Estimating and Rate Analysis
Estimating and Rate Analysis
Challenges in Estimating
The job of an estimator is not only to calculate the quantity and cost of the material, but to co-ordinate different parties
involved in the project or construction in particular. An estimator of the construction company has to get involved with
the site engineer, material supplier, instrument (plant) manager and senior management staff to obtain the various
details of the cost and explaining the calculation to higher management. An estimator has to understand the project
details, study drawing and specification, obtain working conditions, labour and equipment productivity and collecting
other data from the site. An estimate also assesses the temporary work at the site such as formwork for concreting,
temporary plant for the storage of materials. Virtually, an estimator has to build the project on paper to obtain the right
guess.
• In the organization, background work for estimation is carried out by higher
management and organizations keeps the details regarding unit cost of the items
called schedule of rate, productivity, and guideline for basic calculation. The basic
calculation is carried out by junior level engineers or assistants.
• In preparing detailed estimate, we need to know the following two things
• Quantities of the items involved.
• Obtaining cost of the items involved.
• Methods of obtaining quantities of the items involved is called quantity estimate
and method obtaining unit cost of the items involved is called rate analysis.
• Types of Estimate:
• Based on the rigor with which an estimate is prepared, the estimate can be
classified as
• Preliminary estimate.
• Detailed estimate.
• Requirements of preliminary and detailed estimate:
• To prepare a preliminary estimate, quantity of work to be planned is measured in terms of unit of
person, built up area, extent of work in kilometer such as a preliminary estimate of housing can be
calculated based on type of house and number of house to be built. Similar preliminary estimate of
highway can be calculated by knowing the type of road in terms of lane or pavement and length of
the load.
• Preliminary Estimate
• Different methods of preliminary estimate can be grouped into the following categories –
• Time referenced cost estimate
•
Cost capacity factor
•
Component ration/installation cost ratio
•
Parameter cost
• The preliminary estimate is obtained during early phases of project. As the project progresses, an
estimate keeps on getting refined and lastly we get definitive estimate.
• Time referenced cost estimate – If the cost of construction of facilities is known at a certain time,
the present cost can be estimated by multiplying it with the cost index, with reference to that
time. Generally government finance department publishes cost index based on depreciation, etc.
But this cost index is very crude. Construction department keeps the cost index based on the
items and method of construction used. There are some limitations of such method. During the
time, technology changes; productivity of various equipment may change; degree of competition
may be different. One should be aware of all these factors while using the cost index to estimate
the constructed facilities.
•
Cost capacity factor – This factor refers to the change in cost of built-up facilities with the change
in size of the project of similar type. If C1 and C2 be the cost of facilities to be built and old
facilities. Let their size be Q1 and Q2 . We can calculate the cost of the new facility as
• C1=C2*( Q1/Q2)^X
Where x is called the capacity factor. Many organizations publish the value of capacity factor. It is
reasonable to consider cost capacity factor between 0.6 to 0.8.
The capacity factor method and time reference method can be combined.
• Installation cost ratio – In the industrial project, the equipment to be installed is known quite
earlier to the details for their installation. In such situations, an estimate is prepared based on
the ratio or percentage of the cost incurred as the installation cost. The organization generally
maintains this type of data. Example- The cost of an equipment is Rs10,00,000, and its
installation cost , including accessories is 50%. Thus the estimated cost is
• 10,00,000 + ( 0.5 x 10,00,000) = 15,00,000
We can consider the equipment in component wise and calculate the installation cost
individually. This approach will require detailed information, but will be more accurate.
• Unit Parameter cost – In many of the projects, it is possible to obtain the cost of unit parameter
of construction. These parameters may be unit area, unit volume, etc. This type or procedures
are used in building construction. Residential apartment in our country are generally estimated
using this method. There are different variations of the method. Some of them widely used are
as follows - Residential buildings are generally estimated using this method.
• Requirement for detailed estimate:
• To calculate the detailed estimate, complete structural drawing of the facilities to be built up
and specification of the items are necessary. We also need to know the rate of each of the
items, which includes profit of the contractor.
• Revised Estimate:
• Due to change in the rate of material or change in specification of materials, an estimate is often
required to be modified. Thus, we prepare revised estimate against the original estimate. In the
preparation of revised estimate, original estimate is also provided such that comparison can be
made. There is no change in structural drawing and additional items are not added in the revised
estimate.
