Programme Evaluation Review Technique (Pert)
Programme Evaluation Review Technique (Pert)
Technique (PERT)
and
Critical Path Method (CPM)
Network Analysis
What is Management ?
Art of getting things done, through and with people in
formally organized groups.
- Harold Koontz
To forecast ,to plan, to organise, to command, to
coordinate and control activities of others.
- George R Terry
Health System Management
Traditional Modern
●
Gantt chart and work scheduling
Activity analysis ●
Queuing theory
Mathematical ●
Network analysis -PERT ,CPM
●
Linear programming
techniques
●
Cost benefit analysis
Financial techniques ●
Cost accounting
Funding mechanism
Population need
Planning
Scheduling
Controlling
Project management team
List activities.
Determine activity durations
Assign activity relationships
Technique whereby
objectives are identified,
activities and tasks identified and
interrelationships graphically presented as
network and used as basis for determining
sequence of activities and allocation of resources.
Guidelines for network construction
Activities-represented by arrows .
Tail (Start) event and head (end) event for every activity.
Network have unique starting and completion node.
E
Tail event 4 6 H
G
Predecessor activity
Activity that must occur before another activity.
Successor activity :
Activity that must occur after another activity
Activity-on-node (AON)
Nodes represent activities, and arrows show relationships
Activity-on-arrow (AOA)
Arrows represent activities and nodes denote events
Network analysis for measles vaccination programme
Monitoring, evaluation
Establishment of
,feedback system
surveillance
Simple to understand
Inexpensive
NETWORK ANALYSIS
2
D(2) 5
A(6)
I(5)
START B(3) 6
1 3 FINISH
E(3) 8
H (5)
C (4)
F(5)
4 7 J(3)
G(3)
2) MEAN DURATION AND VARIANCE
Variance
2 2
σ = [(Tp –To ) ÷ 6 ]
DURATION (IN WEEKS)
Mean
ACTIVITY PREDECESSOR OPTIMISTIC MOST PESSSIMISTIC duration variance
(To) LIKELY (Tp) (Te)
(Tm )
A - 5 6 7 6 0.11
B - 1 3 5 3 0.44
C - 1 4 7 4 1.00
D A 1 2 3 2 0.11
E B 1 2 9 3 1.78
F C 1 5 9 5 1.78
G C 2 2 8 3 1.00
H E,F 4 4 10 5 1.00
I D 2 5 8 5 1.00
J H,G 2 2 8 3 1.00
3) Critical Path and Project Completion Time
ES y= Max ( ES x + Dxy )
ES x = LF x
ES y = LF y
ES y - ES x = LF y –LF x = D xy
Expected Project completion time = C-F-H-G
(1-4-6-7 )
= 4+5+5+3 = 17 weeks
4) Probability of completing the project on or
before 22 weeks?
Critical activities
List activities
Identify constraints
Deliverable 1 Deliverable 2
SLACK OR FLOAT
4 I (2)
7
10/10 16/12
Floats calculation-Total float
y = next activity