RC Detailing
RC Detailing
RC Detailing
Er.T.RANGARAJAN,B.E,M.Sc(struct.engg),F.I.E,F
ACCE,LACI,LISSE,LIASE
According to USA President Herbert Hoover, who was an
engineer before he became a politician, said:
The great liability of the engineer …compared to men of other
professions……is that his works are out in the open where all
can see them.
His acts …..step by step …are in hard substances.
He cannot bury his mistakes in the grave like the DOCTORS.
He cannot argue them into thin air…..or blame the judge…..like
the LAWYERS.
He cannot, like the ARCHITECT, cover his figures with trees
and vines.
He cannot, like the politicians, screen his shortcomings by
blaming his opponents….and hope the people will forget. The
ENGINEER simply cannot deny he did it.
If his works do not work……he is damned.
A design engineer’s responsibility should include
assuring the structural safety of the design,
details, checking shop drawing.
Detailing is as important as design since proper
detailing of engineering designs is an essential
link in the planning and engineering process as
some of the most devasting collapses in history
have been caused by defective connections or
DETAILING. There are many examples explained
in the book" DESIGN AND CONSTRUCTION
FAILURES by Dov Kaminetzky.
Detailing is very important not only for the
proper execution of the structures but for the
safety of the structures.
Detailing is necessary not only for the steel
structures but also for the RCC members as it is
the translation of all the mathematical
expression’s and equation’s results.
GOOD DETAILING IS AS IMPORTANT AS
DESIGN AND PLANNING.
For the RCC members for most commonly used for buildings we can
divide the detailing for
1. SLABS-WITH OR WITHOUT OPENINGS.(RECTANGULAR,CIRCULAR,NON-
RECTANGULAR-PYRAMID SLAB,TRIANGULAR ETC)
-BALCONY SLAB,LOFT SLAB,CORNER SLAB etc
2. BEAMS- WITH OR WITHOUT OPENIGS.(SHALLOW & DEEP BEAMS)
3. COLUMNS.(RECTANGULAR,L-SHAPE,T-SHAPE,
CIRCULAR,OCTAGONAL,CROSS SHAPE etc)
4. FOUNDATIONS.
Detailing for gravity loads is different from the lateral loads specially for
the SEISMIC FORCES.
Apart from the detailing for the above there is a different detailing
required for the Rehabilitation and strengthening of damaged structures.
We will now dwell on the DETAILING OF MEMBERS FOR THE GRAVITY
AND SOME CODAL DETAILINGS AS PER IS CODE IS 13920 AND IS 4326
AS REQUIRED FOR SEISMIC FORCES.
DO’S-GENERAL
1. Prepare drawings properly & accurately if possible label each bar and show
its shape for clarity.
12”
I ¼”dia@12”c/c
1- ¼”dia@12”c/c
Cross section of retaining wall which collapsed immediately after placing of soil
backfill because ¼” rather than 1-1/4” dia. were used. Error occurred because
Correct rebar dia. Was covered by a dimension line.
2. Prepare bar-bending schedule , if necessary.
3. Indicate proper cover-clear cover, nominal cover or
effective cover to reinforcement.
4. Decide detailed location of opening/hole and supply
adequate details for reinforcements around the
openings.
5. Use commonly available size of bars and spirals. For
a single structural member the number of different
sizes of bars shall be kept minimum.
6. The grade of the steel shall be clearly stated in the
drawing.
7. Deformed bars need not have hooks at their
ends.
8. Show enlarged details at corners, intersections of
walls, beams and column joint and at similar
situations.
9. Congestion of bars should be avoided at points where members
intersect and make certain that all rein. Can be properly placed.
10. In the case of bundled bars, lapped splice of bundled bars shall
be made by splicing one bar at a time; such individual splices
within the bundle shall be staggered.
11. Make sure that hooked and bent up bars can be placed and have
adequate concrete protection.
