisson then is filled with
gravel, concrete, or some other material and allowed to sink to the
river bed. The filled caisson then becomes the lowest portion of the
new bridgepier.
3. Cofferdams
• DEFINITION: It is a temporary structure constructed in a
river or lake or any other water bearing surface for
excluding water from a given site to enable the water
building operation to be performed under dry conditions.
walls are water tight
• Temporary structure
• Built within or in pairs across a body of water
• Allows the enclosed space to be pumped out ,creating a
• dry work environment.
Types of cofferdams
1. Earth filled cofferdams
2. Rock filled cofferdams
3. Sheet pile cofferdams
•Single wall cofferdams,
•Double wall cofferdams.
1. Earth filled Cofferdams
• Earthen cofferdam consist of earthen embankment built
around the area to be enclosed.
• It can be constructed if the water depth is more than 1.4
to1.8m and the velocity of the flowing water is very
low.
• Top width of the dam should not be less than 1.00m
and the side slope may vary from 1:1.5 to 1:1.2. the
inner portion called as embankment consist of clay and
sand or clay or gravel
2.Rock Filled cofferdams
• In case of a rock filled cofferdam , the depth of water to be
retained is of order of 1.8 to 3.00m .stone or rubble is used
for embankment
3. Sheet pile cofferdam
1.Single wall cofferdams
•If the area to be enclosed is very small and the depth of water
is about 4.5 to 6.0m then timber piles known as guide piles
are first driven deep into the firm ground below the river bed,
the distance between the piles may vary from 1.7 to 3.5m
depending upon the velocity of the flow.
•Then Wales are bolted to guide piles at suitable distance
•Then sheet or wooden sheet piles are driven into the river
bed along the Wales and secured by bolts to the Wales.
•Thus , the area can be enclosed and the water is pumped out
to start the construction in dry condition.
Single wall cofferdams
2. Double walled cofferdam
• If the area to be enclosed is very large and if the depth
of water is large then double wall cofferdam are used
instead of single wall cofferdam.
• The construction is same , only in case of a single wall
a pair of wall with a gap between is provided.
• This is suitable up to a depth of 10 to 12.0m
• To prevent leakage the sheet piles are firmly driven
into the ground.
Double walled cofferdam
Dewatering of foundation by
Pumping Method
• For Water Logged Foundation It Is Essential To
Carry Out Dewatering Of Soil Before Carrying
Construction Activity.
• Methods Of Dewatering
1. Sumps and Ditches
2. Well Point System
3. Deep well System
4. Vaccum Method
1. Sumps and Ditches
• This is the simplest form of dewatering used in shallow
excavation in coarse grained soils.
• Sallow low pits ,calls as sumps are dug along the periphery of
the area drainage ditches.
• The water from the slope or sides flows under gravity and is
collected in sumps from which it is pumped out.
2. Well point Systems
• A well point system is a perforated pipe of 5 to 8 cm in diameter
and one metre long covered by cylindrical wire gauge screen
known as STRAINER.
• These pipes are joined to a horizontal pipes known as HEADER
pipe.
3. Deep well system :-This system is suited when the
depth of excavation is more than 16m.
4. Vacuum Method
• In this method a hole of 30cm diameter is bored around
the well point and the riser pipe.
• It then sealed using bentonite, soil- cement or clay. The
header pipe is then connected to vacuum pump for
removal of water.
Special Foundation
• These foundations are provided when the bearing
capacity of the soil is low and hard strata is not
available on the given site.
• The most commonly constructed special foundation
are 1. Mat or raft foundations , 2.Under-reamed piles .
Under- Reamed Piles
• The under reamed piles are the best solution for foundation
• black cotton soil.
• Bored cast in situ concrete piles having bulb shaped enlarge
base
• Such structure is anchored to the ground at depth where ground
movement due to change in moisture content negligible
• Bearing capacity increased by increasing the number of bulbs
• Hand auger or machine auger used for boring with extension
• rod
• After boring upto certain depth the base of hole is enlarged in
the form of bulb
Under- Reamed Piles
Setting out of foundation
1.Site Clearance
•Site Clearance is an important factor to be considered in the job
layout plans , before commencement of project work
•There should not be any obstruction like trees , plants , shrubs,
bigger size stones, etc.
• Approach road should be wide so as to allow the truck
for loading and unloading the constructional material .
If site ground is uneven , then it should be made plane ,
for this contouring is done in advance.
• In short site should be cleared by all the way, otherwise
no activity can be launched in construction processes.
2. Preparing Job Layout
1. A plan in which the arrangements for placing site office,
store room , labour quarter, medical aid center, godowns
for keeping construction materials and other facilities are
properly prepared is called as Job layout or site layout .
2. The arrangements for processes should be such that the
work is done smoothly and in orderly manner.