Chapter III
Managing Systems Projects
Chapter Objectives
• Explain project planning, scheduling,
monitoring, and reporting
• Describe work breakdown structures, task
patterns, and critical path analysis
• Explain techniques for estimating task
completion times and costs
2
Chapter Objectives
• Describe various scheduling tools, including
Gantt charts and PERT/CPM charts
• Analyze task dependencies, durations, start
dates, and end dates
• Describe project management software and
how it can assist you in project planning,
estimating, scheduling, monitoring, and
reporting
3
Chapter Objectives
• Discuss the importance of project risk
management
• Understand why projects sometimes fail
4
Overview of Project Management
• Project Management is the process of planning and
controlling system development within a specified time
at a minimum cost with the right functionality
• A project is a set of activities with a specified beginning
and end point meant to create a system that brings value
to the business
• Project Managers monitor and control all tasks and roles
that need to be coordinated
• Inception phase: generate a system request based on a
business need or opportunity
• Perform a feasibility analysis; revise the system request
• Approve or decline the project
Overview of Project Management
• Project Management
• A successful project must be completed on
time, within budget, and deliver a quality
product that satisfies users and meets
requirements
• Project manager or project leader
• Project coordinator
6
What is Project Management?
Project management encompasses all the
activities needed to plan and execute a project:
– Deciding what needs to be done
– Estimating costs
– Ensuring there are suitable people to undertake the
project
– Defining responsibilities
– Scheduling
– Making arrangements for the work
– continued ...
7
Overview of Project Management
• What Does a Project Manager Do?
– Project manager, project leader
– Project planning
– Project scheduling
– Project monitoring and controlling
– Project reporting
8
Overview of Project Management
• Project Activities and Planning Steps
9
Step 1: Create a Work Breakdown
Structure
• Work breakdown structure (WBS)
• What is a Gantt Chart?
– Task group
– Can present an overview of the project’s status,
but does not provide detailed information that is
necessary when managing a complex project
10
Step 1: Create a Work Breakdown
Structure
• What is a PERT/CPM Chart?
– The Program Evaluation Review Technique (PERT)
– Critical Path Method (CPM)
– The distinction between the two methods has
disappeared over time
11
Step 1: Create a Work Breakdown
Structure
• What is a PERT/CPM Chart ?
– PERT/CPM is called a bottom-up technique
– Project tasks
– Once you know the tasks, their duration, and the
order in which they must be performed, you can
calculate the time that it will take to complete the
project
12
Step 1: Create a Work Breakdown
Structure
• Which Type of Chart is Better?
– Although a Gantt chart offers a valuable snapshot
view of the project, PERT charts are more useful
for scheduling, monitoring, and controlling the
actual work
– PERT and Gantt charts are not mutually exclusive
techniques, and project managers often use both
methods
13
Step 1: Create a Work Breakdown
Structure
• Identifying Tasks in a Work Breakdown
Structure
– Task or activity
– Event or milestone
– Break the project down into smaller tasks, creating
a work breakdown structure
14
Step 1: Create a Work Breakdown
Structure
• Identifying Tasks in a
Work Breakdown
Structure
– Listing the tasks
• Can be challenging,
because the tasks might
be embedded in a
document
• Create a table with
columns for task number,
description, duration, and
predecessor tasks
15
Step 1: Create a Work Breakdown
Structure
• Identifying Tasks in a Work Breakdown
Structure
– Estimating Task Duration
• Person-days
• Best-case estimate (B)
• Probable-case estimate (P)
16
Step 1: Create a Work Breakdown
Structure
• Identifying Tasks in a Work Breakdown
Structure
– Estimating Task Duration
• Worst-case estimate (W)
• Weight
(B+4P+W)
6
17
Step 1: Create a Work Breakdown
Structure
• Identifying Tasks in a Work Breakdown
Structure
– Factors Affecting Duration
• Project size and scope
• Human resources
• Experience with similar project
• constraints
18
Step 1: Create a Work Breakdown
Structure
• Displaying the Work Breakdown Structure
– If you are managing a complex project with many
tasks, you can use task groups, just as you would
in a Gantt chart, to simplify the list
19
Step 2: Identify Task Patterns
• What are Task Patterns?
– Large or small, tasks depend on each other and
must be performed in a sequence, not unlike the
commands in a software program
– Task patterns can involve dependent tasks,
multiple successor tasks, and multiple predecessor
tasks
20
Step 2: Identify Task Patterns
• How do I Use Task Boxes to Create a Model?
21
Step 2: Identify Task Patterns
• What are the Main Types of Task Patterns?
