Operations Research Project: BY:-Nikhil Malhotra 19021141074
Operations Research Project: BY:-Nikhil Malhotra 19021141074
RESEARCH
PROJECT
BY:-
NIKHIL MALHOTRA
19021141074
Sequencing Problem
Seven biscuit brands of company Britannia are to be made in the
same factory using four machines; Machine 1 for creaming, Machine
2 for mixing, Machine 3 for baking and Machine 4 for packing. The
time required for preparing each pack of biscuit is as following.
2
JOBS
MACHINES A B C D E F G
4
From the data of the problem, it is observed that
Min {tM1, j} = 7 = {tM1,B} and
Max {tM2, j} = 6 = {tM1,D}
6
A B C D E F G
MACHINE G 28 22 24 28 22 25 25
7
The optimum sequence obtained is as follows
D C F A B G E
8
MACHINES
M1 M2 M3 M4
JOB
SEQUENCE
D 0-11 11-17 17-28 28-30
C 11-18 18-23 28-40 40-41.5
F 18-28 28-33 40-50 50-52.5
A 28-41 41-45 50-61 61-62
B 41-49 49-53 61-71 71-72
G 49-61 61-65 71-80 80-81.5
E 61-70 70-75 80-88 88-89
9
Total time elapsed corresponding to the optimal sequence has
been calculated as shown in the table using individual
processing times given in the original problem
10
MACHINES Idle time
M1 (89-70)=19
M2 (89-75)+(11+1+5+8+4+8+5)=56
M3 (89-88)+(17)=18
M4 28+10+9.5+7.5+9+8+6.5=78.5
Hence, the idle time for machines M1, M2, M3 and M4 the
idle times are 19, 56, 18 and 78.5 minutes respectively.