Power Stations: Load Curves
Power Stations: Load Curves
Power Stations: Load Curves
Load Curves
Rethwan Faiz
EEE Department
Energy Requirements
• For Power plant design the first step is to
define the Energy Requirements that the plant
must meet.
Demand Factor
The building may not be using all the light points, power points and the lift at a time in
practice.
Assume that 300 lamps and 50 power points are working at a time.
So, the average load of the lamps and the power points = (300x60) + (50x500)
= 43 kW
The demand factor of the building is = (Avg.load/Max. Connected laod)
= (43 kW/90 kW)
= 0.581.
• The peak load is 13 MW but it is for around 1.5 hrs (19:00 – 20:30)
• But the load demands are different at other times of the day.
• It is correct to say that the maximum demand of the station for 1.5
hrs (19:00 – 20:30) is 13 MW. We have to mention a period for
which the load is considered.
Diversity of Load
• Consider that, a station supplies to the following categories of load:
– Category A (Industrial) = 5000 kW
– Category B (Cinema) = 900 kW
– Category C (Commercial) = 2000 kW
– Category D (Private) = 1000 kW
– Category E (Water works) = 1100 kW
• Let, between 7 pm to 8 pm, the consumer wants power. So, their resultant
maximum demand = 10,000 kW
• So, the station has to supply this huge 10,000 kW amount of power for a
very short time. During the other times of the day, the average load on the
station may be less than 50% and the station has to remain idle.
• The capital investment of the plant has not been put to best use and the
scheme will be uneconomical.
• But if the consumers are advised to diversify their loads or to ask for their maximum
demand at different times, the station operation can be made very economical.
• Consumer A (Industrial): They work in shifts and may be asked to fix the time of
their shifts. For e.g.,
– Shift 1 = 8 am to 8 pm not 11 am to 8 pm.
• So, at the time of peak load this category may have a maximum demand of 40%
only, i.e., 2000 kW.
• Consumer B, C and D cannot have that much of variations.
• Consumer E (Water works) can be told to fill up their tanks during 12 am to 4 am or
12 pm to 4pm.
• This value is always greater than the unity. For example, factors for
residential consumers are usually highest at about 5.0, whereas for
industrial consumers may have values as low as 1.3.
• Greater the GDF the lesser is the cost of the generation of power.
Because it refers lesser maximum demand which indicates lesser plant
capacity is required means capital investment on the plant is reduced
Peak Diversity Factor (PDF)
• The peak demand of a system is made up of the individual
demands of the devices that happen to be functioning at the
time of the peak.
• Let,
– C1, C1’, C1” … C1n = individual connected loads of group 1
– C2, C2’, C2” … C2n = individual connected loads of group 2
– d1 = demand factor of group 1
– d2 = demand factor of group 2
– D1 = GDF among the consumers of group 1
– D2 = GDF among the consumers of group 2
– M1 = max demand of group 1
– M2 = max demand of group 2
– r1 = PDF for group 1
– r2 = PDF for group 2
– Lm = system max demand
– L1, L2, L3, … Ln = demands of each type of consumers at
the time of system max demand.
Sum of Individual Maximum Demands
Group Diversity Factor
Actual Maximum Demand of Group
– r1 = M1 / L1
– So, L1 = M1 / r1
– Similarly, L2 = M2 / r2
– and LM = L1 + L2 + L3 + … Ln
Mathematical Problem
Example 30.1: A new housing development is to be added to the
lines of a public utility. There are 1000 apartments each having a
connected load of 4 kW, also stores and services are included of
the characteristics shown in the following tabulation.
Store or Service Connected kW Demand Factor (%)
1 Laundry 20 68
2 Churches 10 each 56
1 Restaurant 60 52
1 Bookstore 5 66
1 Dry Goods Store 7 76
2 drugstores 10 each 79
2 grocery stores 5 each 73
1 shoe store 2 67
1 clothing store 4 53
1 theater 100 49
• The demand factor of the apartments is 45%. The
GDF of residential load is for the system is 3.5,
the PDF is 1.4. The commercial load group GDF
is 1.5 and the peak diversity factor is 1.1.