12. Indicate all expansion, construction and contraction joints on plans
and provide details for such joints.
13. The location of construction joints shall be at the point of minimum
shear approximately at mid or near the mid points. It shall be
formed vertically and not in a sloped manner.
DO’S – BEAMS & SLABS:
1. Where splices are provided in bars, they shall be , as far as
possible, away from the sections of maximum stresses and shall be
staggered.
2. Were the depth of beams exceeds 750mm in case of beams without
torsion and 450mm with torsion provide face rein. as per IS456-
2000.
3. Deflection in slabs/beams may be reduced by providing
compression reinforcement.
4. Only closed stirrups shall be used for transverse rein. For members
subjected to torsion and for members likely to be subjected to
reversal of stresses as in Seismic forces.
5. To accommodate bottom bars, it is good practice to make
secondary beams shallower than main beams, at least by 50mm.
Do’s –COLUMNS.
1. A reinforced column shall have at least six bars of longitudinal
reinforcement for using in transverse helical reinforcement.-for
CIRCULAR sections.
2. A min four bars one at each corner of the column in the case of
rectangular sections.
3. Keep outer dimensions of column constant, as far as possible ,
for reuse of forms.
4. Preferably avoid use of 2 grades of vertical bars in the same
element.
DONOT’S-GENERAL:
1. Reinforcement shall not extend across an expansion joint and
the break between the sections shall be complete.
2. Flexural reinforcement preferably shall not be terminated in a
tension zone.
3. Bars larger than 36mm dia. Shall not be bundled.
4. Lap splices shall be not be used for bars larger than 36mm dia.
Except where welded.
5. Where dowels are provided, their diameter shall not exceed the
diameter of the column bars by more than 3mm.
6. Where bent up bars are provided, their contribution towards
shear resistance shall not be more than 50% of the total shear to
be resisted. USE OF SINGEL BENT UP BARS(CRANKED)
ARE NOT ALLOWED IN THE CASE OF EARTHQUAKE
RESISTANCE STRUCTURES.
The building plan DX-3 shows the slabs
in different levels for the purpose of
eliminating the inflow of rainwater into
the room from the open terrace and also
the sunken slab for toilet in first floor.
The building plan DX-A3 is one in which
the client asked the architect to provide
opening all round.
Refer the 3d
elevation
Different shapes of slabs used in the
buildings. 6”depression for OT &
9” for sunken slabs.
19’-6”
SLABS:
It is better to provide a max spacing of 200mm(8”) for main bars
and 250mm(10”) in order to control the crack width and spacing.
crack
INCORRECT
Ldt
CLOSE
STIRRUPS
Ldt/2
Ld/2 Ld/2
CORRECT
Ld
NON PRISMATIC BEAM
crack
INCORRECT
Ldt
CLOSE
STIRRUPS
Ldt/2
Ld/2 Ld/2
CORRECT
Ld
GRID BEAM
INCORRECT
Close rings
1.5d 1.5d
300
300
d
Main beam
INCORRECT
Secondary beam
Close rings
1.5d 1.5d
300
300
d
60degree
1/4OR INCORRECT
1/5 SPAN
Ld
Ld
LINE OF CRACK
d/2
t
t
d/2
1.5d d/2+d/2Cot(t)
CORRECT
continuous beam Span/4 Span/4
Span/4
Span/4 Span/4
incorrect
Span/4 Span/4
1.5d
1.5d 1.5d
correct
CONTINUOUS BEAM
SPAN/4 SPAN/4 SPAN/4
INCORRECT
L1 .15L1 .15L2 L2
CORRECT
NONPRISMATIC
SECTION OF BEAM
CRACK
D
D
D
INCORRECT
CLOSE RING
D
CORRECT
D
CLOSE RING
CANTILEVER BEAM PROJECTING
FROM COLUMN
COLUMN
INCORRECT
NOT LESS
THAN 0.5Ast NOT LESS THAN GREATER OF 0.5L OR Ld
50mm
Ld
0.25Ast
COLUMN
CORRECT Ld/3
SLOPING BEAM
CRACK
Ld
Ld
CORRECT
HAUNCH BEAMS
CRACK CRACK
INCORRECT
Ld Ld
CORRECT
Ld L/8 TO Ld
L/10 L/8 TO
L L/10
STRESSES AT CORNERS C-COMPRESSION
T-TENSION
C
t
C CRACK
t
RESULTANT TENSILE STRESS FOR
ACROSS CORNER(ONE PLANE)
CRACK
c
t
c
SHEAR AND TORSION REIN. IN
BEAMS Stirrups taken round outermost
bars spacing<=x1
<=(x1+y1)/4
<=300mm
Min 0.2%bd to control deflection as
well as for seismic requ.
