Project Management: Cpm/Pert

This document discusses project management techniques like critical path method (CPM) and program evaluation and review technique (PERT). It provides three examples of network diagrams for projects with multiple activities and dependencies. For each example, it asks to draw the network diagram, identify the critical path, and calculate total slack and project duration. It also provides examples of network diagrams with optimistic, most likely, and pessimistic times to calculate project duration probabilities.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
53 views68 pages

Project Management: Cpm/Pert

This document discusses project management techniques like critical path method (CPM) and program evaluation and review technique (PERT). It provides three examples of network diagrams for projects with multiple activities and dependencies. For each example, it asks to draw the network diagram, identify the critical path, and calculate total slack and project duration. It also provides examples of network diagrams with optimistic, most likely, and pessimistic times to calculate project duration probabilities.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 68

Project Management

CPM/PERT
Exercise-1
Draw network diagram from following activities and
find critical path and total slack of activities

Activity Time in Days Preceding


Activity
A 5 -
B 6 A
C 5 B
D 4 A
E 3 D
F 4 C,E
Exercise-2
Draw network diagram from following activities and find critical path
and total slack of activities

Activity Preceding Activity Duration


A - 15
B - 20
C A 25
D A 10
E B 15
F B 20
G D,E 20
H D,E 30
I D,E 15
J C,G 10
K F,I 20
Exercise-3
Draw network diagram from following activities and find critical path
and total slack of activities

Activity Preceding Activity Duration


A - 13
B A 8
C B 10
D C 9
E B 11
F E 10
G D,F 8
H E 6
I H 7
J G,I 14
K J 18
Exercise-3

Activity Optimistic Most likely Pessimistic


Sequence time time time
1-2 20 30 46
1-3 9 12 21
2-3 3 5 7
2-4 2 3 4
3-4 1 2 3
4-5 12 18 24

1. Draw a PERT diagram


2. Calculate the project duration
3. Mark the critical path
4. Find the probability the project will be completed in 50days
Exercise-4
Activity Optimisti Most Pessimistic
Sequence c time likely time time
1-2 5 8 10
1-3 18 20 22
1-4 26 33 40
2-5 16 18 20
2-6 15 20 25
3-6 6 9 12
4-7 7 10 12
5-7 7 8 9
6-7 3 4 5

1. Draw the network diagram of activities and determine the critical path
2. The probability of an even occurring at the excepted completion
date if the original scheduled time of completing the project is 41.5 weeks
3. The duration of the project that will have 95 percent chance of being completed.