Managing Construction Projects
Managing Construction Projects
Debopam Roy
NICMAR, Pune
Global Construction Industry
2nd largest industry after Agriculture
3.6%
7.2%
75 large
40% of all
companies
development
28000 organized
investments of last
companies
50 years
>5000 years of
construction history
Overview of Indian Construction Industry
Table: India Construction and Infrastructure Industry, 2011 - 2020
2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 2019/20 2020/21
Constuction Industry
Value, INRbn 6,682 7,713 8,830 10,002 11,272 12,639 14,111 15,763 17,572 19,493
Construction Industry % of
GDP 7.9 7.9 8.0 8.0 8.0 8.0 8.0 7.9 7.9 7.8
Total Capital Investment, 26,784 30,864 35,986 41,376 47,355 53,949 60,951 68,607 77,080 86,194
INRbn
Total Workforce, ‘000 803,769 818,273 832,851 847,141 860,948 873,803 886,229 898,389 910,552 922,846
Infrastructure Industry
Value As % of Total 47.4 48.1 49 49.3 49.8 50.2 50.5 50.8 51.1 51.3
Construction
Residential and Non
Residential Building
52.6 51.9 51 50.7 50.2 49.8 49.5 49.2 48.9 48.7
Industry Value As % of
Total Construction
Larsen&Toubro
ENR – 47, 28
STRENGTH WEAKNESS
OPPORTUNITIES THREATS
• Formation of Contract:
– Object
– Proposal / Offer
– Acceptance
– Consideration
– Reciprocal promise
Typical Parties for Works Contract
• Owners
– Public Owner (Government bodies)
– Private Owner (also include quasi-public bodies)
• Architect/Engineers (A/E)
• Prime/General Contractor
• Project Management Consultants / Construction Managers
• Sub-contractors
• Suppliers
• Banks & Financial Institutions
• Specialized Service Agencies
• Labor
• Regulatory agencies
• General Public
Rules for the Participants
• Contracts
• Tort Law
• Specifications
• Drawings
Execution
Monitoring Levels
Weekly Reports
& Activity Targets
Productivity Trends
9 9
0 0 3 6 Finish
Start E 3 9 0 9
0 0 0 4 1 7
6 8
0 4
C 2
F 4
7 1 9
3 3 7
LSM Schedule
• Location
• House• 4Excavation
• Foundation•
• House 3 Framing
•• House 2
House 1
• Day
• Day
• Day
• Day
• Day
• Time
• 2• 4• 6• 8• 10
Resource Planning
• To allocate resources and schedule activities
such that the daily resource requirement on
any particular day does not exceed the
maximum number of resources available on
that particular day
• Resource Leveling – Shift non‐critical activities
within their available floats to obtain the
levelled resource histogram
Resource Leveling
Act R Time
1 2 3 4 5 6 7 8 9 10
A 2
D 6
F 2
B 2
C 4
E 1
Total 4 4 2 2 10 10 6 6 3 2
Average = 4.9. Max Resource = 6. Target = 6
Strategy – Day 5 Res. Req > 6. Shift (C, 1R)
Act R Time
1 2 3 4 5 6 7 8 9 10
A 2
D 6
F 2
B 2
C 4
E 1
Total 4 4 2 2 6 10 10 6 3 2
Strategy – Day 5 Res. Req is ok.
Day 6 Res Req>6. Shift (C, 1R)
Act R Time
1 2 3 4 5 6 7 8 9 10
A 2
D 6
F 2
B 2
C 4
E 1
Total 4 4 2 2 6 6 10 10 3 2
Strategy – Day 6 Res. Req is ok.
Day 7 Res Req>6. Shift (C, 1R)
Act R Time
1 2 3 4 5 6 7 8 9 10
A 2
D 6
F 2
B 2
C 4
E 1
Total 4 4 2 2 6 6 6 10 7 2
Strategy – Day 7 Res. Req is ok.