INCORRECT
d y1
Skin rein.10dia is D
required when depth 100 to
D-n>500mm
exceeds 450mm(0.1% 200mm
x1 CORRECT
b
CANTILEVER BEAM WITH
POINT LOAD
Shear rein.
INCORRECT
2/3d
d Ld
CORRECT
Ld
Extra ties
INCORRECT
opening
crack crack
Closed stps
Closed stps
for d/2
for d/2
Ld
INCORRECT
2”max
CLOSED STPS
U TYPE BARS
Ld
IN TENSION-Ld
CORRECT
SPLICE DETAIL FOR COLUMN
COVER
CLOSE
TIES @S/2 SLOPE 1:6
S-SPACING
CORRECT
INCORRECT
REDUCTION
COLUMN BOTH
SIDES
INCORRECT
SPLICE
SLOPE 1:8 FROM
BEAM BOTTOM 3NO.CLOSE TIES
CORRECT
TERMINATION OF COLUMN BARS INSIDE BEAM
INCORRECT
Ld
CORRECT
*COL.CORE HAS TO
BE CONFINED BY
EQ REGION-BEAM-COL JN-EXTERIOR CIRCULAR OR
RECTANGULAR TIES
IN ACCORDANCE
WITH END REGION
SPACING OF
LATERAL
TIES <=d/2
COL.
END REGION
CORE*
SPACING OF
LATERAL
TIES
<=100mm
INCORRECT CORRECT
SPACING OF
LATERAL
TIES <=d/2 BEAM COL. JUNCTION-EQ
REGION
COLUMN DETAILS IN EQ REGIONS
incorrect
First stirrups correct
50mm from beam
face
END
REGION END REGION-h/6 or D or
450MM whichever is
greater
h
b d
END
REGION END
REGION
INCORRECT
50mmmax
CONTINUOUS BARS NOT LESS THAN ¼
AREA OF BARS AT COL.FACE CORRECT
Ld
stp@maxd/2 stp@maxd/2
2d 2d
2d Stirrup spacing=d/4 or
100mm or 8dia which
ever is the least
FOOTING-DETAILS(INDEPENDENT)
INCORRECT COLUMN
BARS
STARTER
NATURAL
BARS
G.L
COVER TO
STARTER
Lb
3” SIDE COVER
Ldt
Min.300
Ldt COVER50mm
IF p.c.c below
CORRECT or 75mm
TYPICAL REIN DETAILS OF
INCORRECT HAMMER FOUNDATION BLOCK
CORRECT
Ld
Ld
SECTION OF TRENCH
INCORRECT
CRACK
CORRECT
Ld
Ld
Ld
STAIRCASE-WITH WAIST SLAB
INCORRECT
Extra bar
Ld(min)
Ld(min)
Ld(min)
CORRECT
SLABLESS STAIRCASE
Dist.
