ARC 441 - Spec-05 - Brick Work

Download as ppt, pdf, or txt
Download as ppt, pdf, or txt
You are on page 1of 14

General Brick Work Construction

Scope of work:

• The work covered under this specification pertains


to procurement of best quality locally available
stock bricks

• and workmanship in buildings walls of various


thicknesses in strict compliance with the
specifications and applicable drawings.
Materials:

• Brick shall be best quality locally available stock


bricks and samples shall be got approved by the
Engineer-in charge before incorporation in the work
on large scale and maintain the same for the entire
work.
• The nominal size of bricks shall be 23 cm x 11.5 cm x
7.5 cm (9"x4.5”x2.75”).
• Permissible tolerance on dimensions shall be +/-3
mm in length & +/- 1.5 mm in width/thickness.
• If the plastering to be done is more than the
specified thickness to bring the plaster surface to
perfect line and level with adjoining columns, beams,
walls etc., the contractor shall be responsible to
provide more thickness of plaster at his own cost and
nothing extra will be paid on this account.
• In case the size of bricks used in the work, found
more than the permissible, the contractor shall chip
out the exposed edges of bricks up to the required
level of wall to receive specified thickness of plaster.

• Minimum crushing strength shall not be less than 35


Kg/cm² and water absorption shall not be more than
15% by the weight.

• Bricks shall be thoroughly soaked in water before


using till the bubbles cease to come up.
• No half or quarter brick shall be used except as
closer.

• The closers shall be cut to required size and used


near the end of the walls.

• The walls shall be raised truly to plumb.

• The type of bond to be adopted shall be properly


done (Stretcher/English/Flemish), but vertical joints
shall be laid staggered.
Brick bonds
Workmanship:

• Four courses of brickwork with four joints should not


exceed by more than 40mm. (1.6 inch) the same
bricks piled one over the other without mortar.
• Brickwork shall not be raised more than 10 courses a
day unless otherwise approved by the Engineer-in-
charge.
• The brickwork shall be kept wet for at least 10 days.
• Brickwork shall be uniformly raised around and no
part shall be raised more than 1.0 meter above
another at any time.

• All joints shall be thoroughly flushed with mortar of


mix as specified in the schedule of quantities, at
every course.

• Care shall be taken to see that the bricks are bedded


effectively and all joints completely filled to full
depth.
• The surface of brickwork shall be cleaned down and
watered properly before the mortar sets.

• The adhesion between the brick masonry surface


and the concrete surface of columns, beams, lintels
etc. should be proper by ensuring that the concrete
surface coming in contact with brick masonry is
chipped, cleaned and cement is applied so that
proper bond is achieved between the two dissimilar
materials.
• The mortar should completely cover the bed and
sides of the bricks.

• Proper care should be taken to obtain uniform


mortar joint throughout the construction.

• the walls should be raised uniformly in proper,


approved bond.

• All the courses shall be laid truly horizontal and


vertical.
• Deviation shall not exceed 6 mm per 3m height.

• Deviation from position shown on plan of any


brickwork shall not exceed 12.5mm.
• The rates for brickwork shall include the cost of the
following:

1. Providing and fixing necessary single or double


scaffolding and removing the same after the works
are completed.

2. Watering, curing, and lifting of materials to any


height.

3. Raking out of joints to receive plaster.


4. Forming slab sittings, cutting or leaving holes for
windows, doors, sills, switch boxes etc.

5. Making holes to any depth due to conduit pipes,


bolts, switch and plug boxes etc.

6. Bedding pre-cast lintels on walls.

You might also like