Cost Optimization
Cost Optimization
MANAGEMENT
MODULE 2
2
SYLLABUS
Crashing and time – cost trade off, Resource smoothing and resource
levelling – Construction, equipment, material and labour schedules.
Preparation of job layout.
Indirect cost rises with increased duration. For any project, the relationship
between indirect cost and project duration is shown in figure (a) considering
only overhead and supervision.
It would be represented by a straight line, with a slope equal to daily
8
overhead.
But when there is a loss in profits, due to inability to meet demand or due to
9 some penalty due to delay, a corresponding cost increase must be added to the
cost of overheads, producing the curve as shown in fig(b). Such a loss is called
the outage loss.
To get the same work done in less time, we have to increase amount of
labour or equipment or time saving materials that too at extra charges which
simply means increase in direct cost.
The figure shows a generalised curve between direct cost and project
duration.
The project has the highest cost corresponding to the crash duration and
normal cost corresponding to the normal duration.
11
Normal cost () : This is the direct cost required to complete the activity in
normal time duration.
The straight line or segmented approximation of the direct cost curve is helpful
in carrying out the project cost analysis. In such analysis, the cost slope is used.
Cost Slope
The cost slope is the slope of the direct cost curve, approximated as straight line.
It is defined as follows:
Cost slope =
or CS = = ; where CS = cost slope
15 Δ C = increase in cost
Δ t = decrease in time
If the cost curve is approximated to a single line, it will have one cost slope.
If, however, the cost curve has segmented approximation, it will have more than
one cost slope.
The single or multiple cost slopes will depend upon the non-linearity of the
direct cost curve.
The segmented approximation of cost curve, having multiple cost slopes, is
more accurate but calculations are more involved. Generally single cost slope is
assumed.
CRASHING THE NETWORK FOR COST OPTIMISATION
(Refer the PDF 1)
16
Steps in Crashing
c) The critical activity having minimum cost slope is crashed in first stage. The next stage crashing will
involve activity having second lower cost slope in critical path.
e) Steps (c) & (d) are repeated till all activities of project are crashed along the critical paths &
corresponding time is crash time of project.
f) It is to be noted that only critical activities should be crashed. (As non- critical activities do not
control the project duration & completing them earlier has no benefit rather it increases project cost.)
(For problems : refer the PDF 1)
TIME - COST TRADE OFF
17
The Time & Cost are the two most important resources that a project
manager deals with.
Both these resources have constraints & the job of a project manager is to
have a judicious balance between the two.
The judicious balance between time & cost is called Time – cost Trade off
and it can be achieved by studying the availability of these two resources and
the demand for these two resources for the given project.
Every project is unique & the same time – cost trade off rule will not be
applicable to all projects uniformly.
For eg:
18
The duration for a project as obtained from network calculations might be
longer than the desired duration. Social, environmental or political
constraints may necessitate early completion of the project even at a
higher cost.
When cost is the only constraint & there is no necessity that the project
should be hurried through, the project time can be extended till the total
cost becomes the minimum.