Alternate 1
Main bar
Main bar
SLABLESS STAIRCASE
Main bar
L=horizontal span
Alternate 2
A=0.25L
DEVELOPMENT LENGTH OF BARS
FOR A CONCRETE GRADE M20 &STEEL STRENGTH Fy=415
2 10 470.0 376.0
3 12 564.0 451.0
4 16 752.0 602.0
5 20 940.0 752.0
6 22 1034.0 827.0
7 25 1175.0 940.0
8 28 1316.0 1053.0
9 32 1504.0 1203.0
Flange Width
Reinforcement:
• Minimum reinforcement:
• 0.25% of the gross area in longitudinal & transverse direction
• It shall be provided in two curtains, if
• Shear stress > 0.25 √fck
• Wall thickness > 200mm
Diameter:
Lw/5 or
3 tw or
450mm whichever is less
Where,
Lw =Horizontal length of wall
tw =Thickness of wall web
Reinforcement detail:
• Vertical reinforcement
Shall not be < 0.8%
Shall not be > 6%
Practical upper limit = 4%
Anchorage:
• Anchor near the edges (or)
• Anchor in the confine core of boundary element
Splicing:
• Should be avoided as far as possible in yielding zone
Lateral Ties:
Spacing:
• Shall not exceed 150mm c/c
Seismic inertia forces are transferred through various beams and columns to the ground.
Correct building components need to be made ductile.
Failure of beam causes localized effect.
Failure of column causes instability of whole building.
Beams are made ductile weak links than columns.
Based on the performance of RCC structures
designed as per IS 4326:1976
• Deficiencies in IS 4326 are identified
• Corrected in IS 13920
Note
• IS 4326:1976 – Code of practice for earthquake resistant design and construction of
buildings.
Provide adequate toughness and ductility to RCC buildings
• To resist severe earthquake shocks without collapse.
Beam
Ast3
Top and bottom bars of beam (in an external
joint) – Cl.6.2.5
• Crossties with 900 hook at one end and 1350 hook at other end will be sufficient.
Shear Design by Va Vb Stirrups Spacing of stirrups required Spacing specified Spacing provided
Max. Spacing Min. Spacing
IS 456 (from analysis) 222 kN 219 kN 2L- 8 mm 0.87 fy Asv d Not more than Not less than 220 mm
Sv = = 220 mm
Vus 0.75d = 414 mm -
300 mm
IS 13920 (from analysis) 222 kN 219 kN 2L- 8 mm 0.87 fy Asv d Not more than Not less than 135 mm
Sv = = 220 mm
' Vu' Calculation not Vus d / 4 = 138 mm 100 mm
Considered 8 db = 200 mm
IS 13920 329 kN 353 kN 2L- 8 mm 0.87 fy Asv d Not more than Not less than 100 mm
Sv = = 101 mm
' Vu' Calculation Vus d / 4 = 138 mm 100 mm
Considered 8 db = 200 mm
The spacing of hoops over a length of ‘2d’ at either
end of beam shall not exceed
• d/4
• 8 times the dia. Of smallest longitudinal bar, but not less than 100mm.
First hoop
• At a distance not exceeding 50mm from the joint face.
• The ratio of shortest cross sectional dimension to the perpendicular dimension shall not be
less than 0.4
Remarks (DR.Cl.C.7.1.2)
• Problems in columns having small width,
300mm
Splicing
• Provided only in the central half of the member length.
• Proportioned as a tension splice.
• Hoops provided over the entire splice length at spacing not exceeding 150mm c/c.
• Not more than 50 % of bars shall be spliced at one section.
Rectangular hoops
• Closed stirrup having 1350 hook with a 10 times dia. extension (but not < 75mm).
Spacing between parallel legs <300mm
• Parallel legs of rectangular hoops shall be provided.
• Shall be provided
i. Over a length ‘l0’ from each joint face, towards
mid span.
iii. 450mm.
When column terminates into a footing or mat
(Cl.7.4.2)
• Special confining reinforcement shall extend at least 300mm into the footing or mat.
Half the special confining reinforcement shall be provided at the end of the column.