Day 8 Res Req>6. Shift (C, 1R)
Act R Time
1 2 3 4 5 6 7 8 9 10
A 2
D 6
F 2
B 2
C 4
E 1
Total 4 4 2 2 6 6 6 6 7 6
Strategy – Day 8 Res. Req is ok.
Day 9 Res Req>6. Shift (E, 1R)
Act R Time
1 2 3 4 5 6 7 8 9 10
A 2
D 6
F 2
B 2
C 4
E 1
Total 4 4 2 2 6 6 6 6 6 7
Strategy – Day 9 Res. Req is ok.
Day 10 Res Req>6. Cannot do anything
On Site Layout
Site office location/Size
Stores/ Material yards
Labour camps
Location of equipments/ construction machinery
Water supply/ Temporary storage
Electric supply/ Generator set
Site laboratory
Access roads
Site security
Sanitary facilities
Signs & baricades
Utilities
Temporary Power
Temporary Water
Temporary Sewage Disposal
Job Site Security
Fencing
Lighting / Bright Yard Lights
Local Police
Watch Man
Access Roads
Entry Register System
Sign & Barricades
Site Layout Planning
Material handling
Labour productivity
Equipment constraints
Site constraints
Job site security
Site Layout Planning
G A M M O N - A R C H IR O D O N JV.
Estimation & Costing
• Quantity Survey
– Approximate methods based on preliminary design
– Detailed estimate based on detailed design
• Cost Estimation
– Quotations from Vendors & Subcontractors
– Labor rates, material rates, equipment hire charges
– Productivity, mix design
– Rate Analysis
• Markup
– Overheads, Taxes, Contingencies, Profits
Budget & Cash Flow
• Projected rate at which project’s cash resources will be
spent
• Developed from the cost estimate and the project
schedule
• Working capital management to maximize return on
investment / minimize interest payment
• Projected monthly expenditures, represented by series of
vertical bars, with tops joined, result in typical bell curve
• S Curve – Cumulative monthly project expenditure /
income
Cashflow analysis
• Done by both owner and contractor separately.
• Owner- regular progress payments to the contractor
– Timing of those payments is a matter of contractual agreement
and cannot be delayed
– Payment lag can be used as a negotiation parameter
• Contractor
– Working capital during the construction
– Key management tool – Scorecard against which profitability is
measured
• Cashflow analysis made before the work starts, the amount
of working capital needed each month is determined
Example
Materials Labor
Information Equipment
Operating Safety
Environment Requirements
EQUIPMENT
Design
Skilled labor MANAGEMENT
Sophistication
Corporate Level
Regional Level
Project Level
Work-Package Level
Operation Level
LABOUR & TOTAL FACTOR PRODUCTIVITY
CONSTRUCTABILITY
QA/ QC
MANPOWER PROCUREMENT
PROCEDURES
UTILIZATION PROCEDURES
EQUIPMENT
UTILIZATION TOTAL
………….. LABOUR
& FACTOR
MECHANIZATION
PRODUCTIVITY
PRODUCTIVITY
OPERATING
CONSTRUCTION EFFECTIVENESS
MATERIAL
METHODS SMALL TOOLS
UTILIZATION
UTILISATION
Productivity- Definition
?
Sources of Lost Time
Slow
Rework
Work
Excessiv Lost
e Travel Time
Idle
Time
Idle Time
– Late Starts & Early Quits
– Accidents
– Paperwork
– Layout
Slow Work
– Fatigue
– Adverse weather
Rework
–Engineering Errors
–Inaccurate drawings
Transport
Waiting
Overproduction
Defects
Inventory
Motion
Excess processing
DO WE MEASURE FACTORS FOR ALL ACTIVITIES ?
