Week 5 Lectures: Advanced Variance Analysis
Week 5 Lectures: Advanced Variance Analysis
Dr Akanga
www.bournemouth.ac.uk
Learning Outcomes
www.bournemouth.ac.uk
Recall
www.bournemouth.ac.uk
Currently Attainable Standard
Costs
• These standards represent those costs that
should be incurred under efficient operating
conditions. They are standards that are
difficult, but not impossible, to achieve.
Attainable standards are easier to achieve
than ideal standards because allowances
are made for normal spoilage, machine
breakdowns and lost time. Attainable
standards provides the best norm to which
actual costs should be compared.
www.bournemouth.ac.uk
Standard costing and
management by exception
• Standard costs when set are usually average unit
costs. Hence actual results will vary to some extent
above the average. These differences (or variances)
should only be reported if there is significant
difference between actual and standard.
• This costing therefore enables the principle of
management by exception to be practised.
• Management by exception is defined by CIMA as the
practice of concentrating on activities that require
attention and ignoring those which appear to be
conforming to expectations.
www.bournemouth.ac.uk
Setting standards costs
www.bournemouth.ac.uk
Managing Costs
Standard Actual
cost cost
Comparison between
standard and actual
performance
level
Cost
variance
www.bournemouth.ac.uk
Variance Analysis
www.bournemouth.ac.uk
Variances to be analysed
Sales
Direct Direct
Materials Labour
Manufacturing
Overheads
www.bournemouth.ac.uk
1. Direct materials
Price Quantity
Standard
Actual
Purchases Production
www.bournemouth.ac.uk
Direct Materials Cost
Variances
• Total Direct Material Cost Variance =
SP SQ
1. Price Variance =
(Standard Price – Actual Price) × Actual Quantity
(SP – AP) × AQ
2. Usage Variance =
(Standard Quantity – Actual Quantity) × Standard
Price
(SQ – AQ) × SP
www.bournemouth.ac.uk
Material Price Variance
www.bournemouth.ac.uk
Summary
www.bournemouth.ac.uk
Example 1
www.bournemouth.ac.uk
Example 1 Solution
www.bournemouth.ac.uk
Example 1 Solution Cont.
www.bournemouth.ac.uk
Example 1 Solution Cont.
a.£170 unfavourable.
b.£ 170 favourable.
c.£ 800 unfavourable.
d.£ 800 favourable.
www.bournemouth.ac.uk
2. Direct Labour
Rate Hours
Standard
Actual
HR Production
www.bournemouth.ac.uk
Direct Labour Cost Variances
www.bournemouth.ac.uk
Direct Labour Cost Variances
(SH – AH) × SR
www.bournemouth.ac.uk
REASONS FOR LABOUR VARIANCES
www.bournemouth.ac.uk
Example 2 Solution Cont.
a.£310 unfavourable.
b.£ 310 favourable.
c.£ 300 unfavourable. LRV = AH(SR - AR)
LRV = 1,550 hrs(£10.00 -
d.£ 300 favourable. £10.20)
LRV = £310 unfavorable
www.bournemouth.ac.uk
Example 2 Solution Cont.
a.1,550 hours.
b.1,500 hours.
c.1,700 hours. SH = 1,000 units × 1.5 hours per unit
SH = 1,500 hours
d.1,800 hours.
www.bournemouth.ac.uk
Example 2 Solution Cont.
a.£510 unfavourable.
b.£510 favourable.
c.£500 unfavourable.
d.£500 favourable.
www.bournemouth.ac.uk
3. SALES VARIANCES
www.bournemouth.ac.uk
SALES VARIANCES (cont’d)
www.bournemouth.ac.uk
Example 1
• Calculate the:
• Budgeted sales
• Actual sales
• Sales volume variance
• Sales price variance
• Over all variance
www.bournemouth.ac.uk
Example 1 Solution
a)£8,000 F
b)£8,000 A SVV = (ASQ - BSQ)*SC
SVV = (12,000- 10,000)(£11- £7)
c)£8,500 F SVV = £ 8,000 favorable
d)£8, 500 A
www.bournemouth.ac.uk
Example 1 Solution
www.bournemouth.ac.uk
Example 2
SPV = (AP-SP) x AQ
= (12.50-£12.00)*7,700
= £3,850 (F)
SVV = (AQ-BQ)X SC
= (7,700 – 8000) x (£12-£7)
= £1,500 (A)
www.bournemouth.ac.uk
4. Manufacturing Overhead
Variances
• Whereas direct materials and direct labour are
variable costs, manufacturing overhead is
comprised of both variable and fixed cost
components. Therefore, the analysis of the
overhead cost variance differs somewhat from
the analysis of materials and labour variances.
