Material Requirements Planning: Introduction To Materials Management, 8e Introduction To Materials Management, 8e

Download as pptx, pdf, or txt
Download as pptx, pdf, or txt
You are on page 1of 31

Introduction to

MATERIALS MANAGEMENT

CHAPTER 4
Material
Requirements
Planning

IntroductiontotoMaterials
Introduction MaterialsManagement,
Management,8e 8e Copyright © 2017 by Pearson Education, Inc.
Chapman,Arnold,
Chapman, Arnold,Gatewood,
Gatewood,and
andClive
Clive All Rights Reserved
Independent versus Dependent
Demand
• Independent Demand
▪ Not related to demand for other assemblies or
products
▪ From outside sources
▪ Generally forecasted demand
• Dependent Demand
▪ Generally related to production of an end
product (as defined on the MPS)
▪ Can be calculated instead of forecasted

Introduction to Materials Management, 8e Copyright © 2017 by Pearson Education, Inc.


Chapman, Arnold, Gatewood, and Clive All Rights Reserved
Dependent Demand Approach –
Material Requirement Planning (MRP)

• Major Objectives of MRP


▪ Determine requirements – Calculated to meet
product requirements defined in the MPS
• What to order
• How much to order
• When to order
• When to schedule delivery
▪ Keep priorities current

Introduction to Materials Management, 8e Copyright © 2017 by Pearson Education, Inc.


Chapman, Arnold, Gatewood, and Clive All Rights Reserved
Links To Other MPC Functions

Introduction to Materials Management, 8e Copyright © 2017 by Pearson Education, Inc.


Chapman, Arnold, Gatewood, and Clive All Rights Reserved
Major Inputs to MRP

• Master Production Schedule quantities and times


• Inventory records of all items to be planned
▪ Planning factors such as lead times, order
quantities, and safety stock
▪ Current status of each item
• Bills of material for MPS items

Introduction to Materials Management, 8e Copyright © 2017 by Pearson Education, Inc.


Chapman, Arnold, Gatewood, and Clive All Rights Reserved
Sample Bill of Material

Introduction to Materials Management, 8e Copyright © 2017 by Pearson Education, Inc.


Chapman, Arnold, Gatewood, and Clive All Rights Reserved
Bill of Material Points

• The BOM shows all parts to make one of the item


• Each part has one, and only one, part number
• A part is defined by form, fit, and function
• Any change requires a new part number

Introduction to Materials Management, 8e Copyright © 2017 by Pearson Education, Inc.


Chapman, Arnold, Gatewood, and Clive All Rights Reserved
Sample Product Tree for the BOM

Introduction to Materials Management, 8e Copyright © 2017 by Pearson Education, Inc.


Chapman, Arnold, Gatewood, and Clive All Rights Reserved
Breaking Down the BOM into More
Detail – the Multilevel Bill

Introduction to Materials Management, 8e Copyright © 2017 by Pearson Education, Inc.


Chapman, Arnold, Gatewood, and Clive All Rights Reserved
Indented BOM – Use Indentation to
Show Parent-Component Relationships

Introduction to Materials Management, 8e Copyright © 2017 by Pearson Education, Inc.


Chapman, Arnold, Gatewood, and Clive All Rights Reserved
Planning Bill of Material

• Artificial grouping of components for planning


purposes
• Used to simplify
▪ Forecasting
▪ Planning
▪ Master Scheduling
• Represents an average, not buildable product

Introduction to Materials Management, 8e Copyright © 2017 by Pearson Education, Inc.


Chapman, Arnold, Gatewood, and Clive All Rights Reserved
Sample Planning BOM

Introduction to Materials Management, 8e Copyright © 2017 by Pearson Education, Inc.


Chapman, Arnold, Gatewood, and Clive All Rights Reserved
Where-Used and Pegging

• Where-used reports
▪Shows the parents for a component (contrast
with a bill of material that shows the
components for a parent)
• Pegging report
▪Shows the parents for a component, but only
those parents where there is an existing
requirement

Introduction to Materials Management, 8e Copyright © 2017 by Pearson Education, Inc.


Chapman, Arnold, Gatewood, and Clive All Rights Reserved
Major Uses for Bills of Material

• Defines the product


• Provides method for design change control
• Planning – What is needed and when
• Order entry – order configuration and pricing
• Production – Parts needed to assemble a product
• Costing – material cost of goods sold

Introduction to Materials Management, 8e Copyright © 2017 by Pearson Education, Inc.


Chapman, Arnold, Gatewood, and Clive All Rights Reserved
Basic MRP Record

Introduction to Materials Management, 8e Copyright © 2017 by Pearson Education, Inc.


Chapman, Arnold, Gatewood, and Clive All Rights Reserved
Key Terms

• Lead time – Span of time for a process


• Exploding – Process of multiplying requirements
by usage to get BOM requirements
• Offsetting – Placing requirements in the proper
period based on lead time
• Planned orders – Orders planned during the
explosion, but not yet released for processing
• Low-level code – Lowest level on which a part
resides on the bill of material

Introduction to Materials Management, 8e Copyright © 2017 by Pearson Education, Inc.


