Module 3 (KTU)
Module 3 (KTU)
Piping Fundamentals
PIPE:
It is a Tubular item made of metal, plastic, glass etc.
meant for conveying Liquid, Gas or any thing that
flows.
Defined as a pressure tight cylinder used to convey
fluid under pressure in applicable material of
construction.
It is a very important component for any industrial
plant. And it’s engineering plays a major part in
overall engineering of a Plant.
PIPING
10
CM4120
Unit Operations Lab
Piping Systems
11
CM4120
Unit Operations Lab
Piping Systems
12
Schedule number
• Sc= 1000P/S
• P= internal pressure in psig
• S= allowable working stress in Psi
• t = (PD/2S)+C
• D= outside pipe dia in inches
• t= thickness of pipe in inches
• C = corrosion allowance
Material of construction
• 150 different material specified by ASTM
• Carbon steel
• Alloy steel
• Non ferrous
• Plastic
• ASTM A-106-seam less pipe specification
• ASTM A-53- seam less
• ASTM A-83- tubular
CM4120
Unit Operations Lab
Piping Systems
15
CM4120
Unit Operations Lab
Piping Systems
16
Tests for piping
• Hydrostatic
• Check analysis- chemical composition
• Tensile
• Bending- suitability for bending operation
• Flattening- check suitability for forming
operation
Pipe joints
• Threaded joints-unions and coupling
• Flanged joints –welding neck, slip on, lap joint,
socket welding, threaded flange, integral
flange.
• Welded joints
• Expansion joints
• Socket and spigot joint
Flange classification
• Raised face- widely used
• Male and female
• Tongue and groove- ammonia service
• Ring joint
• Flat faced facing
• Oval, triangular, square flanges
• Gaskets- asbestos combined with other
materials, metal gaskets.
Pipe fittings
• Welded pipe fittings
• Flanged pipe fittings
• Screwed pipe fitting
• Elbow, tee, cross, reducer, cap, union,
coupling,
Cast iron pipe and fitting
• ASA- American standard association
• AWWA- American water works association
• AGA- American gas association
• Bell and spigot joints
• Flange
• Compression coupling
• Threaded
Valves
• 1.Gate valve
• 2.Globe valve
• 3.Non return valve –Check valve
• 4.Ball valve
• 5.Butterfly valve
• 6.Diaphram valve
• 7.Plug valve -Cock
• 8.Needle valve
• 9.Safety valve
• 10.Solenoid valve
• 11.Control valve
• Valves may also be classified by how they are
actuated:
• Hydraulic
• Pneumatic
• Manual
• Solenoid
• Motor
Valve selection
• Fluid to be handled
• Operating condition
• Flow characteristics and frictional losses
• Size of valve
• Any special requirement- quick opening
Purpose of valve
• 1.On-off service
• 2.Throttling- Controlling
• 3.Diverting
• 4.Unidirectional flow
Parts of valves
• Valve body containing flow control element-
disc,plug,gate,ball etc.
• Stem
• Bonnet-gland,stuffing box
• Hand wheel
Gate valve
• On-off service
• Not recommended for throttling
• Minimum resistance to line flow
• Low pressure drop
Gate valve
Gate valve
Globe valve
• Controlling the flow
• On-off service
• High pressure drop
• Seating arrangement offer resistance to flow
Globe
valve
Globe valve
Non return valve
Types of non return valve-
• 1.Swing check valve
2.Lift check valve
• 3.Ball check valve
-Providing flow in one direction
• Prevent back flow
Lift check valve
Plug
valve
Plug valve
Safety valve
• Spring loaded safety valve
• Weight loaded safety valve
• To release excess pressure
• Safety purpose
• Boilers,pressure vessel,compressor etc.
Spring loaded safety valve
Weight loaded safety valve
Control valve
• Automatic control
• Pneumatic or hydraulic
• Consists of valve,Bonnet and actuating
mechanism
• Sliding stem control valve-linear motion of the
valve plug-globe valve,angle valve,Three valve
• Rotary shaft control valve-rotary motion of the
valve plug-Ball valve,butterfly valve
Control valve
Actuator
Bonnet Assembly
Expansion joints
• This joint permits longitudinal expansion or
contraction of the pipes, which is due to the
change in temperature.
• Corrugated bellow (packless joint) (made of
Cu)
• Loop joint (made of Cu)
• Gland and stuffing box (slip joint)
Pipe supports
• Structural steel pipe support
• Pipe shoe
• Pipe roll stand
• Hangers:-
• Adjustable clevis hanger
• Adjustable swivel type hanger
• Pipe clamp with chain type hanger
• Adjustable roller hanger
• Spring hanger
Blinds
• Line blind is used to seal off a line or piece of
equipment.
