Project Scheduling PERT/CPM
Project Scheduling PERT/CPM
A Project
Construction of a bridge
Highway
Power Plant
Repair and maintenance of an oil refinery
Design and development
Marketing of new product
Starting End
event Activity
event
Predecessor Activity: Activities that must be completed
immediately prior to the start of another activity.
ys
D
4 da
1 14
day
s
A 7 days
2 4
c
Critical Path Analysis
8
2 5
4
4 7
Forward Pass Calculation
TES (Task Early Start) - the earliest start time of that activity.
TEF (Task Early Finish) - the earliest finishing time of the
activity
TLF (Task Late Finish) - this is the latest time that the activity
can end.
Latest event time for event i, is the minimum of the latest start
of all activities from the event
8 19 ||19
0 ||0 2 5
4
4 7
2 ||6
10 ||10
Concept of Slack and Float
* Slack means the freedom for scheduling or to start of the activity.
* It is calculated by the diff. between Es and Lf for any event.
* An event for which the slack time is zero is know as critical event.
Critical Path: It can located by all those activities for which slack
time is Zero.
7 ||8 11 | 12
4
Es| Ef Ls| Lf
te= (a+4m+b)/6
Network Construction
Activity a m b te σ2
1-2 1 2 9 3 1.78
2-3 1 4 7 4 1
2-4 2 4 12 5 0.69
3-5 2 3 4 3 0.11
4-5 4 6 8 6 0.44
4-6 3 5 7 5 0.44
5-6 0.5 1 1.5 1 0.33
3-7 6 8 16 9 2.78
6-7 3 5 13 6 2.78
5-7 5 7 15 8 2.78
5
4 6
5 6 6
3
1
1 2
4 8
3 5
3
7
9
Critical Path ( 1- 2 – 4 – 5 – 7)
The critical path will be ( 1- 2 – 4 – 5 – 7)
Te = 22 days
Variance (σ2) = 1.78 +0.69+0.44+2.78 = 5.69
σ = 2.385
Z = ( Ts – Te)/ σ = (25 – 22)/2.385 = 1.25
8 5 10
6
1
5 9 7
7
3 5
Step-I: The critical path is (1-2-4-6-7). The project duration
is 30 weeks. And the total direct cost Rs. 45,200/.
Indirect cost is Rs 2,000 per week.
8 5 10
6
1
5 9 7
7
3 5
8 5 10
2
1
5 9 7
7
3 5
The minimum cost slop (1-2). And it can crash in next step
3
6
2 4 6
4 5 10
2
1
5 9 7
7
3 5
4 5 10
2
1
5 9 7
5
3 5
4 5 7
2
1
5 9 7
5
3 5
4 5 7
2
1
5 9 7
5
3 5
(1-2), (2-4)
(5-6) 24 52,500 48,000 100,500
Activities Project Total Total Total Cost
Crashed direct cost Indirect cost
(Rs.) (Rs) (Rs)
_________________________________________________
(1-2), (2-4),
(5-6), (3-5) 23 53,700 42,000 95,700
(1-2), (2-4),
(5-6), (3-5),
(6-7) 20 56,400 40,000 96,400
(1-2), (2-4),
(5-6), (6-7),
(3-5), (4-6) 19.5 57,000 39,000 96,600
If the object is to minimize the total cost of the project, the
activities (1-2), (2-4),(5-6), (6-7), (3-5) is crashed and it
is a optimal solution and the cost is Rs 96,400.