Chapman, Arnold, Gatewood, and Clive All Rights Reserved
Key Terms (continued)

• Scheduled receipts – Open orders released for


processing (production or purchase) scheduled to
be received at a defined time
• Gross Requirements – Total of a component
needed to meet requirements not taking any
existing inventory into account
• Net Requirements – Actual amount of a
component needed after existing requirements
taken into account

Introduction to Materials Management, 8e Copyright © 2017 by Pearson Education, Inc.


Chapman, Arnold, Gatewood, and Clive All Rights Reserved
Key Terms (continued)

• Projected available – The expected inventory


position at the end of the period
• Planned order release – The amount that should
be ordered (using the lot size) to prevent a
negative projected available balance
• Planned order receipt – When the order should be
available for use, offset by lead time from the
planned order release

Introduction to Materials Management, 8e Copyright © 2017 by Pearson Education, Inc.


Chapman, Arnold, Gatewood, and Clive All Rights Reserved
Example Problem

Lead time for this component is 2 weeks and order


quantity is 200. Complete the table. What action should
be taken?

Introduction to Materials Management, 8e Copyright © 2017 by Pearson Education, Inc.


Chapman, Arnold, Gatewood, and Clive All Rights Reserved
Example Problem Solution

The order for 200 should be released

Introduction to Materials Management, 8e Copyright © 2017 by Pearson Education, Inc.


Chapman, Arnold, Gatewood, and Clive All Rights Reserved
Example of a Multilevel BOM

Lead time for each component is 1 week


Introduction to Materials Management, 8e Copyright © 2017 by Pearson Education, Inc.
Chapman, Arnold, Gatewood, and Clive All Rights Reserved
Netting and Exploding Level 0
Parts

Introduction to Materials Management, 8e Copyright © 2017 by Pearson Education, Inc.


Chapman, Arnold, Gatewood, and Clive All Rights Reserved
Netting and exploding Level 1
Parts

Introduction to Materials Management, 8e Copyright © 2017 by Pearson Education, Inc.


Chapman, Arnold, Gatewood, and Clive All Rights Reserved
Completed Material Requirements
Plan

Introduction to Materials Management, 8e Copyright © 2017 by Pearson Education, Inc.


Chapman, Arnold, Gatewood, and Clive All Rights Reserved
Sample Multiproduct MRP
Explosion

Introduction to Materials Management, 8e Copyright © 2017 by Pearson Education, Inc.


Chapman, Arnold, Gatewood, and Clive All Rights Reserved
Points About the MRP Record

• Current time – beginning of first period (often


called time buckets)
• Items considered available at beginning of period
• Quantity in Projected Available row considered at
end of period
• Current period often called action bucket – action
should be taken to avoid a future problem

Introduction to Materials Management, 8e Copyright © 2017 by Pearson Education, Inc.


Chapman, Arnold, Gatewood, and Clive All Rights Reserved
Planner Responsibilities for MRP

• Launch Orders – Production or Purchasing


• Reschedule orders as required
• Reconcile errors and search for causes
• Solve critical material shortages
▪ Replan
▪ Expedite
• Coordinate with other functions to resolve
problems

Introduction to Materials Management, 8e Copyright © 2017 by Pearson Education, Inc.


Chapman, Arnold, Gatewood, and Clive All Rights Reserved
Moving Through Time –
An Example

This record shows the status of the part Monday morning.


The computer is showing the need to release the order of
30
Introduction to Materials Management, 8e Copyright © 2017 by Pearson Education, Inc.
Chapman, Arnold, Gatewood, and Clive All Rights Reserved
During the week, the following
events happen
• Only 25 units of the scheduled receipt move into
inventory. The balanced is scrapped.
• The gross requirement for week 3 is changed to 10.
• The gross requirement for week 4 is increased to 50.
• The gross requirement for week 7 is 15.
• An inventory count reveals there are 10 more in
inventory than the record shows
• The gross requirement for week 1 is issued from
inventory
• The planned order release of 30 in week 1 is released
and becomes a scheduled receipt in week 3.
Introduction to Materials Management, 8e Copyright © 2017 by Pearson Education, Inc.
Chapman, Arnold, Gatewood, and Clive All Rights Reserved
The new record reflects those
events from week 1

Introduction to Materials Management, 8e Copyright © 2017 by Pearson Education, Inc.


Chapman, Arnold, Gatewood, and Clive All Rights Reserved
Additional Key Terms

• Firm Planned orders – Orders not yet released,


but “frozen” in quantity and time to reduce
system “nervousness”
• Exception messages – Messages generated by
the computer signaling planner action needed
• Bottom-up replanning – Actions to correct for
changed conditions made as low as possible in
the product structure

Introduction to Materials Management, 8e Copyright © 2017 by Pearson Education, Inc.


Chapman, Arnold, Gatewood, and Clive All Rights Reserved

You might also like