Progress Status Report Aug, 2020: Project Overall
Progress Status Report Aug, 2020: Project Overall
00 5%
Project Overall
Elapsed Days Planned Completion Date: 31 st May 2021
Remaining Days 36% Actual Completion Date: 23 June 21
160
160 Elapsed Days: 389 D
480 Delays 58%
Remaining Days: 304 D
Total Delay: 23 D
320
3%
Phase 1
elapsed days
Planned Completion Date: 31 st Mar 2021
Actual Completion Date: 15 Apr 21
Remaining Days
43%
55%
Elapsed Days: 386 D
delay
Remaining Days: 227 D
Elapsed Days Remaining Days Total Delay Total Delay: 45 D
389 D 304 D 23 D
1%
Phase 2
Elapsed Days Remaining Days Planned Completion Date: 31 st May 2021
Actual Completion Date: 23 June 21
Delays
49% 50% Elapsed Days: 389 D
Remaining Days: 304 D
Total Delay: 23 D
ABC Building Progress Outlook
Progress Status Report
Aug, 2020 ABC Building Project
Engineering Construction
90,000,000.00
Progress Status Report 80,000,000.00 Earned Value
8,000,000.00 80,000,000.00
Aug, 2020 Acc. PV
7,000,000.00 Acc. EV 70,000,000.00
60,000,000.00
6,000,000.00 60,000,000.00
40,000,000.00 5,000,000.00 50,000,000.00
Work 20,000,000.00
4,000,000.00
3,000,000.00
40,000,000.00
30,000,000.00
Performance -
PV EV 2,000,000.00
1,000,000.00
20,000,000.00
10,000,000.00
- -
89.3% 1.00
1.00
Planned Schedule Performance Line
0.97 0.97
0.94
Planned Value 0.94 0.93
0.92
89,352,170.4 0.91 0.91
0.90
0.91
0.89 0.89 0.89 0.89
0.88
0.87
0.85
81.8%
Completed
The Project is behind the schedule according to the comparison
Earned Value SPI made to the accumulative planned value against the
accumulative earned value from the project start up to this
81,842,008.4 0.92 update. However, the performance line is showing that there
was a trend for a good performance during the last 4 months.
ABC Building
Progress Status Report
Aug, 2020
Progress Narrative
100% Excavation work completed on 20 Aug 19, and the work moved to piles execution
on 21 Aug 19
Piles Execution has completed 100% on 11 Nov 19. 1050 Pile achieved within 90 days
In 12 No 19, the structural Skelton works have been started, and up to date, the progress
of the structure works recorded 100% work done in phase 1. Structure works for phase
2
recorded 85%. The structure works for annex building still under progress with about
25% Achievement.
30,000 m3 Concrete has been casted & 3000 Tone of steel rebar have been
fixed and assembled.
Block works started on 10 Jan 20 and 97% completed up to date
Water Proofing Activities are running in parallel with the concrete works. For foundation , it
is estimated that 95% of the WP works are completed.
Electrical works started on 16 Jan 20 in phase 1, the work started by installing the
conduits and cable tray for in the ground floor, and the work achieved up to date is almost
95% in phase 1.
Electrical Work has reached to the stage of installing cables and wires in phase 1 & 2 with
progress achievement reached up to 25%
Mechanical works started on 20 Jan 20 by installing the Water Supply and drainage
pipes which reached up to 76% in phase 1 & 22% in phase 2
HVAC work started on 23 Jan 2020 in phase 1 with 33% completed up to date. Phase 2
recorded 15% in ground floor..
ABC Building Time Management
Progress Status Report
Aug, 2020 50
45
44
39 40
40
35
30
Delay Accumulation 24
Delay Analysis 20
10 12 11 13
10
10 9
3
0
Total Delay = 35 days 1-Jul 1-Aug 1-Sep 1-Oct 1-Nov 1-Dec 1-Jan 1-Feb 1-Mar 1-Apr 1-May 1-Jun 1-Jul 1-Aug
30,000,000.00
80 80
30,000,000.00
23,878,738.
25,000,000.00 04
16,000,000.00
14,000,000.00 13
13,676,801.
12,646,192.
78
Progress Status Report 19,794,706. 12,000,000.00
Aug, 2020 25,000,000.00 20,000,000.00
96
10,000,000.00
20,000,000.00
15,000,000.00 8,000,000.00
100,000,000.0089,352,170.
47 81,843,208. 15,000,000.00
67 6,000,000.00
10,000,000.00
80,000,000.00 10,000,000.00
4,000,000.00
5,000,000.00
60,000,000.00 5,000,000.00 2,000,000.00
- - -
40,000,000.00 ACC. PV ACC. EV ACC. PV ACC. EV ACC. PV ACC. EV
20,000,000.00
Package 100% Completed Package 40% Completed Package 80% Completed
-
Acc. PV Acc. EV
Mech. Package
16,000,000.00 W.P Package Ex. Finish Package
13,785,504. 2,500,000.00
81 12,934,653. 6,000,000.00 5,417,530
14,000,000.00 2,022,812.6 .00
87 9
2,000,000.00 1,786,474.1
5,000,000.00
81.5% 12,000,000.00
10,000,000.00
0
4,000,000.00
3,874,058
.56
1,500,000.00
Completed
8,000,000.00
3,000,000.00
6,000,000.00 1,000,000.00
Structueal WP 2,000,000.00
4,000,000.00
Mechanical Electrical 500,000.00
Finishing Façade & CW 2,000,000.00 1,000,000.00
- - -
ACC. PV ACC. EV ACC. PV ACC. EV ACC. PV ACC. EV
Ahmed Abdelfattah
Project Control & Planning manager
www.ahmed-Fattah.com
ABC Building
Progress Status Report
Aug, 2020
Gallery the first building is being prepared to block works process of curing is under progressing
RC columns for the Annex Building Metal Duct Material Delivered Block Works is under progress for the
100%, and the fabrication is under Building #01 with progress reached to
have ben casted with 68%
Completed , and the curing process progress with 33% Completed 45%
is under progress