Pert & CPM
Pert & CPM
A D
C
PERT :
This method uses three time estimates : Optimistic time, Most
likely time and Pessimistic time.
Optimistic time (a): This is the shortest time for completing an
activity.
Most likely time (m): This refers to the time that is expected to
occur, if the activities are repeated under exactly the same
condition.
PERT & CPM
Beta curve
Probability
a m tei b
Time duration of activity
PERT & CPM
•• The
three time estimates are reduced into a single expected
time (tei ) which can be computed using following formula :
• tei = where
• tei = Expected time of the ith activity
• a = Optimistic time
• m = Most likely time
• b = Pessimistic time
• The standard deviation, Ϭi of the completion time of an
activity is calculated as follows :
• Ϭi =
• The variance = = ()2
PERT & CPM
EF LF
4 4 EF LF
C=1
3
EF LF A=2 EF LF 9 9
E=3
t=0 7 7
F=2
0 0 5
B=4 D=2
4
1
EF LF
2
EF = ES + t Slack = LS - ES
LF = LS + t Slack = LF – EF 4 4
PERT & CPM
0 1 2 3 4 5 6 7 8 9
A C
B D E F
EF LF EF LF
28 28 36 36
EF LF EF LF
C,7 F,8
21 21 38 38
A,21 G,2
EFE,5LF
33 36
EFB,5 LF EFD,2 LF
26 26 28 28
PERT & CPM
E
3 5
B D G
A H I
C
1 2 6 7 8
F
4
Calculation of expected time and variances
Activity a m b Tei =(a+4m+b)/6 Ϭi = (b-a)/6 Ϭi2
Activi A B C D E F G H I J K L
ties
Depen - - - B,C A C E E D,F, E J G
dence H
Durati 9 4 7 8 7 5 10 8 6 9 10 2
on
(Days)
EF LF
25 25
EF LF EF LF EF LF
7
J EF LF K
EF LF 9 9 16 16
26 33 35 35
A E G L
6 8
0 0 EF2 LF 9
1 EF LF H EF LF I
B
C 7 D 21 24 29
3Dummy activity
5
(t=0) F
4
EF
7 LF
21
Activity Duration EF LF SLACK Critical
(t) =LF - EF activity
A 9 9 9 0 A
B 4 4 21 17
C 7 7 21 14
D 8 15 29 14
E 7 16 16 0 E
F 5 12 29 17
G 10 26 33 7
H 8 24 29 5
I 6 30 35 5
J 9 25 25 0 J
K 10 35 35 0 K
L 2 28 35 7
CRITICAL PATH : A – E – J – K
PROJECT COMPLETION TIME = 9 + 7 + 9 + 10
= 35 DAYS