Lecture 4b Critical Path and Float

The document outlines a project with 15 activities and their durations, predecessors, and costs. It describes how to determine the critical path and float times by calculating the earliest and latest start and finish dates for each activity. The critical path for this project is activities A-D-G-H-L-M, with a total project duration of 45 days.

Uploaded by

Randy Sooknanan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
0% found this document useful (0 votes)
46 views13 pages

Lecture 4b Critical Path and Float

The document outlines a project with 15 activities and their durations, predecessors, and costs. It describes how to determine the critical path and float times by calculating the earliest and latest start and finish dates for each activity. The critical path for this project is activities A-D-G-H-L-M, with a total project duration of 45 days.

Uploaded by

Randy Sooknanan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
You are on page 1/ 13

Determining Critical Path and Float Times

Determining Critical Path and Float Times

Activity Duration Predecessors Cost

A 7 - $350

B 6 A $750

C 3 A $370

D 4 A $650

E 6 B $1250
F 7 C,D $875

G 8 D $975

H 8 G $850

I 5 E,F $1575

J 3 E $1553

K 6 J $876

L 9 H,I $698

M 9 K,L $654
Determining Critical Path and Float Times
Determining Critical Path and Float Times
Determining Critical Path and Float Times
Determining Critical Path and Float Times
Determining Critical Path and Float Times

Duration = Max{( 10+7), (11+7)}


Determining Critical Path and Float Times

Duration of the project = 45 days


Determining Critical Path and Float Times

Float Activities

Earliest Start Date + Duration = Earliest Finish Date

Latest Start Date + Duration = Latest Finish Date


Determining Critical Path and Float Times
Determining Critical Path and Float Times
Determining Critical Path and Float Times

Activities with zero slack


will be on critical path
Determining Critical Path and Float Times

Duration of the project = 45 days


Critical Path A-D-G-H-L-M