Project Management
CPM/PERT
Exercise-1
Draw network diagram from following activities and
find critical path and total slack of activities
Activity Time in Days Preceding
Activity
A 5 -
B 6 A
C 5 B
D 4 A
E 3 D
F 4 C,E
Exercise-2
Draw network diagram from following activities and find critical path
and total slack of activities
Activity Preceding Activity Duration
A - 15
B - 20
C A 25
D A 10
E B 15
F B 20
G D,E 20
H D,E 30
I D,E 15
J C,G 10
K F,I 20
Exercise-3
Draw network diagram from following activities and find critical path
and total slack of activities
Activity Preceding Activity Duration
A - 13
B A 8
C B 10
D C 9
E B 11
F E 10
G D,F 8
H E 6
I H 7
J G,I 14
K J 18
Exercise-3
Activity Optimistic Most likely Pessimistic
Sequence time time time
1-2 20 30 46
1-3 9 12 21
2-3 3 5 7
2-4 2 3 4
3-4 1 2 3
4-5 12 18 24
1. Draw a PERT diagram
2. Calculate the project duration
3. Mark the critical path
4. Find the probability the project will be completed in 50days
Exercise-4
Activity Optimisti Most Pessimistic
Sequence c time likely time time
1-2 5 8 10
1-3 18 20 22
1-4 26 33 40
2-5 16 18 20
2-6 15 20 25
3-6 6 9 12
4-7 7 10 12
5-7 7 8 9
6-7 3 4 5
1. Draw the network diagram of activities and determine the critical path
2. The probability of an even occurring at the excepted completion
date if the original scheduled time of completing the project is 41.5 weeks
3. The duration of the project that will have 95 percent chance of being completed.