Line Protection: Substation Automation Products
Line Protection: Substation Automation Products
Line protection
Section 4
1. Neutral
2
conductor
2 1
2 2. Phase
conductors
3. Tower
3 4. Tower footing
5. Earth
5 4
Section 4
1. Phase to
ground
2. Phase to
phase
3. Three phase
4. Phase to
3 phase to ground
5. Three phase to
2 ground
1
Section 4
© SA-T Training
1MRG005475
Slide 4
Section 4
Section 4
Section 4
Section 4
Section 4
WA1 Section 4
QB1 QB2
Remote Line CT
21FL FL 87L 3Id/I>
LMB RFLO L3C PDIF
QB9
MET Usqi MET P/Q 51/67 3I> 21
60FL Z<
VTS
V MSQI CV MMXN OC4 PTOC ZMQ RFUF
SDD PDIS
QC9
DFR/SER DR MET W/Varh MET I MET Isqi
DRP RDRE ETP MMTR C MMXU C MSQI
QB1 QB2
Remote Line CT
21FL FL 87L 3Id/I>
LMB RFLO L3C PDIF
QB9
MET Usqi MET P/Q 51/67 3I> 21
60FL Z<
VTS
V MSQI CV MMXN OC4 PTOC ZMQ RFUF
SDD PDIS
QC9
DFR/SER DR MET W/Varh MET I MET Isqi
DRP RDRE ETP MMTR C MMXU C MSQI
ZL
RL
Section 4
Under impedance protection - resistive fault
Measured impedance ZL
Zm = ZLf + Rf
Rf
R
RL
Section 4
Under impedance protection - resistive fault
Rf
ZL
Rf
R
RL
Section 4
Under impedance protection - resistive fault
I Z1
L1
R5 R4 R3 R2 R1 R1
ZN
Z1
L3
Z1
R2
N
I ZN
R3
R4
R5
Section 4
Phase to phase faults
arc resistance
Reach (settings X1, R1)
(Setting RFPP)
L1 Z1
L2 Z1
L3 Z1
L1
jX
R1+j X1
RFPP
φ = tan-1 XR
(R1, X1)
2
RFPP
2
L2
R1+j X1
φ =LineAng
RFPP
R
2
RFPP
R1+
ZM measures the ohm/phase impedance to the fault 2
L1
R1+j X1 RFPP
jX φ = tan-1 XR
2
(R1, X1)
L2
R1+j X1 RFPP RFPP
2 2
L3
R1+j X1
φ =LineAng
RFPP
R
2
RFPP
ZM measures the ohm/phase impedance to the fault R1+
2
L1 Z1
L2 Z1
Rf
L3 Z1
N ZN
RFPE
N
α = tan -1
2X1+X0
2R1+R0
Z0 - Z1
KN =
3Z1
Section 4
Phase to earth characteristic
Settings in PST
X1PE = X1
R1PE = R1
X0PE = X0
R0PE = R0
RFPE = RFPE
Section 4
Example of ZM settings
Z1 = (3,2+j36) Ω
Ip Z0 = (13+j145) Ω
1200 A/1 A
TRIP/CLOSE
Bus A
Bus B
Is 400 kV/100 V
Settings of Z zones
Z1 = 85% of line (fw) 0 ms
Z2 =125% of line (fw) 400 ms
Z3 = 150% of line (rv) 800 ms
Z4 = 200% of line (fw) 1000 ms
Z5 = OFF
Section 4
Settings for ZM01, 85% of line (fw) 0 ms
Settings are in primary, so there is no
need to convert primary settings into
secondary.
ZM01 is switched On
Directional is set FW
0,85(3,2+j36) = (2,72+j30,60) Ω
0,85(13+j145) = (11,05+j123,5) Ω
ZM02 is switched On
Directional is set FW
1,25(3,2+j36) = (4,0+j45,0) Ω
1,25(13+j145) = (16,25+j181,25) Ω
ZM03 is switched On
Directional is set FW
4,0(3,2+j36) = (1+j144,0) Ω
4,0(13+j145) = (1+j181,25) Ω
R1 and R0 are set low as the line angle
not is consistent (line angle almost 90
degrees)
ZM04 is switched On
Directional is set RV
0,1(3,2+j36) = (0,32+j3,6) Ω
0,1(13+j145) = (1,3+j14,5) Ω
ZM05 is switched On
Directional is set RV
1,3(16,25+j181,25) = (21,13+j235,62) Ω
A B
STZ2 400 ms
STZ1
Carrier send
ZCPSCH
tCoord=0
ZM02-START CACC
t TRIP To trip function
Carrier receive CR AND
ZMQAPDIS ZM01
A B
STZ2 400 ms
STZ1
Carrier send
ZCPSCH
ZM02-START tCoord =0
CACC
t TRIP To trip function
Carrier receiveCR AND
ZMQAPDIS ZM05, T5
ZMQAPDIS ZM02, T2
ZMQAPDIS ZM01
A B
ZMQAPDIS ZM05, T5
ZMQAPDIS ZM02, T2
ZMQAPDIS ZM01
ZCPSCH
ZM02-START tCoord≠ 0
CACC
t TRI To trip function
Carrier receiveCR AND P
Pre-fault
V=0
I=0
At closing!
Fault
Vf If
(small) V = Fault voltage (Vf)
I = Fault current (If)
© SA-T Training
1MRG005476
Slide 40
Section 5
What happens seen from the IED
U
I Energized line
Pre-fault
U = High voltages
t I = Load current
Fault
Fault voltages
Fault currents
Pre-fault Fault
© SA-T Training
1MRG005476
Slide 41
Section 7
Fuse failure
U prim OK U prim OK
Iprim OK Iprim OK
U sec OK U sec 0
I sec OK
I sec OK
0
Z sec OK Z sec 0 TRIP !
I sec
© SA-T Training
1MRG005478
Slide 42
Section 4
Line differential protection
© SA-T Training
1MRG005475
Slide 43
Line differential protection
Kirchhoff's current law
© ABB
8/17/20 | Slide
44
Line differential protection
Design Criteria
© ABB
8/17/20 | Slide
45
Line differential protection
Design Criteria
Master-master or Master-slave
The nework configuration does not matter for differential protection and enables us
to protect complex lines that under impedance would not be able to protect.
© ABB
8/17/20 | Slide
46
Line differential protection
Synchronizing of internal clock, with Echo-timing
Time difference
© ABB
8/17/20 | Slide
47
Line differential protection
CT Saturation
Primary current
Secondary current
© ABB
8/17/20 | Slide
48
Line differential protection
CT Saturation
CT Saturation:
Primary current
Secondary
current
Differential
current
© ABB
8/17/20 | Slide
51
Section 4
© SA-T Training
1MRG005475
Slide 52