Drugstores 2 10 20 79 15.8
Grocery stores 2 5 10 73 7.3
Shoe store 1 2 2 67 1.34
Clothing store 1 4 4 53 2.12
Theater 1 100 100 49 49
140.1
• Actual Max demand of the commercial group =
140.1 / 1.5 = 94 kW
The degree of variation of load over a period of time is measured by the load factor
which may defined as
L avg E / h
Load factor
L max L max
• if a load factor => 0 the curve approaches to L shape with very low or no load
during the major portion of time
• if a load factor => unity the curve approaches to a rectangular shape indication
high sustained load
Capacity Factor
Capacity Factor:
The extent of use of the generating plant is measured by the capacity factor also
called plant factor or use factor
• If during a given period a plant is kept fully loaded it is evident that it is used to
the maximum extent or operated at 100% capacity factor
• If no energy was produce the capacity factor would be 0%
L avg L max
Capcity Factor ( ) Load factor Utilization Factor Load factor
Cap Cap
Utilization Factor
Utilization Factor:
The utilization factor measures the use made of the total installed capacity of the
plant
L
Utilization Factor max
Cap
• A low utilization factor may mean that the plant is used only for standby
purpose or that the capacity has been installed well in advance of need
• A high utilization factor indicates the plant is probably most efficient in the
system
• In an isolated system a high utilization factor refers a good design with some
reserve capacity allowance
• It might be higher than unity which pointing towards that the loads have been
carried in excess of the rated capacity of the equipment
Mathematical Problem
Exercise: 30.4
The yearly duration curve can be considered as a straight line from 20,000 to
3,000kW. To meet this load 3 turbine generator units, 2 rated at 10,000kW each
and 1 at 5,000kW are installed. Determined:
i. Installed Capacity
ii. Plant Factor
iii. Maximum demand
iv. Load factor
v. Utilization Factor
Mathematical Problem
Solution:
The time has to be converted into hour format
From the graph the we can observe that the maximum load is 20,000kW (Lmax)
v. Utilization Factor
Class of Total Connected Demand Group Diversity Peak Diversity Maximum Maximum
Service Load (kW) Factor (%) Factor Factor Demand Demand Group
Public
100 35 1.6 1 35 21.88
Building
Apartment 1000 55 4 1.2 550 137.50
Hospital 200 45 1.5 1.05 90 60.00
Theater 150 60 1.6 1 90 56.25
Laundries 50 70 1.8 1.05 35 19.44
Residence 3000 40 4.5 1.2 1200 266.67
Stores 500 65 1.6 1.05 325 203.13
Offices 100 70 1.8 1.05 70 38.89
Lighting
600 100 1 1 600 600.00
(Street)
Foundry 3500 80 1.1 1.05 2800 2545.45
Boiler
4000 90 1.1 1.05 3600 3272.73
Factory
Hotel 700 25 1.8 1.2 175 97.22
Motor
5000 75 1.1 1.05 3750 3409.09
Factory
13320 10728.24
Mathematical Problem
/
Maximum Load (kW) Group Diversity Factor
Class of Total Connected Demand Group Diversity Peak Diversity Maximum Maximum
Service Load (kW) Factor (%) Factor Factor Demand Demand Group
Public
100 35 1.6 1 35 21.88
Building
Apartment 1000 55 4 1.2 550 137.50
Hospital 200 45 1.5 1.05 90 60.00
Theater 150 60 1.6 1 90 56.25
Laundries 50 70 1.8 1.05 35 19.44
Residence 3000 40 4.5 1.2 1200 266.67
Stores 500 65 1.6 1.05 325 203.13
Offices 100 70 1.8 1.05 70 38.89
Lighting
600 100 1 1 600 600.00
(Street)
Foundry 3500 80 1.1 1.05 2800 2545.45
Boiler
4000 90 1.1 1.05 3600 3272.73
Factory
Hotel 700 25 1.8 1.2 175 97.22
Motor
5000 75 1.1 1.05 3750 3409.09
Factory
13320 10728.24
Mathematical Problem
Exercise 30.2: An electrical railway system has such severely fluctuating loads that instantaneous
wattmeter reading do not define its load curve adequately. The readings of the following table
has taken from the station totalizing watt-hour meter at the times indicated. The station meter
constant is 10,000 to convert to kilowatt-hours.
Time Meter Reading Time Meter Reading
12pm 5595 2pm 5639
1am 5597 3 5643
6 5602 4 5648
7 5605 5 5654
8 5611 6 5661
9 5618 7 5667
10 5624 8 5672
11 5629 9 5676
12m 5633 10 5678
1pm 5636 12 5682
a.Plot the average hourly chronological and load duration curve
b.Plot the load-energy curve for the average hourly loads
c.Find the load factor based on the average hourly peak
d.If the instantaneous peak is 85MW, what is the load factor?
e.What is the utilization factor and capacity factor of the plant serving this load if its capacity is
100MW?
Mathematical Problem
kWhr = ( Present Reading – Previous Reading ) x Meter Constant
MW = kWhr / (1000 x hour duration)
Time Meter Reading Duration (Hours) kWhr MW
12pm 5595 0 0 0
1am 5597 1 20000 20
6 5602 5 50000 10
7 5605 1 30000 30
8 5611 1 60000 60
9 5618 1 70000 70
10 5624 1 60000 60
11 5629 1 50000 50
12m 5633 1 40000 40
1pm 5636 1 30000 30
2pm 5639 1 30000 30
3 5643 1 40000 40
4 5648 1 50000 50
5 5654 1 60000 60
6 5661 1 70000 70
7 5667 1 60000 60
8 5672 1 50000 50
9 5676 1 40000 40
10 5678 1 20000 20
12 5682 2 40000 20
Mathematical Problem
Time MW
12pm 0
1am 20
6 10
7 30
8 60
9 70
10 60
11 50
12m 40
1pm 30
2pm 30
3 40
4 50
5 60
6 70
7 60
8 50
9 40
10 20
12 20
Mathematical Problem
Mathematical Problem
10 => 10 X 24 = 240
30=> 15 X 10 = 150
430 + 150 = 580
40=> 10 X 12 = 120
580 + 120 = 700
50=> 10 X 9 = 90
700 + 90 = 790
60=> 10 X 6 = 60
790 + 60 = 850
70=> 10 X 2 = 20
850 + 20 = 870
Mathematical Problem
10 => 10 X 24 = 240
30=> 15 X 10 = 150
430 + 150 = 580
40=> 10 X 12 = 120
580 + 120 = 700
50=> 10 X 9 = 90
700 + 90 = 790
60=> 10 X 6 = 60
790 + 60 = 850
70=> 10 X 2 = 20
850 + 20 = 870
Mathematical Problem
c. Load Factor = Lavg/ Lmax
d. If Lmax = 85MW