Quality Training Part 1 (Telecom Sites)
Quality Training Part 1 (Telecom Sites)
NOT OK
4. Site Acquisition 4a. Resurvey
1. Marketing Input OK
HUTCH 5a. GBT Soil Test Report
Responsibility 5b. Structural Site Dwgs & Layout
Nokia to follow-up
Engineer visit
Critical
6. Site H/o by Acqn with NOC
PERMITS FLOW During
Marking
A) SACFA Application
7. Marking & Excavation
B) NOC Application
(Municipal ETC.) RND TND
Data
C) EB Connection 8. PCC
Application
Engineer visit
Critical. (Fill
MATERIALS 9. Steel Cutting/Binding & Shuttering sec-3.2 of site
folder)
FLOW
Infra (i) Bolts & Templates 10. RCC with Cube Collection
Implementation:
(40 to 42 Days) RND TND 18. Other Elec. Works
PERMISSION
Engineer visit
17. Earthing 20. Site RFI Critical. (Fill sec-
5 of site folder)
(iv) Telecom Equipments
21. TI
Telecom
Engineer visit
Implementation: (3 to Critical. (Fill sec- 22. Site ON AIR 22. Site ACCEPTANCE
5 Days) 6,7,8 of site
folder)
23. Site Optimization
Site Built out Process – GBT
Model ACTIVITY PHOTOGRAPHS
1. EXCAVATION
JPEG Image
2. STEEL BINDING
JPEG Image
4. RCC
5. CURING
NOT OK
4. Site Acquisition 4a. Resurvey
1. Marketing Input
OK
HUTCH 5. Structure Stability of building NOT OK
Responsibility (Nokia to follow-up)
OK Engineer visit
Critical
6. Site H/o by Acqn with NOC
PERMITS FLOW During
Chipping
A) SACFA Application
7. Chipping & Layout
B) NOC Application
RND TND
(Municipal ETC.)
Data
C) EB Connection
Application
8. Steel Cutting/Binding & Shuttering Engineer visit
Critical. (Fill
MATERIALS sec-3.2 of site
folder)
FLOW
Infra (i) Bolts & Templates 9. Template Setting
Implementation:
RND TND 16. Other Elec. Works
(18 Days) CUBE TEST BY HUTCH
PERMISSION
Engineer visit
15. Earthing 18. Site RFI Critical. (Fill sec-
5 of site folder)
(iv) Telecom Equipments
19. TI
Telecom
Engineer visit
Implementation: (3 Critical. (Fill sec- 20. Site ON AIR 21. Site ACCEPTANCE
Days) 6,7,8 of site
folder)
22. Site Optimization
Site Built out Process – ACTIVITY PROCESS FLOW
POLE
Nokia Responsibility 2. Nominal Planning 3. SARF
NOT OK
4. Site Acquisition 4a. Resurvey
1. Marketing Input OK
HUTCH 5. Structure Stability of building NOT OK
Responsibility (Nokia to followup)
OK
6. Site H/o by Acqn with NOC
PERMITS FLOW
A) SACFA Application
B) NOC Application
RND TND
7.
(Municipal ETC.)
Layout
Data
C) EB Connection
Application
Engineer visit
Critical.
MATERIALS
FLOW
Infra
13. Other Elec. Works
Implementation: (9
Days)
PERMISSION
(ii) Shelter / DG 10. DG/Shelter Foundation 11. DG/Shelter I & C 14. PIU Integration
Engineer visit
12. Earthing 15. Site RFI Critical. (Fill sec-
5 of site folder)
(iii) Telecom Equipments
16. TI
NOT OK
4. Site Acquisition 4a. Resurvey
1. Marketing Input
OK
HUTCH 5. Structure Stability of building NOT OK
Responsibility (Nokia to follow-up)
OK
7.
(Municipal ETC.)
Layout
Data
C) EB Connection
Application
Engineer visit
Critical.
MATERIALS
FLOW
Infra
Implementation:
PERMISSION
Engineer visit
11. Site RFI Critical. (Fill sec-
5 of site folder)
(ii) Telecom Equipments
12. TI
Engineer visit
Critical. (Fill sec-
Telecom 6,7,8 of site 13. Site ON AIR 14. Site ACCEPTANCE
Implementation: folder)
( 5 Days)
15. Site Optimization
Handover Documents for site Development
• NOC from landlord
Microsoft Word
Document Microsoft Excel Microsoft Excel
Worksheet Worksheet
MSC
BSC BSC
Shelter
(Equipment Room)
SITE SURVEY
SURVEUOR TOOLS (RTT/GBT)
White Paper, Scale (30cm), Pencil, etc,. to draw the rough layout
Compass
Commercial Building
details. 12m 2.9 12m
5. Mark the existing beam lines. Tower
0.3x0.3
Green Field
G+3
6. Mark the position of stair case, stair case head C3
15m
room, water tank, lift room, etc., C1
C2
C2
2.0
Proposed
7. Mark the adjacent roads, surrounding
2.9 Shelter
structures and its distances. 0.3x0.3
C3
8. Mark the height of the building, no. of floors
C1 C2
and levels. C2
Proposed
9. Mark the proposed area of tower, DG & 3m 3.3
Shelter 3m
DG
C2 C3 C2
10. Mark the proposed Earth Pits
Electric Pole
11. Mark the nearest Elec. Pole / Transformer to 9m 3.0
the site
12. Write your name, Employee ID No., Ph. Mumbai
Pune
No., Date & Sign
h P
13. Take the Owner sign and C1 - 0.3 dia – 6 nos 12 dia Rajes
C2 - 0.3x0.45 – 6 nos 16 dia & 2 nos 20dia P Rajesh
customer site engineer sign
C3 - 0.4x0.45 – 8 nos 16 dia 401501
