Time Planning: Chapter # 2
Time Planning: Chapter # 2
Chapter # 2
5. Reviewing progress
The Most Important Step:
priorities
It is important to continually review your planning
strategy to make sure that it is up to date (an ineffective
5. Reviewing time manager allows all of their priority points to slide
progress towards the top right hand corner of their graph when
everything is urgent and everything needs to be done
yesterday!). Try to avoid this
Project scheduling is a mechanism to communicate what
tasks need to get done and which organizational resources
Project will be allocated to complete those tasks in what timeframe.
Risk Identification
Increase Productivity
Scheduling
Identify Problems / Solutions
Team Motivation
Why activity planning Activity Planning will help to:
Why activity Produce a detailed schedule showing which staff carry out each activity
g?
Precedence analysis
Things to learn Gantt Charts
PERT / CPA
Decides what activities must be carried out before
Precedence particular activity can start.
Gantt Charts They are very useful for use on less complex projects.
planning Developed by
DuPont Inc in the
Models
Late fifties early sixties(1958) to facilitate
2 d
Network a
e 5 g
planning Start 1
b
5 End
3 h
c
models f 5
4
Activity
A specific task, uses resources takes time to
complete
Terminology Event
The result of completing an activity
Networks d b 2 days
e b 5 days
f c,d 8 days
How to start …..
a 2
On Arrow start
1
b
Networks
3
What not to do
c
a 2 4
On Arrow start 1
b
Networks d 5
3
e
6
A better way …
c
a 2
Continue… start 1
b
d
3
e
It is then less confusing that c & d go to the same event …
but what about e & f ?
c f
Continue… a 2 4 6
start 1
b d
e
3 5
The completed on arrow network ….
c
a 2 4
f
Continue…
start
1 d
b 5 end
e
3
Another on arrow network to draw
Tasks Precedence Time
a - 6 weeks
b - 4 weeks
c a 3 weeks
Assignment
d b 4 weeks
e b 3 weeks
f - 10 weeks
g e,f 3 weeks
h c,d 2 weeks
Tasks Precedence Time
a - 6 weeks
b - 4 weeks
c - 3 weeks
d a 4 weeks
Assignment e b 3 weeks
f b 2 weeks
g c 3 weeks
h d,e 2 weeks
i f 1 week
j g,i 2 weeks
Thank You