Design
Basis
and instrumentation).
IV.4 Piping General Arrangements
IV. Main Pipiing Equipment/ Eng.Documentation
(GA’s)
Title Block
Full title block details shall be filled prior to starting the drawing. In
particular, the title, drawing number and scale shall be indicated. A four-line
title is standard:
PLANT NAME
UNIT NUMBER - AREA NUMBER
PLAN FROM GRADE TO EL. ------
PIPING GENERAL ARRANGEMENT
In case of producing piping sections in another drawing sheet, the title block
shall be as follows:
PLANT NAME
UNIT NUMBER - AREA NUMBER
PLAN FROM GRADE TO EL. ------
PIPING SECTION
IV.4 Piping General Arrangements
IV. Main Pipiing Equipment/ Eng.Documentation
(GA’s)
PLAN AT GRADE
PLAN FROM GRADE TO EL 105600
PLAN FROM EL 105600 TO EL 110600
PLAN ABOVE 110600
Scale
Normal scale for piping plans is 1:33 1/3 metric (3/8": 1' - 0"
imperial) . If it is necessary to show piping in detail, scales 1:10, 1:20
and 1:25 may be selected for individual items. Where piping runs are
extensive e.g. off plots and storage areas, scales of 1:50 or 1: 100 shall
be utilized, with details of pumping stations tie-ins etc. enlarged to
1:33 1/3 where greater clarity is necessary. All dimensions not drawn
to scale shall be marked N.T.S. accordingly.
Scale shall be mentioned in the title block in addition to a
corresponding scale ruler shown in the drawing.
Add picture scale
IV.4 Piping General Arrangements
IV. Main Pipiing Equipment/ Eng.Documentation
(GA’s)
IV.4 Piping General Arrangements
IV. Main Pipiing Equipment/ Eng.Documentation
(GA’s)
Match Lines
Match lines identify the limits of the total area to be drawn as indicated
on the unit piping plans index. External boundaries identified on
drawings as "Match lines", indicate that the drawn area has matching
area(s) with corresponding match line(s) so continuation-drawing
reference shall be mentioned. External boundaries identified on
drawings as "Area Limits" establish the outer boundary of an area and
in turn the units without a corresponding match line.
Drawing limits must be indicated utilizing North/South and East/West
coordinates as follows:
Sections and elevations shall only be produced when piping details cannot
be adequately shown on the plan as in the case of pipe racks and multi-
levels structures. Where possible, such detail should be shown using an
elevation view outside the limits of the match line or another drawing
sheet. If it is necessary to draw sections they shall be titled:
SECTION A-A
When elevation details are drawn, they shall be titled:
DETAIL A
IV.4 Piping General Arrangements
IV. Main Pipiing Equipment/ Eng.Documentation
(GA’s)
Key Plan
Drawing Content
Checklist
Piping Elevations
Line Numbers
Line
East Number
Coordinate Elevatio
n
IV.4 Piping General Arrangements
IV. Main Pipiing Equipment/ Eng.Documentation
(GA’s)
Insulation
Pipe Supports
Tie- Ins