Types of Estimation
Types of Estimation
Types of Estimation
ESTIMATION SPECIFICATION
AND CONTRACTS
METHODS OF ESTIMATION
ESTIMATION SPECIFICATION AND CONTRACTS
L T P C
4 0 0 3
The objective of this course is to enable the students to:
• Understand the quantity calculations of different components of the buildings.
• Understand the rate analysis of different quantities of the buildings components.
• Learn various specifications and components of the buildings.
UNIT I
General items of work in Building – Standard Units Principles of working out
quantities for detailed and abstract estimates –Approximate method of Estimating.
UNIT II
Rate Analysis – Working out data for various items of work over head and contigent
charges.
UNIT III
Earthwork for roads and canals, Reinforcement bar bending and bar requirement
schedules.
UNIT IV
Contracts – Types of contracts – Contract Documents – Conditions of contract,
Valuation of buildings Standard specifications for different items of building
construction.
UNIT V
Detailed Estimation of Buildings using individual wall method.
UNIT VI
Detailed Estimation of Buildings using centre line method.
FINAL EXAMINATION PATTERN:
The end examination paper should consist of SIX questions from Unit 1 to Unit 4, out
of which THREE are to be answered (60% weight-age) & ONE mandatory question
(40% weight-age) from Units 5 & 6 is to be answered.
Text Books:
1. Estimating and Costing, B.N. Dutta, UBS publishers, 2000.
2. Civil Engineering Contracts and Estimates, B. S. Patil, Universities Press (India)
Pvt. Ltd., Hyd.
3. Construction Planning and Technology, Rajiv Gupta, CBS Publishers &
Distributors Pvt. Ltd. New Delhi.
4. Estimating and Costing, G.S. Birdie.
References:
1. Standard Schedule of rates and standard data book, Public works department.
2. IS 1200 (Parts I to XXV-1974/ Method of Measurement of Building & Civil Engg
Works – B.I.S.
3. Estimation, Costing and Specifications, M. Chakraborthi; Laxmi publications.
4. National Building Code
ESTIMATION
Estimation is the scientific way of working out
the approximate cost of an engineering
project before execution of the work.
2) SPECIFICATIONS
a) General Specifications:
This gives the nature, quality of work and materials in general
terms to be used in various parts of wok. It helps to form a
general idea of building.
b) Detailed Specifications:
This gives the detailed description of the various items of work
laying down the Quantities and qualities of materials, their
proportions, the method of preparation workmanship and
execution of work.
3) RATES
For preparing the estimate the unit rates of each item of
work are required.
1. For arriving at the unit rates of each item.
2. The rates of various materials to be used in the
construction.
3. The cost of transport materials.
4. The wages of labor, skilled or unskilled of masons,
carpenters, Amador, etc.,
LUMPSUM:
While preparing an estimate, it is not possible to work out in
detail in case of petty items. Items other than civil
engineering such items are called lump sum items or simply
L.S.Items.
Factors to be considered for estimation
Example 2 (ctd)
Extra for internal installations = 14 % of the buiding cost
Extra for electric services = 12.5 % of buiding cost
Extra for sui gas services = 6 % of buiding cost
Extra due to deep foundations at site = 1.0 % of buiding
cost
Contigencies = 2.5 % overall
Supervision charges = 8 % overall
Design charges = 2.5 % overall
2.DETAILED ESTIMATE
• Detailed estimates are prepared by carefully and
separately calculating the costs of various item of the
work that constitute the whole project from the
detailed working drawings after the design has been
finalized.
Length of Long wall = 5.3+0.9 = 6.2 m Length of Short wall = 4.3-0.9 = 3.4 m
Quantity of concrete in foundation = 2 x (6.2+3.4) x 0.9 x 0.3 cu.m
Estimation of Quantity of
Brickwork in 1st step Foundation
Center Line method:
Total Length of Center Line = 5.3+5.3+4.3+4.3 = 19.2 m
width of foundation = 0.6 m
Total quantity of brickwork in 1st step foundation = 19.2 x 0.9 x 0.3 cu.m
Long Wall & Short Wall method:
Length of Long wall = 5.3+0.6 = 5.9 m Length of Short wall = 4.3-0.6 = 3.7 m
Quantity of brickwork in 1st step foundation = 2 x (5.9+3.7) x 0.6 x 0.3 cu.m
Estimation of Quantity of
Brickwork in super structure
Center Line method:
Total Length of Center Line = 5.3+5.3+4.3+4.3 = 19.2 m
width of wall = 0.3 m Total quantity of brickwork in wall = 19.2 x 3.5 x 0.3 cu.m
Long Wall & Short Wall method:
Length of Long wall = 5.3+0.3 = 5.6 m Length of Short wall = 4.3-0.3 = 4.0 m
Quantity of brickwork in wall = 2 x (5.6+4.0) x 0.3 x 3.5 cu.m
Problem-2
Estimate in detail the quantities of following items of work for a
given plan and section as shown in Fig.2 using Centre line method
and Long wall & short wall method.
Concrete in foundation
Brickwork in 1st step in foundation
First class brickwork in super structures
Estimation of Quantity of
Concrete in Foundation
Center Line method:
Total Length of Center Line = (4 x 5.3) +(3 x 4.3) = 34.1 – 0.9 = 33.2 m
width of foundation = 0.9 m
Total quantity of concrete in foundation =33.2 x 0.9 x 0.3 cu.m
Long Wall & Short Wall method:
Length of Long wall = 5.3+5.3+0.9 = 11.5 m Length of Short wall = 4.3-0.9 = 3.4 m
Quantity of concrete in foundation= [ (2x11.5) + (3X3.4) ] x 0.9 x 0.3 cu.m
References:
https://www.wikipedia.org/
https://nptel.ac.in/course.php
THANK YOU