Concrete For PE Exam DPWH
Concrete For PE Exam DPWH
Concrete For PE Exam DPWH
REVIEW ON
CONTRACTOR AND
CONSULTANT
MATERIALS ENGINEER
CONCRETE
TECHNOLOGY
Concrete is a stone-like
material obtained by
permitting a carefully
proportioned mixture of
cement, and gravel or other
aggregate, and water to
harden in forms of the shape
and dimensions of the
desired structure.
Nilson and Winter
Composition of Concrete
Major Composition
Paste (cement and water)
Mineral Aggregate (coarse and
fine)
Portland Cement
( GRINDING or PULVERIZING)
Types of Cement
Blended Cement
Portland-Pozzolan Cement
….blended hydraulic cement
consisting of an intimate and
uniform blend of Portland cement
or Portland blast-furnace slag
cement and fine pozzolan blended
within specified limits.
Pozzolan
NATURAL
POZZOLAN
CLINKER
MIXING BY INTER-GRINDING
and / or BLENDING
+ =
PORTLAND
CEMENT PORTLAND- POZZOLAN
PORTLAND CEMENT
BLAST-FURNACE
ARTIFICIAL
SLAG CEMENT POZZOLAN
Types of Cement
White Portland For general construction use when the special properties specified for any
T-I n/a
other type are not required
Cement
BLENDED CEMENT
Three color bands For general concrete construction use, Moderate sulfate resistant and
T – IP BRIGHT YELLOW moderate heat of hydration cement
Two color bands For general concrete construction use when special characteristics attributed
Portland - to the larger quantities of pozzolan in the portland-pozzolan cement are not
T – I(PM) BRIGHT YELLOW
Pozzolan required.
One color band For general concrete construction use not requiring high early strength, sulfate
T-P BRIGHT YELLOW resistant, Low Heat of hydration cement
Portland Blast- Two color bands For general concrete construction, Moderate sulfate resistant and moderate
T - IS heat of hydration cement
furnace Slag BLUE COLOR
One color band For general concrete construction not requiring high early strength, sulfate
SLAG CEMENT T–S BLUE COLOR resistant, Low Heat of hydration cement
Calculations:
where :
R = modulus of rupture in MPa or psi
P = max. applied load indicated by testing machine in Ton,
N or lb.
L = span length in mm or in.
b = ave. width of specimen in mm or in.
d = ave. depth of specimen in mm or in.
FLEXURAL STRENGTH OF CONCRETE
(Using Simple Beam with Mid-Point Loading)
P
d = L/3 = 6”
R = 3PL 9” 9”
2bd²
18”
where:
R = modulus of rupture, psi (MPa)
P = max. applied load indicated by the testing machine, lb.
L = span length, in (mm)
b = ave. width of specimen, in (mm)
d = ave. depth of specimen, in (mm)
FLEXURAL STRENGTH OF CONCRETE
(Using Simple Beam with Third-Point
Loading)
Ex. R= ?
P = 7000 lb. b = 6 in.
L= 18 in. d = 6 in.
R = PL
bd²
R = 7000 (18)
6 (6)²
= 583 psi or 4.02 MPa
Example
:
One (1) set of beam sample was taken on a newly poured
(330 sq.m.) reinforced concrete pavement. The flexural
strength of the samples when tested by the third-point
method are:
Remarks:
____________
Example :
One (1) set of beam sample was taken on a newly poured
(330 sq.m.) reinforced concrete pavement. The flexural
strength of the samples when tested by the mid-point
method are:
Sample I.D. Strength
(MPa/(psi)
B1
B2 4.7 (682)
B3 5.1 (740)
3.9 (566)
Remarks:
____________
COMPRESSIVE STRENGTH OF CYLINDRICAL
CONCRETE SPECIMENS
R = P/A
where:
R = modulus of rupture, psi (MPa)
P = max. applied load indicated by the testing
machine, lb.
A = cross-sectional area of the specimen
During the application of the first half of the
anticipated load, a higher rate of loading shall
be permitted. Note the type of failure and the
appearance of the concrete.
