SUKKUR BARRAGE REHABILITATION
AND MODERNIZATION PROJECT
Brief on Rehabilitation Works
Atkins-ACE-NDC Joint Venture
8th March 2018
1
Project Profile
Total Cost: Rs. 16,662.5 Million World Bank Loan: Rs. 14,685 million
Govt. of Sindh Share: Rs. 1002.25 million
Govt. of Pakistan Share: Rs. 1002.25 million
Approvals: ECNEC 22nd May 2018, Approved the Scheme
World Bank Additional Financing 2017
Credit/Loan Financing Agreement Signed
13 June 2018
Loan Effectiveness August 2018
Closing Date 30 September 2022.
Project Objectives The project development objective (PDO) is to strengthen the Sindh
Irrigation Department’s capacity to effectively rehabilitate, operate, and
manage the Sukkur Barrage.
SUKKUR BARRAGE
The Lifeline for Sindh Province
• Agricultural Dependency of Sindh
– With Command Area of about 8 million acres (3.2 million hectares),
about 80% of agricultural land in Sindh depends on Sukkur Barrage.
– About 50% of the population of Sindh
(25 million out of 50 million) earns its
lively hood, in one way or the other,
through Sukkur Barrage.
SU K
KU
CO RB
MM AR
AN
D A RA G
RE E
A
SINDH
3
Main Issues of the Barrage
Issues Proposed Solutions
Reduction in Barrage Flood Capacity from 1.5 million - Increase freeboard, under the fully
cusecs to 0.9 million cusecs, after closing of 10 gates. opened gates, for 1.3 million cusecs
flood.
Sedimentation Problems due to: Follow proper annual flushing when
- Reduction in River inflows to allow flushing sufficient flows in the river are
- Heavy siltation in Left & Right Pockets and Approach & available
Tail Channels. - Cleaning of silt from Pockets
- Silting in canals due to heavy silt intake from pockets. through Dredging/excavation and
de-silting of canals.
Deteriorations in the Barrage structure - Repairs to structure
- Routine Maintenance
Monitoring system Completely new Monitoring System
- The instruments are almost nonfunctioning
Electrical System Outdated Replacement
Laboratory and Workshop non-operational due to New workshops, laboratory and
damages to existing buildings other buildings
4
Siltation as Observed in Closure 2014
Tail Channel Right Pocket Right Pocket
(looking toward Gates) (looking toward Submerged Weir)
Upstream Main River Channel Downstream of Barrage Rice Canal Head Regulator
(from Left Pocket) on Right Side (at immediate downstream)
5
Deteriorations in Barrage Structure
d/s Gate Bridge Arch u/s gate Arch Roadway Arch
Pier of Canal Head regulator Deteriorations in Poor Condition of
Stone masonry Gate Deck Slab
6
Condition of Gates and Mechanical Works
7
Main Barrage Gates under stress corrosion
Crack in the middle Girder (Stress Corrosion)
8
Rehabilitation Works for 1.3 Million Cusecs Flood
Retaining Existing Right Pocket River Training Works
• Civil Repair Works
• Gates and Mechanical Works
• Electrical Works
– RCC Arches. – Repairs and Epoxy Coating in
– Complete replacement
– Stone Arches. all gates.
of all switchboards, LCP
– Stone Spandrel Filling. – Increasing in gate height by and cabling.
– Stone Piers of Barrage. 2ft, replacing existing
– Dedicated feeding from
– RCC Jacketing of Canal Head temporary arrangement of
WAPDA Grid.
Regulator Piers. wooden planks.
– 11 Kv Transformers and
– Gate Deck Flooring and Road – Increasing of freeboard for
main Controls
Surface with Stormwater fully opened condition.
Switchboard.
Drainage. – Changes in Hoisting to work
– Standby Generators.
– Rising of Left Divide Wall. without Counterweight.
– Replenishment of Scour – Replacement of all moving
• Dredging Works
Protection Works. components and seals. – Left & Right Pockets.
• Monitoring and Control – Tail Channel & Approach
Instrumentation Channel.
• Foundation Inspection and Increase in Serviceable Life – Downstream of Right
Repairs - 50 Years for Civil Works Pocket.
Construction Duration - 30 Years for Electrical & – Approach to Left Pocket.
- Four Years Mechanical Works
• Canal De-silting 9
THANK YOU