MPSA Principle
Measured Productivity For Significant Activities
CONCRETE OPERATION
Steel Reinf
Concrete
Placement
Support
Activities
Curing Finishing
Repair
Indirect
BASED ON MPSA PRINCIPLE MEASURE ONLY IMPORTANT ACTIVITIES
Formwork
Steel Reinf
Concrete
Placement
Support
Activities
Curing Finfshing
Repair
Indirects
PRODUCTIVITY ANALYSIS
Selected Activity in Progress
Quantities
Work Hours
Productivity Calculations
• Level of Effort
• Incremental Milestone
Units Complete
• Activities with well defined scope
• Output determined quickly by counting
• Relatively few Sub-Tasks
• Short duration for completing each unit of
output
• Single Craft or trade
– Piling
Percentage Complete
• Performance Factors
• Forecasting
PERFORMANCE FACTOR =
PF COMPARISONS CAN BE :
* NUMERICAL
* GRAPHICAL
EXAMPLE PERFORMANCE EVALUATION REPORT
1.0
Start-
Up
25 50 75 100
% COMPLETE
Productivity Reporting
• DAILY
• WEEKLY – PERIODICAL
• CUMULATIVE
FORECASTING
= WORKHOURS TO DATE
% COMPLETE
UNITS OF WORK QUAN- ESTIMATED TOTAL
ACTIVITY MEASURE HOURS TITY QUANTITY FORECAST
TO DATE TO DATE WORK HOURS
LIN FT
1066
LIN FT 1824 917 2,121
PIPING
PIECE
PIPING 2350 9790
1958 86 11,750
STRUCT- LIN FT
20
STEEL 782 638
517 965
CABLE 81
1060 14327 6819
21 5048
Productivity Evaluation - Tools
• Productivity Measurement Systems
– Daily Progress Report
• Work-Sampling
– Observation based measurement of activity level to
ascertain where time is lost
• Foreman-Delay Survey
– Measures where time is lost based on foreman’s opinion
Direct work
Travel Empty
Handed
30% Transport
Tools/Material
55% Idle
2% Unexplained
3%
10% Waiting Work
Related
Implementation of FDS
The FDS is accomplished through five–step process.
Foreman Orientation
1 2 3 4
20
mins 15
10
1 2 3 4
Line Balance : Simple Example
Promotes one- Avoids Minimises the 7 Reduces
piece FLOW overburden wastes Variation
1 2 3 4
20
15
10
5
Project Communication & Documentation
• Objectives
• Record Types and Content
• Cost Documentation
• Correspondence
• Contractual Requirement Documentation
• Meeting Minutes
Documentation – Objectives
• Accurate documentation – Essential function of project
administration
• Contractor operates within tight cost and time
constraints, a number of activities beyond the control
of the contractor Contractor’s performance
• Activity deviation – may not appear to impact contract
at the time it happens, however it may be felt at a later
date
• Disputes resolutions clear documentation – quick
and equitable solutions
Keys to effective jobsite documentation &
communication
• Objectivity and truthfulness
• Timeliness
• Retrievability
• Appropriate distribution
• Standard, uniform information
• Completeness and comprehensiveness
Different areas to be documented
• Project Start-up:
– Construction Schedule
– Schedule of Values
– List of Subcontractors
– Product submittal, shop drawings and samples
• Construction Progress:
– Progress payment requests
– Construction Schedule Updates
– Certified Payrolls
– Contract Change orders: Proposals, Directives, Change-orders
Contractual Requirement Documentation
(cont.)
• Project Closeout:
– Certificate of Substantial Completion
– Lien Releases
– Consent of Surety
– Warranties
– Operation and Maintenance Manuals
– Spare Parts
– Punch Lists
Project Manager – Responsibilities &
Functions
• Responsible to upper • Select, build and retain
management for team. Lead team to achieve
profitability goal
• Achieve project • Planning, Monitoring, and
parameters (time, cost, Control
quality, safety, • Decision-making (Technical,
sustainability) Financial & Administrative)
• Delivery of contractual • Co-ordination and liaison
liabilities with agencies
• Compliance of statutory • Mobilization, Allocation and
and tort liabilities Management of Resources