• Revised estimate is a detailed estimate. It is also accompanied by the original estimate for
comparative purpose. While submitting the revised estimate, the reason for revision should also be
stated.
• Supplementary estimate:
• During the execution of project, structural modification are required or addition work is added for
construction. The estimate for additional work is called supplementary estimate. Supplementary
estimate is also required to be prepared when some of the items are overlooked. In preparing the
supplementary estimate reason for preparing the estimate would be clearly stated.
Example: Additional partition can be planned in the building. The estimate is prepared for
partitioning as supplementary estimate. Structural / architectural changes are prerequisite for
supplementary estimate.
• Measurement In Civil Engineering
• Measurement of civil Engineering work executed in the field is carried out based on thumb rule. Indian
standards provide the approximate rules to measure the quality in the field. They are comprehensive and
follows almost all areas. Following are the list of Indian Standards -
• Indian standards
• Standard Description
• IS 1200 : Part 1 : 1992 Methods of measurement of building and civil engineering works: Part 1 Earthwork
• IS 1200 : Part 2 : 1974 Method of measurement of building and engineering works: Part 2 concrete works
• IS 1200 : Part III : 1976 Method of Measurement of Building and Civil Engineering Works - Part III : Brickwork
• IS 1200 : Part 4 : 1976 Method of measurement of building and civil engineering works: Part 4 stone masonry
• IS 1200 : Part 5 : 1982 Method of measurement of building and civil engineering works: part 5 form work
• IS 1200 : Part 6 : 1974 Method of measurement of building and civil engineering works: Part 6 refractory work
• IS 1200 : Part 7 : 1972 Method of measurement of building and civil engineering works: Part 7 hardware
• IS 1200 : Part 8 : 1993 Method of measurement of building and civil engineering work: Part 8 steel work and
iron
work
• IS 1200 : Part 9 : 1973 Method of measurement of building and civil engineering work: Part 9 roof covering
(including cladding)
• IS 1200 : Part 10 : 1973 Method of measurement of building and civil engineering works: part 10 ceiling and linings
• IS 1200 : Part 11 : 1977 Method of measurement of building and civil engineering work: Part11 paving, floor finishes
dado and skirting
• IS 1200 : Part XII : 1976 Method of Measurement of Building and Civil Engineering Works - Part XII : Plastering and
Pointing
• IS 1200 : Part 13 : 1994 Method of measurement of building and civil engineering works: Part 13 Whitewashing,
colour washing, distampering and painting of building surfaces
• IS 1200 : Part 14 : 1984 Method of measurement of building and civil engineering works: Part 14 glazing
• IS 1200 : Part 15 : 1987 Method of measurement of building and civil engineering works: Part 15 painting, polishing,
varnishing etc
• IS 1200 : Part 16 : 1979 Method of measurement of building and civil engineering works: Part 16 laying of water and
sewer lines including appurtenant items
• IS 1200 : Part 17 : 1985 Method of measurement of building and civil engineering works: Part 17 road work including
air field pavements
• IS 1200 : Part 18 : 1974 Method of measurement of building and civil engineering works: Part 18 demolition and
dismantling
• IS 1200 : Part XIX : 1981 Method of Measurement of Building and Civil Engineering Works - Part XIX : Water Supply,
Plumbing and Drains
• IS 1200 : Part 20 : 1981 Method of measurement of building and civil engineering works: Part 20 laying of gas and oil
pipelines
• IS 1200 : Part 21 : 1973 Method of measurement of building and civil engineering works:
Part 21 wood-work and joinery
• IS 1200 : Part 22 : 1982 Method of measurement of building and civil engineering works:
Part 22 materials
• IS 1200 : Part 23 : 1988 Method of measurement of building and civil engineering works:
Part 23 piling
• IS 1200 : Part 24 : 1983 Method of measurement of building and civil engineering works:
Part 24 well foundations
• IS 1200 : Part 25 : 1971 Method of measurement of building and civil engineering works:
Part 25 tunneling
• IS 1200 : Part 26 : 1987 Method of measurement of building and civil engineering works:
Part 26 Acid resistant lining
• IS 1200 : Part 27 : 1992 Method of measurement of building and civil engineering works:
Part 27 Earthwork done by mechanical appliances
• IS 1200 : Part 28 : 1992 Methods of measurement of building and civil engineering works:
Part 28 Sound insulation works