• It provides more positive and reliable seal
than a conventional valve.
• Figure 8 blinds
Piping layout
• Process requirement
• Transmission of excessive stress from piping to
equipment, and the transfer of vibration from
equipment into the piping system.
• Economy
• Operational accessibility
• Maintenance and replacement
• Excessive stress in piping system
Piping stress
• Stress due to internal and external pressure
• Residual stress after fabrication
• Stress due to temp change.
Magnitude of temp stress
• S=ECT
• S = stress
• E= modulus of elasticity
• C= coefficient of expansion
• T= temp change.
• Force = stress x metal area
Methods for relieving expansion stress
http://www.ehw.org/Chemical_Accidents/CHEM_RenoLtr.htm 99/63
Active safety systems (Engineered safety
system or Add on safety)
• Design of control systems
• Alarms, Trips
• Pressure relief devices
• Automatic Shutdown systems (ESD)
• Redundancy (duplication of key equipments)
• Fire detection and leak detection
• Fire fighting equipments
• Sprinkler systems
Passive safety systems
• Dike
• Underground drainage systems
• Fireproofing
• Fire wall
• Blast wall
• Flame arrester
• Refrigeration system
• Plant layout
• Equipment layout
• Hazard area classification
PROCEDURAL SAFE DESIGN
• Procedural — Prevention or minimization of
incident impacts using:
• Safe operating procedures and operator
training
• Administrative safety checks
• Management of Change
• Planned emergency response
DESIGN IN OVERALL SAFETY MANAGEMENT
Art M. Dowell, III, Layer of Protection Analysis, 1998 PROCESS PLANT SAFETY
SYMPOSIUM, October 27, 1998 Houston, TX
Plant constructions
• Project engineer should have some
understanding of
• Construction planning
• Labour and labour relations
• Actual construction operation
Construction planning
• Design drawing and Specification give the
detailed information to construction department.
• Construction engineers should study the
preliminary engineering data and scale models of
plants to be erected.
• Selection of derricks and hoisting equipments.
• Positioning of construction equipments
• Planning of errection
• Constructional labour distribution
• Labour disputes
• Labour rates
Construction operations
• Site preparation
• Driving of pile
• Temporary buildings
• Temporary water supply
• Road ways and rail
• Excavation operations
• Installation of underground facilities
• Electrical conduit and underground piping
• Foundation construction
• Erection of derricks
• Erection of elevated reinforced concrete
structure and structural steel.
• Erection of major equipments
• Installation of piping
• Pipe identification
• insulation
• Buildings:- office buildings, ware houses,
change houses, canteens, M/C shop, lab etc.
• Final stages of construction :-
• Instruments, electrical apparatus, small piping
for instrumentation,
• Cleaning of site
• Installation of safety equipments
Commissioning of Process Plants
• Mechanical Completion
• P& ID Checking
• Pre commissioning
• Commissioning –
• Cold commissioning – Wet and Dry
• Hot commissioning – Live commissioning
• Start up
• Initial stages of operation
• Performance run
• Post commissioning
Commissioning
• Mechanical completion
• Precommissioning
• Commissioning of control systems
• Commissioning of utilities, offsite
• Process Commissioning
• Guarantee run- performance and acceptance test.
• Handed over to the owner
• Post commissioning documentation
Mechanical completion
• Records
• Audits and reviews
• Maintenance records
• Log sheet
• Accident report
• Stack analysis
Start up and commissioning
• Once the plant is mechanically complete, efforts
will be made to start up and commission the plant.
• Following are the important step involved in start
up and commissioning.
• 1. Mobilization of commissioning crew.- training
• Mechanical, electrical, instrumentation, chemists,
process.
• 2. Clearing up the plant and site
• 3. Inspection and testing
• - Check all the parts are properly fitted
• Check list preparation
• - Mechanical integrity of the plant
• - Leak test
• - Pressure test
• - Electrical machinery and instruments are
also given special tests.
• Whatever deficiencies observed are rectified.
• 4. Mobilization of materials
• Raw materials
• Steam
• Cooling water
• Power
• BFW
• Chart paper
• Ink
• Lubricating oil, greese, solvents, catalyst
• 5.Charging various items:-
• Lubricating oil, solvents, catalyst
• Activation of catalyst
• Furnace , heater:- curing of refractories
• 6. section wise start up
• 7. Performance testing
• 8. Check the quality of final and intermediate
product
• 9. capacity is gradually raised
• 10. consumption of raw material and utilities
are brought down to guarantee level.
• 11. Commissioning
• 12. Trial run
• 13. Handed over to the owner.