Project Cost Management
1
Outline
Cost management processes
Resource planning
Cost estimating
Cost budgeting
Cost controlling
2
What is Cost and Project Cost Management?
Cost is a resource sacrificed or fore-gone to achieve a specific
objective or something given up in exchange
Costs are usually measured in monetary units like birr, dollar, etc
Project cost management includes the processes required to
ensure that the project is completed within an approved budget
Project managers must make sure their projects are well defined, have
accurate time and cost estimates and have a realistic budget that they
were involved in approving
33
Project Cost Management Processes
1. Resource planning: determining what resources and quantities
of them should be used
2. Cost estimating: developing an estimate of the costs and
resources needed to complete a project
3. Cost budgeting: allocating the overall cost estimate to
individual work items to establish a baseline for measuring
performance
4. Cost control: controlling changes to the project budget
4
Cost of Software Defects
Phase of Software Development Relative Cost to Repair Defects
Requirements and Analysis 1
Coding and Unit Test 5
Integration and System Test 10
Beta Test 15
Post-Product Release 30
NB: is a normalized unit of cost and can be expressed in dollars, person-hours, et.
It is much more cost-effective to spend money on defining user
requirements and doing early testing on IT projects than to wait
for problems to appear after implementation
If it would cost $1,000 to repair a software defect in the
requirements and analysis phase but it would cost $30,000 to
5
fix it in the post-product release phase
Resource Planning
The nature of the project and the organization will affect
resource planning
Some questions to consider:
How difficult will it be to do specific tasks on the
project?
Is there anything unique in this project’s scope
statement that will affect resources?
What is the organization’s history in doing similar
tasks?
Does the organization have or can it acquire the
people, equipment, and materials that are capable and
6 available for performing the work?
Cost Estimating
An important output of project cost management is a
cost estimate
There are several types of cost estimates, and tools
and techniques to help create them
It is also important to develop a cost management plan
that describes how cost variances will be managed on
the project
7
Cost Estimation Tools and Techniques
3 basic tools and techniques for cost estimates:
Analogous or top-down: use the actual cost of a
previous, similar project as the basis for the new estimate
Bottom-up: estimate individual work items and sum
them to get a total estimate
Parametric: use project characteristics in a mathematical
model to estimate costs
8
Typical Problems with Cost Estimates
Developing an estimate for a large software project is a complex
task requiring a significant amount of effort. Remember that
estimates are done at various stages of the project
Many people doing estimates have little experience doing them.
Try to provide training and mentoring
People have a bias toward underestimation. Review estimates and
ask important questions to make sure estimates are not biased
Management wants a number for a bid, not a real estimate. Project
managers must negotiate with project sponsors to create realistic
cost estimates
9
Cost Budgeting
Cost budget involves allocating the project
cost estimate to individual work items and
providing a cost baseline.
10
Cost Control
Project cost control includes
monitoring cost performance
ensuring that only appropriate project changes are included
in a revised cost baseline
informing project stakeholders of authorized changes to the
project that will affect costs
Earned value management is an important tool for cost
11 control
Earned Value Management (EVM)
12
Earned Value Management (EVM)
EVM is a project performance measurement
technique that integrates scope, time, and cost data
Given a baseline (original plan plus approved
changes), you can determine how well the project is
meeting its goals
You must enter actual information periodically to use
13 EVM.
Earned Value Management
Earned Value Analysis is an industry standard way to:
measure a project’s progress,
forecast its completion date and final cost, and
provide schedule and budget variances along the way.
By integrating three measurements, it provides consistent,
numerical indicators with which you can evaluate and
compare projects.
14
EMV enables
1. Knowing where you are on schedule?
2. Knowing where you are on budget?
3. Knowing where you are on work
accomplished?