– Dependent Tasks
– Multiple successor tasks
• Concurrent task
• Predecessor task
• Successor task
– Multiple Predecessor Tasks
22
Step 2: Identify Task Patterns
• How Do I Identify Task Patterns?
– You can identify task patterns by looking carefully
at the wording of the task statement
– Words like then, when, or and are action words
that signal a sequence of events
• How Do I Work With Complex Task Patterns?
– When various task patterns combine, you must
study the facts carefully in order to understand
the logical sequence
23
Step 2: Identify Task Patterns
• How Do I Work With Complex Task Patterns?
– Consider the following three fact statements and
the task patterns they represent
• Dependent tasks
• Dependent tasks and multiple successor tasks
• Dependent tasks, multiple successor tasks, and multiple
predecessor tasks
24
Step 3: Calculate the Critical Path
• What Is a Critical Path?
25
Step 3: Calculate the Critical Path
• How Do I Calculate the Critical Path?
– First, you should review the task patterns
– The next step is to determine start and finish
dates, which will determine the critical path for
the project
– Slack time
26
Project Monitoring and Control
• Monitoring and Control Techniques
– The project manager must keep track of tasks and
progress of team members, compare actual
progress with the project plan, verify the
completion of project milestones, and set
standards and ensure that they are followed
– Structured walkthrough
– Called design reviews, code reviews, or testing
reviews
27
Project Monitoring and Control
• Maintaining a Schedule
– Maintaining a project schedule can be a
challenging task
– The better the original plan, the easier it will be to
control the project
– If enough milestones and frequent checkpoints
exist, problems will be detected rapidly
– Project managers often spend most of their time
tracking the tasks along the critical path
28
Reporting
• Members of the project team regularly report
their progress
• Project Status Meetings
29
Reporting
• Project Status Reports
– A project manager must report regularly to his or
her immediate supervisor, upper management,
and users
– Should explain what you are doing to handle and
monitor the problem
– Most managers recognize that problems do occur
on most projects; it is better to alert management
sooner rather than later
30
Project Management Examples
• PERT/CPM Example
– You construct a PERT/CPM chart from this task list
in a two-step process
• Step 1: Create the work breakdown structure
• Step 2: Enter start and finish times
31
Project Management Examples
• Software-Driven
Example
– Open Workbench
– Open-source software
– When you use project
management software,
you follow the same
step-by-step process to
develop a WBS and
create various types of
charts
32
Project Management Examples
• Software-Driven
Example
– Work breakdown
structure
– Gantt chart
– Network diagram
– Project planning is a
dynamic task and
involves constant change
33
Risk Management
• Every IT project involves
risks that systems
analysts and project
managers must address
• Risk management
• Steps in Risk
Management
– Develop risk
management plan
– Identify the risks
• Risk identification
34
Risk Management
• Steps in Risk Management (continued)
– Analyze the risks
• Qualitative risk analysis
• Quantitative risk analysis
– Create a risk response plan
– Monitor risks
35
Risk Management
• Risk Management Software
– Most project management software includes
powerful features
– The IT team can make a recommendation
regarding the risks
– Depending on the nature and magnitude of the
risk, the final decision might be made by
management
36
Managing for Success
• Business Issues
– The major objective of every system is to provide
a solution to a business problem or opportunity
– A system that falls short of business needs also
produces problems for users and reduces
employee morale and productivity
– Project creep
37
Managing for Success
• Budget Issues
– Cost overruns typically result from one or more of
the following:
• Unrealistic estimates
• Failure to develop an accurate forecast that considers
all costs over the life of the project
• Poor monitoring of progress and slow response to early
warning signs of problems
38
Managing for Success
• Budget Issues
– Cost overruns typically result from one or more of
the following:
• Schedule delays due to factors that were not foreseen
• Human resource issues, including turnover, inadequate
training, and motivation
39
Managing for Success
• Schedule Issues
– Problems with timetables and project milestones
can indicate a failure to recognize task
dependencies, confusion between effort and
progress, poor monitoring and control methods,
personality conflicts among team members, or
turnover of project personnel
40
END
41
Chapter Review Questions
1. What is project management, and what are its main objectives?
2. What is the relationship between tasks and events, or milestones?
3. What is a work breakdown structure? How do you create one?
4. What are task patterns, and how can you recognize them?
5. Compare the advantages and disadvantages of Gantt and
PERT/CPM charts.
6. Define the following terms: best-case estimate, probable-case
estimate, and worstcase estimate, and describe how project
managers use these concepts.
7. How does a project manager calculate start and finish times?
8. What is a critical path, and why is it important to project
managers? How do you identify the critical path?
9. What are some project reporting and communication techniques?
10. 10. What is risk management, and why is it important? 42