Network Diagram Exercises
Network Diagram Exercises
PRESENTATION BY:
AJAY R. LAQUI
1. Number the events of the following networks in proper sequence.
2 4
1 6
3 5
2. Construct a network diagram from the following information :
b c,d 13
c e 8
d end 5
e end 3
3. Construct a network diagram from the following information :
f g, h 10
g i,j 10
h j 8
i end 6
j k 12
k end 7
4. From the following information, draw the CPM network and number the events in their
proper sequence.
• A, B and C are starting activities and may begin at the same time.
• D and E follows A and cannot start until A is completed.
• G follows and depends on C.
• F is dependent on the completion of B and D.
• G and F must be done before H can start.
• J also depends on G and F and it is an ending activity.
• I is also an ending activity but it cannot start until E and H are completed.
Activity Precedes
A D,E
B F
C G
D F
E I
F H,J
G H,J
H I
I end
J end
5. Draw the network diagram of the following information:
• A is the first job of the project.
• O and N are the two final job for the project completion.
• K precedes O.
• N follows L and M.
• J restricts the start of K and M.
• C and B depends on the completion of A.
• D follows B and may go on in parallel with C and E.
• E follows C
• I restricts the start of J and L
• H and G also restricts K and M.
• F must precede F and may go in parallel with H.
• E and D restrict H and I.
• C must precede F.
Activity Precedes
A C,B
B D
C E
D H,I
E H,I
F G
G K,M
H K,M
I J,L
J K,M
K O
L N
M N
N end
O end
6. Draw the following network: