Traffic Engineering Project

The document summarizes traffic surveys conducted at various locations in Noida. Volume surveys were conducted to count the number of vehicles at Parichowk, Jagat Farm, Kasna, and between various routes. The surveys found the highest traffic volumes between Parichowk to Noida, with cars making up 63% of vehicles. PCU (Passenger Car Unit) values and vehicle type percentages are provided for each location and route.

Uploaded by

Sonu Choudhary
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
82 views32 pages

Traffic Engineering Project

The document summarizes traffic surveys conducted at various locations in Noida. Volume surveys were conducted to count the number of vehicles at Parichowk, Jagat Farm, Kasna, and between various routes. The surveys found the highest traffic volumes between Parichowk to Noida, with cars making up 63% of vehicles. PCU (Passenger Car Unit) values and vehicle type percentages are provided for each location and route.

Uploaded by

Sonu Choudhary
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 32

SUMMER INTERNSHIP


TRAFFIC SURVEY
AT
PARICHOWK
INTRODUCTION

 Traffic survey : Traffic survey is undertaken to determine the
volume of Traffic in the particular routes …
 Types of traffic survey :
 Volume Surveys (traffic count)
 Speed Surveys
 Classification Counts
 Gap Studies
 Turning Movement
 Multi-lane Classification
 Pedestrian Surveys
 License Plate Surveys
Traffic Survey Done By Us ?

 Volume Survey (Traffic Count) : It’s a survey where
vehicle’s count by automatically and manually
process.
 Pedestrian survey : It’s a survey where pedestrian
counted by manually or automatically..
Traffic Volume Count

 Prepare
 Set location
 Complete study
 Document work
IMAGE OF LOCATION

Data of all roots

 NOIDA TO PARICHOWK
 Total number of vehicle = 3241

Time LCV & 3 Buses & Two Wheelers Cars Total


Wheelers Trucks
09-09:30AM 160 85 270 480 995
09:30-10:00 125 75 255 420 875
10:00-10:30 97 55 245 495 892
10:30-11:00 75 34 105 265 479
Piechart

Sales

14.10 %

Cars 2 wheelers
7.68%

truck & busses lcv &3 wheeler


51.21%

26.99%
Percentage & PCU

 PCU/Lane/Hour for LCV and 3  Percentage Of Vehicles
Wheelers
 PCU = (457×2÷3)×(60÷120) =  LCV & 3 Wheelers =
152.33 457÷3241×100 =14.10%
 PCU for Trucks and Buses
 Trucks and Buses =
 PCU = (249×3.7÷3)×(60÷120) =
153.55 249÷3241×100 =7.68%
 PCU for 2 Wheelers  2 Wheelers =
 PCU = (875×0.75÷3)×(60÷120) =
875÷3241×100 =26.99%
109.37
 PCU for Cars  Cars = 1660÷3241 ×100
 PCU = (1660×1÷3)×(60÷120) = = 51.21%
276.6
Parichowk to Jagat farm
Time

LCV & 3
Wheelers
Buses &
Trucks
Two
Wheelers
Cars Total
Sales

30%
09-09:30AM 653 150 536 752 2091
38%

09:30-10:00 727 100 522 808 2157

5%
10:00-10:30 573 98 625 965 2261

27%
10:30-11:00 647 100 647 839 2233 Lcv & 3 wheelers
Truck and busses
2 wheelers
Cars

TotalNo.ofVehicles = 8742
PCU & Percentage

 PCU/Lane/Hour for LCV and 3  Percentage Of Vehicles
Wheelers
 PCU = (2600×2÷3)×(60÷120) =
 LCV & 3 Wheelers =
866.66 2600÷8742×100 = 29.74%
 PCU for Trucks and Buses  Trucks and Buses =
 PCU = (448×3.7÷3)×(60÷120) = 448÷8742×100 = 5.12%
276.26
 PCU for 2 Wheelers  2 Wheelers =
 PCU = (2330×0.75÷3)×(60÷120) = 2330÷8742×100 = 26.65%
291.25  Cars = 3364÷8742×100 =
 PCU for Cars
38.48%
 PCU = (3364×1÷3)×(60÷120) =
560.66
Jagat to Parichowk

Time LCV&3 Buses& TwoWheelers Cars Total
Wheelers Trucks
09-09:30AM 322 95 689 952 2058 28%
33%

09:30-10:00 344 98 487 897 1826


10:00-10:30 244 81 422 822 1569 4%

10:30-11:00 102 63 311 624 1100 Lcv & 3 wheeler


34% truck and busses
2 wheeler
cars
Total No. of Vehicles = 6553
PCU & Percentage


PCU/Lane/Hour for LCV and 3
Wheelers Percentage Of


PCU = (1012×2÷3)×(60÷120) = 337.33
PCU for Trucks and Buses
Vehicles
 PCU = (337×3.7÷3)×(60÷120) = 207.81  LCV & 3 Wheelers =
 PCU for 2 Wheelers (1012÷6553)×100 = 15.44%
 PCU = (1909×0.75÷3)×(60÷120) = 238.62
 PCU for Cars  Trucks and Buses
 PCU = (3322×1÷3)×(60÷120) = 587 =( 337÷6553)×100 = 5.14%
 2 Wheelers =
(1909÷6553)×100 = 29.13%
 Cars = (3522÷6553)×100 =
49.67%
Parichowk to kasna