14. This Rough layout should be sent to 03.03.06
Design department to prepare CAD 09347029652
MG Road – 24m, F. No.112, MG Road Pune
Placing the Tower, Shelter
and DG on the roof top Street road
12m
1.2 3.3 3.5 4.0
C3
C1UP DOWN C2 C2
1.5m dia
2.9
WT
C3
C1
C2 C2
Commercial Building
12m 2.9 12m Tower
Green Field
G+3
C3
C1 C2
15m
C2
2.9
Shelter
C3
C1 C2
C2
3m 3.3 DG
3m C2 C3 C2
9m 3.0
Mumbai
Pune
Column – Size - Steel
C3
C2
Tower
C3
C2
Shelter
C3
C2
DG
C3 C2
Placing the Tower, Shelter
and DG on the roof top
4.0 m
2.9 m
4 legged tower
2.9 m
3.3 m
Placing the Tower, Shelter
and DG on the roof top
4.0 m
2.9 m
4 legged tower
2.9 m
3.3 m
Placing the Tower, Shelter
and DG on the roof top
4.0 m
2.9 m
4 legged tower
2.9 m
3 legged tower
3.3 m
Placing the Tower, Shelter
and DG on the roof top
4.0 m
2.9 m
4 legged tower
2.9 m
3 legged tower
3.3 m
Placing the Tower, Shelter
and DG on the roof top
4.0 m
4 legged tower
2.9 m
2.9 m
3 legged tower
3.3 m
Placing the Tower, Shelter
and DG on the roof top
2.9 m
2.9 m
2.9 m
SECTION X-X
2.9 m
Concrete
AC
X ISMC Pedestal
ISMB
3.3 m
1.8
AC
3.2 x 2.5
2.8
X
Placing the Tower, Shelter
and DG on the roof top
4.0 m
2.9 m
2.9 m
AC
3.3 m
Placing the Tower, Shelter
and DG on the roof top
Approx. DG wt. is 2.5 MT 4.0 m
DG bed size will depends on the
DG base size
0.
3
0.3 2.9 m
1.
1.
0
6
1.5
2.9 m
2.1
AC
DG
DG Bed
3.3 m
0.3 0.3
Street road
C1 12m C3
3. 3. 4. C2
1.2 3
UP DOWN C2 5 0
CAD layout will be made with the help 2.9 1.5m
dia
of rough layout prepared at site C3 WT
0.3x0.3
C1 Earth Pits
C2 C2 1.0
Commercial Building
12 2.9 12m Tower 0.3x0.3
Green Field
G+3
C3
C1 15m
C2 C2
1.0
2.9 Shelter
With this CAD layout, foundation 1.8m
C3
2.8m
0.3x0.3
9m 3m
Mumbai Pune
PLAN
Foundation Detailed Drawing
PLAN
• Construction Procedure OF RTT Site
CONSTRUCTION PROCEDURE – RTT SITE
Marking Procedure
foundation drawing
2. Mark the tower columns position 2.8
Mumbai
Pune
Chipping At site
Purpose Street road
Mumbai
Pune
Chipping PLAIN TEERACE
Purpose
1. To connect the foundation column
reinforcement to existing column
reinforcement
2. To develop the bond between old
concrete with new concrete
Column
Column
SECTION
Chipping PLAN
Purpose
1. To connect the foundation column
reinforcement to existing column
reinforcement
2. To develop the bond between old
concrete with new concrete
Column
Column
SECTION
Chipping PLAN
Purpose
1. To connect the foundation column
reinforcement to existing column
reinforcement
2. To develop the bond between old
concrete with new concrete
Column
Column
SECTION
Chipping PLAN
Purpose
1. To connect the foundation column
reinforcement to existing column
reinforcement
2. To develop the bond between old
concrete with new concrete
Column
Column
SECTION
Chipping PLAN
Purpose
1. To connect the foundation column
reinforcement to existing column
reinforcement
2. To develop the bond between old
concrete with new concrete
Column
Column
SECTION
Chipping PLAN
Purpose
1. To connect the foundation column
reinforcement to existing column
reinforcement
2. To develop the bond between old
concrete with new concrete
Column
Column
3. Procedure for terrace with dummy concrete
column
SECTION
Connecting the reinforcement PLAN
Procedure
2 types
< 50d
Slab
Column
Column
SECTION
Connecting the reinforcement PLAN
Procedure
2 types
< 10d
Slab
Column
Column
SECTION
Connecting the reinforcement PLAN
Procedure
2 types
Critical Condition
Reinforcement can’t be exposed
How to connect if reinforcement can’t
be exposed ??
Slab
Column
Column
SECTION
Connecting the reinforcement PLAN
Procedure
2 types
Critical Condition
Column
Column
SECTION
Bond between old & new concrete
Slab
Grouting
Chemical
Column
Column
SECTION
If foundation reinforcement is not connected properly with existing reinforcement OR old
concrete (chipped portion) and new concrete is not connected with grouting material…..
It results
Bar-bending The reinforcement steel shall be HYSD
bars conforming to IS-1786
Column Rods The reinforcement used in the
Column Stirrups
concrete should be branded one
It should be free from corrosion / oil /
paint
Beam Stirrup
Bottom support
Shuttering
Beam reinforcement Column shuttering
Bottom shuttering
Material to be used
Plywood
Steel Plates
Place the reinforcement on the
bottom shuttering with required
as mentioned in the drawing
Bottom support
Cover Blocks