• There are two elements of the overhead cost
variance:
1. The Variable Overhead Variance; and
2. The Fixed Overhead Variance.
www.bournemouth.ac.uk
Manufacturing Variable
Overhead Variances
• Total Var. Overhead Variance = SC – AC
• Standard Cost = SR × SH
• Actual Cost = AR × AH
• Rate Variance = (SR – AR) × AH
• Efficiency Variance = (SH – AH) × SR
www.bournemouth.ac.uk
Manufacturing Fixed Overhead
Variances
• Total Fixed Overhead Costs Variance =
www.bournemouth.ac.uk
Example
www.bournemouth.ac.uk
Solution
www.bournemouth.ac.uk
5. Variance Report: An Illustration
Example
• The following table summarises the standard costs to
be incurred in manufacturing one unit. It is planned that
the level of production would be 700 units in total.
Total favourable cost variance (actual costs are less than standard) £100
www.bournemouth.ac.uk
Materials Price and Quantity
Variances
• In establishing the standard material cost for
each unit of product, two factors are considered:
• (1) the quantity of materials required and
• (2) the prices that should be paid to acquire
these materials.
• Therefore, a total cost variance for materials
can result from differences in the quantities
used, in the prices paid to suppliers, or a
combination of these factors.
www.bournemouth.ac.uk
• Total Direct Material Cost Variance =
www.bournemouth.ac.uk
Variances £ £
1: Direct Material:
Price Variance £9 000 (F)
---------
Usage Variance ---------
£5 400 (A)
£3 600 (F)
----------
2: Direct Labour:
Rate Variance
Efficiency Variance
Total Variances
www.bournemouth.ac.uk
Labour Rate and Efficiency
Variances
• In establishing the standard labour cost for
each unit of product, two factors are
considered:
• (1) the time required to produce each unit, and
• (2) the rate that should be paid to each hour.
• Therefore, a total cost variance for labour
can result from differences in the hours
required, in the rates paid, or a combination
of these factors.
www.bournemouth.ac.uk
Labour Rate and Efficiency
Variances
• Total Direct Labour Cost Variance = Standard Costs – Actual
Costs
• Standard Cost = SR × SH
= £12
600 units
1.5 hours × --------------
--- × ( ------------- )
= £12 × 900 hours = £10 800
• Actual Cost = AR × AH -
=
£13 1 080 hours =
----- × --------------------- £14 040
Total Direct Labour Variance = - £3 240
Adverse
Variance
www.bournemouth.ac.uk
Labour Rate and Efficiency
Variances
• This adverse variance of £3 240 is then split up into two
subsidiary variances as follows:
Total Variances
www.bournemouth.ac.uk
Manufacturing Overhead
Variances
• There are two elements of the
overhead cost variance:
1. The Variable Overhead Variance; and
2. The Fixed Overhead Variance.
www.bournemouth.ac.uk
Variable Overhead Variance
Total Variances
www.bournemouth.ac.uk
Fixed Overhead Variance
£100
Total Variances ----------
(F)
www.bournemouth.ac.uk
Mix and Yield Variances:
Materials and Labour
• Mix variance: created whenever the
actual mix of inputs differs from the
standard mix
www.bournemouth.ac.uk
Mix and Yield Variances:
Materials and Labour
• Combining two or more mix of raw materials to
affect yield
• Start by determining the estimated cost of
different raw materials and the mix that
minimises output per unit cost while still
meeting standard requirements
• Changes in prices of raw materials can lead to
deviations in the standard mix of materials thus
affect yield and output per unit cost
www.bournemouth.ac.uk
Direct Materials Mix Variance
• (AQSM – AQAM)*SP
www.bournemouth.ac.uk
Material Yield Variance
www.bournemouth.ac.uk
Material Yield Variance
• (AYAQ – SYAQ)*SC
www.bournemouth.ac.uk
Material Mix and Yield
Variances: An Example
• XYZ Company Ltd. has established the following
standard mix for producing 9 Litres of product A
• (Notice that the table does not give standard cost
information per unit of output but instead it gives
standard information per 9 units of output)
• 5 Litres of material x at £7 per litre 35
• 3 Litres of material y at £5 per litre 15
• 2 Litres of material z at £2 per litre 4
54
• A standard loss of 10% of input is expected to occur.
Actual input was.
www.bournemouth.ac.uk
Material Mix and Yield
Variances: An Example
• 53000 litres of material x at £7 per litre 371,000
• 28000 litres of material y at £5.30 per litre 148,400
• 19000 litres of material x at £2.20 per litre 41,800
561,200
• Actual output for the period was 92,700 litres of
product A.
• Required
• Compute the direct material mix variance and direct
material yield variance.
www.bournemouth.ac.uk
Solution
www.bournemouth.ac.uk
Causes of Variances
www.bournemouth.ac.uk
Causes of Variances
www.bournemouth.ac.uk
Sales mix and yield variances
www.bournemouth.ac.uk
Sales-quantity variance
www.bournemouth.ac.uk
a nk
T h
u!
yo
www.bournemouth.ac.uk
Reading List
www.bournemouth.ac.uk