Sales Time LCV&3 Buses& Two Wheelers Cars Total
16%

Wheelers Trucks
5%
09-09:30AM 265 40 290 317 912
50%
09:30-10:00 175 55 365 314 909
29% 10:00-10:30 418 36 350 330 1134
Lcv & 3 wheeler

truck and busses


10:30-11:00 220 39 310 311 880
2 wheeler

cars Total No. of Vehicles = 3835


PCU & Percentage

 PCU/Lane/Hour for LCV and 3  Percentage Of Vehicles
Wheelers
 PCU = (1078×2÷3)×(60÷120) =
 LCV & 3 Wheelers =
359.33 ( 1078÷3835)×100 =
 PCU for Trucks and Buses 28.10%
 PCU = (170×3.7÷3)×(60÷120) =  Trucks and Buses =
104.83
(170÷3835)×100 = 4.432%
 PCU for 2 Wheelers
 PCU = (1315×0.75÷3)×(60÷120) =
 2 Wheelers =
164.37 (1315÷3835)×100 = 34.28%
 PCU for Cars  Cars = (1272÷3835)×100 =
 PCU = (1272×1÷3)×(60÷120) = 212 33.16%
Kasna to Parichowk

Time LCV&3 Buses& Two Wheelers Cars Total Sales
Wheelers Trucks 23%

09-09:30AM 265 40 290 317 912 45%


4%

09:30-10:00 175 55 365 314 909


10:00-10:30 418 36 350 330 1134 27%

Lcv and 3 wheeler

10:30-11:00 220 39 310 311 880 truck and busses


2 wheelers
cars

Total No. of Vehicles = 3589


PCU & Percentage

 PCU/Lane/Hour for LCV and  Percentage Of Vehicles
3 Wheelers  LCV & 3 Wheelers =
 PCU = (986×2÷3)×(60÷120) = (986÷3589)×100 = 27.47%
328.66  Trucks and Buses =
 PCU for Trucks and Buses (184÷3589)×100 = 5.12%
 PCU = (184×3.7÷3)×(60÷120) =  2 Wheelers = (1151÷3589)×100 =
340.4 32.07%
 PCU for 2 Wheelers  Cars = (1268÷3589)×100 =
 PCU = (1151×0.75÷3)×(60÷120) 35.33%
= 143.87
 PCU for Cars
 PCU = (×1÷3)×(60÷120) = 211.33
Parichowk to Noida

Time LCV & 3 Buses & Two Cars Total
Wheelers Trucks Wheelers
11%

09- 58 70 310 425 863


09:30AM
09:30- 18 65 167 747 1013
10:00
26%
10:00- 28 81 97 620 826
10:30
63%
10:30- 14 73 122 411 620
11:00

Total No. of Vehicles = 3322

Lcv and 3 wheeler


truck and busses
2 wheeler
cars
PCU & Percentage

 PCU/Lane/Hour for LCV  Percentage Of Vehicles
and 3 Wheelers  LCV & 3 Wheelers =
 PCU = (118×2÷3)×(60÷120) (118÷3322)×100 = 3.55%
= 39.33
 Trucks and Buses =
 PCU for Trucks and Buses
(289÷3322)×100 = 8.69 %
 PCU =
 2 Wheelers =
(289×3.7÷3)×(60÷120) =
178.21 (696÷3322)×100 =20.95 %
 PCU for 2 Wheelers  Cars = (2203÷3322)×100 =
 PCU = 66.31 %
(696×0.75÷3)×(60÷120) = 87
Finding

 Capacity
 Pcu
Reason for Choking

 Detailed survey of Pari Chowk carried out. Existing
three lanes provided have adequate capacity even if
traffic flows at 30 Kmph at the circle.
 Blocking of the road by autos.
 Improper halting of busses in the second and at times in
the third lane.
 No bypass for heavy vehicles.
 Restricted area available for busses, autos, personal and
commercial vehicles. Larger area can avoid congestion.
 Pedestrian crossing on the main expressway
solution 1


 Shifting of bus stop at Pari Chowk to Alpha Commercial Metro
Station. Thus providing adequate area for busses, autos, private
car parking and commercial vehicles.
 Separate bus lanes (55 busses can be parked simultaneously).
 Separate auto lanes (More than 100 autos can be parked).
 Adequate car (180) and two wheeler / Cycle (350) parking.
 Multimode transit facility.
 No blocking of road and wrong side driving.
 Pedestrians can use metro bridge to cross roadway.
 NIL cost alternative. Relaying / strengthening of existing roads
may be required.
Existing 4.8 m wide Road to be used for Busses


Existing 9.0 m wide Road to be used for Car
Parking


Bus lane for other side

Solution 2

solution 2

 In case shifting Pari Chowk bus stand to Alpha
Commercial not feasible.
 Shifting of bus stop to under the Pari Chowk metro station.
 An opening from the expressway to the service road to be
provided. Busses to stop under the metro station and join
the expressway at Tugalpur junction.
 Hard standing for auto stand to be made in the empty area
near Pari Chowk.
 Autos to use service road in front of Ansal Plaza to come to
Metro Station.
Parking Area For Autos,Uber,Ola

DRIVE WAY FOR AUTOS,UBER & OLA


BUS LANE

OTHER SIDE BUS STAND



THANK YOU

PRESENTED BY :
SONU CHOUDHARY