Topic 4 Earned Value
Topic 4 Earned Value
Project Performance
Tracking and Reporting
Earned Value Analysis EVA
What do we need:
Baselining in MS Project
Tracking and Reporting
Consider Time:
TASK A
Tracking and Reporting
Consider Cost
Time
Time and Cost, what are these telling us?
Considerations:
Client/Project
Who? management team
All of this should be
When? Frequency/Period? recorded and
detailed in a
What? Content/structure
Project Management
Where? Location/archive Plan
How? Meetings/reports
Run
Make some progress on the project
Track
Map what has been achieved against what was planned. This
is passive. It is also referred to as monitoring.
Control
Take actions to bring future intentions back into line with
what was originally intended. This is active.
Tracking
Baselining/Tracking in MS Project
Measuring the work done on site
Actual Cost
Actual Cost of Work Performed ACWP
Earned Value
Budgeted Cost of Work Performed BCWP
Let us develop a simpler picture
EVA
Time now
Cumulative Planned cost, PC
Cost
Actual Cost, AC
Cost Variance, CV
Schedule Variance, SV
Earned Value, EV
What does
this actually
represent??? Time
Illustration to help make this more
understandable
Time now
Planned Cost = 200k (50k + 150k)
Our Plan:
2 Weeks
A 50k 6 Weeks
B 300k 2 Weeks
C 50k
Cost
Actual Cost, AC 250k
Time
Variance
Variance
Cost Variance = Earned Value – Actual Cost
Schedule Variance* = Earned Value – Planned Cost
* based on cost.
Efficiency
Efficiency
Cost Performance Index (CPI) = Earned Value
Actual Cost
Schedule Performance Index (SPI) = Earned Value
Planned Cost
Note if these are less than 1.0, then the project is lagging behind that
planned. If these are greater than 1.0 the project is outperforming the plan
Forecasting
Forecasting
Final Cost = Budgeted Cost
CPI
Final Duration = Original Duration
SPI
Example
• It is 8 weeks into a 20 week runway resurfacing
contract which is working five 10 hour night shifts
each week. The contract is for 200 000 m2 and the
contractor tendered £40/m2 for the work. To date,
75 000 m2 have been completed and the cost to
date is £4 000 000. Comment on the performance.
• At ten weeks, 105 000 m2 have been completed at
a cost of £4 100 000. Comment on the
performance at 10 weeks compared with 8 weeks.
Total Value for work = £40/m2 x 200,000m2 = £8,000,000
Planned duration is 20 weeks
At week 8
@8 of 20 weeks we would expect to have completed the following
area of the runway:
Total PC (8 million)
£8million 21.333 weeks
AC
£4million
PC £3.2million
EV
£3million
Predicted
time
8 20
Time
At ten weeks, 105 000 m2 have been completed at a cost of
£4,100,000. Comment on the performance at 10 weeks compared
with 8 weeks.
Cu
Predicted
cost
Total PC (8 million)
£8million
£7,815,500
EV £4.2million 19.05 weeks
AC £4.1million
PC £4.0million
Predicted
time
8 10 20
Time