Example :
One (1) set of cylinder sample was taken on a newly
poured (75 cu.m.) reinforced concrete pavement. The
compressive strength of the samples when tested are:
C1 23.1 (3,350)
C2 24.4 (3,538)
C3 25.0 (3,625)
Remarks: ____________
Control In
Placing
Concrete
Significance of Site Inspection
There is no substitute for site quality control
inspection in concreting work. Total dependence
on test results from control samples can be
misleading. If there are defects in workmanship,
the concrete structure may be structurally
unsound although test results are satisfactory.
This may be due to one or a combination of the
following:
1. Addition of water after samples have been taken
2. Delayed placing
3. Unsuitable weather conditions (rain or excessive
heat)
4. Inadequate compaction
5. Inadequate curing and protection
6. Defective construction control
7. Contamination of concrete mix before or during
placement
Concrete Production
Control
Whether the concrete is mixed at the site, at a
central plant or by transit mixer, the following
control measures should be strictly observed:
Portland Cement
1. Base Support.
2. Form Setting
1. Longitudinal Joint
b. Formed Groove
b. Formed Groove
Sequence
Machine Finishing
a. Non-vibratory Method
a. Hand Method.
b. Mechanical Method.
- After the final finish, but before the concrete has taken its
initial set, the edges of the pavement along each side of each slab,
and on each side of transverse expansion joints, formed joints,
transverse construction joints, and emergency construction joints,
shall be worked with an approved tool and rounded to the radius
required by the Plans. A well – defined and continuous radius shall
be produced and a smooth, dense mortar finish obtained. The
surface of the slab shall not be unduly disturbed by tilting the tool
during the use.
- The concrete shall not be left exposed for more than ½ hour
between stages of curing or during the curing period.
2.Waterproof Paper
- The seals shall be in one piece for the full width of each
transverse joint.
Protection of Pavement
1. Grade
1. Grade
2. Placing Concrete
- The machine shall vibrate the concrete for the full width
and depth of the strip of pavement being placed. Such
vibration shall be accompanied with vibrating tubes or arms
working in the concrete or with a vibrating screed or pan
operating on the surface of the concrete.
Concrete Pavement – Slip Form Method
2. Placing Concrete
2. Placing Concrete
3. Finishing
4. Curing
5. Joints
1. General
1. General
- The last unit in each slab constitutes a lot in itself when its
length is at least ½ of the normal lot length. If the length of the
last unit is shorter than ½ of the normal lot length, it shall be
included in the previous lot.
- Each lot will be divided into five (5) equal segments and
one core will be obtained from each segment in accordance with
AASHTO T 24.
1.Tolerance in Pavement Thickness
2. Pavement Thickness
2. Pavement Thickness
2. Pavement Thickness
2. Pavement Thickness
Portland Cement
Fine Aggregate
Reinforcing Steel
It shall conform to the requirements of Item 710, Reinforcing
Steel and Wire Rope.
Admixtures
Admixtures shall conform to the requirements of Subsection
311.2.
Curing Materials
Curing materials shall conform to the requirements of Subsection
311.2.8.
* The measured cement content shall be within plus or minus 2 mass percent of the design
cement content.
** Based on 40 kg/bag
Minimum Maximum Consistency Designated Minimum
Class Cement Water/ Range in Size of Coarse Compressive
Of Content Cement Slump Aggregate Strength of
Concrete Per m3 Ratio mm (inch) Square Opening 150x300mm
kg kg/kg Std. mm Concrete
(bag**) Cylinder
Specimen at
28 days,
MN/m2 (psi)
Portland Cement
The batch shall be so charged into the mixer that some water
will enter in advance of cement and aggregate. All water shall be
in the drum by the end of the first quarter of the specified mixing
time.
Mixing shall begin within 30 minutes after the cement has been added
either to the water or aggregate, but when cement is charged into a mixer
drum containing water or surface wet aggregate and when the
temperature is above 32oC, this limit shall be reduced to 15 minutes. The
limitation in time between the introduction of the cement to the aggregate
and the beginning of the mixing may be waived when, in the judgement of
the Engineer, the aggregate is sufficiently free from moisture, so that there
will be no harmful effects on the cement.