Project Crashing
Project Crashing
Project Crashing
If so, how!
Direct Cost
=
𝑻 𝒏− 𝑻 𝒄 ∆ 𝑻
• Crash time: minimum activity
duration to which an activity can
be compressed by increasing the (Normal point)
resources and hence by
increasing the direct cost. Cn N
o sts
Indirect Cost
ec t C
Indir
Total Cost
Variable
Direct Costs
Fixed
The cost slope represents the additional cost incurred per unit time (saved) in reducing
the duration of the activity.
3. Crash the critical activity with minimum cost slope. Calculate new direct
cost by adding the additional cost of crashing the normal cost.
4. As the crashing is done, it is possible some non-critical activities also
become critical.
Thus we may have multiple or parallel critical paths, if so, choose an activity from each
such path for crashing
Time-cost trade-off procedure (cont. …)
5. Of the various available combinations, select the one with least cost.
6. Revise the network by adjusting the time and cost of the crashed
activity/activities. Identify the critical path(s) again.
7. Continue the process till no more crashing is possible. This gives the
crash time. Calculate the associated total cost (by adding the normal
direct cost, additional crash cost and indirect cost). This is the
corresponding crash cost
8. Prepare the total cost table corresponding to different project durations.
9. The minimal total cost is called the optimum cost and the associated
time is called the optimum time
Project Crashing
Normal Crash
Activity Time Cost Time Cost
(days) (Rs.) (days) (Rs.)
1-2 9 640 6 700
1-3 8 500 5 575 1. Draw the network and identify critical path
2. Crash the network fully to find out minimum
1-4 15 400 10 550 duration
3. If indirect cost are Rs. 60 per day. Determine
2-4 5 100 3 120 time-cost trade off for the project
1 4 5
15 (10) 2 (1)
8(
6) 6)
0 (
1
3
Paths:
1 – 2 – 4 – 5 = 16 days
1–4–5 = 17 days
1 – 3 – 4 – 5 = 20 days
Normal Crash
Activity
Time Cost Time Cost
2 5( (days) (Rs.) (days) (Rs.)
3)
) 1-2 9 640 6 700
9 (6
1-3 8 500 5 575
𝑪 𝒄 −𝑪 𝒏
𝑪𝒐𝒔𝒕 𝒔𝒍𝒐𝒑𝒆=
Paths Crash Time 𝑻 𝒏− 𝑻 𝒄
1 – 2 – 4 – 5 = 16 days 6+3+1 = 10 days
1–4–5 = 17 days 10+1 = 11 days
1 – 3 – 4 – 5 = 20 days 5+6+1 = 12 days
Normal Crash
Activity
Time Cost Time Cost
2 5( (days) (Rs.) (days) (Rs.)
3)
) 1-2 9 640 6 700
9 (6
1-3 8 500 5 575
𝑪 𝒄 −𝑪 𝒏
𝑪𝒐𝒔𝒕 𝒔𝒍𝒐𝒑𝒆=
Paths Crash Time 𝑻 𝒏− 𝑻 𝒄
1 – 2 – 4 – 5 = 16 days 6+3+1 = 10 days
1–4–5 = 17 days 10+1 = 11 days
1 – 3 – 4 – 5 = 20 days 5+6+1 = 12 days
Paths Crash Time 1st Crashing: Reduce the time only for the critical activities
CP : 1 – 3 – 4 – 5
1 – 2 – 4 – 5 = 16 days 6+3+1 = 10 days CA : 1 – 3, 3 – 4, 4 – 5
1–4–5 = 17 days 10+1 = 11 days CS : 25, 15, 40
1 – 3 – 4 – 5 = 20 days 5+6+1 = 12 days opt for the least slope (activity 3-4)
2-5 3 45 1 65
3-4 6 90 4 200
4-6 8 80 4 300
5-6 4 40 2 100
6-7 3 45 2 80