15
Earned Value Management Terms
Planned value (PV), formerly called the budgeted cost
of work scheduled (BCWS), also called the budget, is
that portion of the approved total cost estimate planned
to be spent on an activity during a given period
Actual cost (AC), formerly called actual cost of work
performed (ACWP), is the total of direct and indirect
costs incurred in accomplishing work on an activity
during a given period
Earned value (EV), formerly called the budgeted cost
of work performed (BCWP), is the percentage of work
actually completed multiplied by the planned value
16
Earned Value Formulas
TERM FORMULA
Earned Value EV = BAC Percent Completed
Cost Variance CV = EV – AC
Schedule Variance SV = EV – PV
Cost Performance Index CPI = EV/AC
Schedule Performance Index SPI = EV/PV
To estimate what it will cost to complete a project or how long it will take based
on performance to date, divide the budgeted cost or time by the appropriate
index.
17
Rules of Thumb for EVA Numbers
Negative numbers for cost and schedule variance indicate
problems in those areas.
The project is costing more than planned or taking longer than planned
Zero variance shows that the project is running according to the plan
CPI and SPI > 1.0 indicate exceptional performance
CPI and SPI < 1.0 indicate poor performance
If CPI or SPI = 1, it shows that the project is performing according to
its plan
18
Example
Suppose you have a software project which is planned
to be completed in 9 months with a budget of Birr
900,000.
After a month,10% of the project is completed at a
total expense of Birr 100,000, but the planned
completion was 15%.
Given:
Budget At Complete (BAC) = Birr 900,000
AC = Birr 100,000
19
Compute
a) PV
b) EV
c) CV - interpretation
d) SV - interpretation
e) CPI - interpretation
f) SPI - interpretation
g) Forecast -Budget at complete
h) Forecast - Time at complete
i) Overall project’s traffic light status
20
…solution
a) Planned Value = Planned Completion (%) * BAC
= 15% * Birr 900,000
= Birr 135,000
b) Earned Value = Percent Completed (%) * BAC
= 10% * Birr 900,000
= Birr 90,000
21
…continued
CV = EV – AC The project is
costing more
= 90,000 – 100,000 than planned
because CV is
= -10,000 less than zero.
SV = EV – PV
= 90,000 – 135,000 The project is
= - 45,000 taking longer
than planned
because SV is
less than zero.
22
…continued
CPI= EV / AC
= 90,000 / 100,000
It shows Poor
= 0.90 Performance
SPI= EV/PV because CPI
and SPI are
= 90,000 / 135,000 less than one.
= 0.67
23
Forecasting Cost
If the project continues at the current
performance, what is the true cost of the
project?
Estimate at Complete
= Budget at Complete (BAC) / CPI
= Birr 900,000 / 0.90 = Birr 1,000,000
At the end of the project, the total project
cost will be Birr 1,000,000
24
Forecasting Time
If the project continues at the current
performance, what is the true time of the
project?
Estimate at Complete
= Original Time Estimate / SPI
= 9 months / 0.67 = 13.43 months
The project will be completed by the end
of 13.34 months.
25
Establish Ranges to Guide Traffic Light
Status
Traffic light status is useful in conveying overall
project’s status with one color
Establish objective SPI and CPI ranges to determine
the true project color.
Average of CPI & SPI i.e. (CPI+SPI)/2
Green [1.0 - 0.95] Good
Warning
Yellow [0.94 - 0.85] Bad
26
Red [0.84 - 0]
Therefore, for the above example,
overall project’s traffic light status is
= (CPI+SPI)/2
= (0.90+0.67)/2
= 0.78 Bad
27
?
Many
28
thanks!
QUIZ-2(5%)
1) Write all project cost management process?
2) How did you understood Earned value management(EVM) in cost
project management?
3) Suppose you have a software project which is planned to be
completed in one year with a budget of Birr 500,000.After a half
month,15% of the project is completed at a total expense of Birr
100,000, but the planned completion was 20%.
So, calculate:
a) PV ?
b) EV ?
c) CV ?
d) SV ?
29