Preliminary Estimate
Preliminary Estimate
DEFINATION AND
IMPORTANCE OF
PRELIMINARY ESTIMATES
DEFINATION
Defined as an activity in particular work to make
possible offer to execute task base on a stipulated sum
CUBIC
FLOOR
AREA
UNIT OF
METHOD WHEN IT IS USED NOTE MESUREMENT
a) Pitch roof
b) Flat roof
20.00
10.00
1.50
3.50
3.50
1.00
a) Pitch
roofvolume
Building = 20.00 x 10.00 x [1.00 +2(3.50) + ½
(1.50)]
=20.00 x 10.00 x 8.75
=1750m3
25.00
5.00
8.00
10.00 15.00
7.00
5.00