Project Mana
Project Mana
• 1 • Project 1 • Project 2
A None2
B A 1
C B 1
D C 2
E C 5
D(2)
F D,E 5
G F 1
E(5)
Determine early starts and early finish times
ES=4
EF=6
Hint:
Hint:Start
Startwith
withES=0
ES=0
and
andgogoforward
forwardininthe
the E(5)
network
networkfrom
fromAAtotoG.
G.
Hint:
Hint:Start
Startwith
withLF=15
LF=15or
orthe
the
total
total time of the project andgo
time of the project and go
backward
backwardininthethenetwork
networkfrom
from
ES=4
Determine late starts EF=6
GGto
toA.A.
and late finish times
ES=0 ES=2 ES=3 D(2) ES=9 ES=14
EF=2 EF=3 EF=4 EF=14 EF=15
LS=7
LF=9
A(2) B(1) C(1) F(5) G(1)
ES=4
LS=0 LS=2 LS=3 EF=9
LS=9 LS=14
LF=2 LF=3 LF=4 LF=14 LF=15
E(5)
LS=4
LF=9
Critical Path & Slack
ES=4
EF=6 Slack=(7-4)=(9-6)= 3 Wks
LS=4
Duration=15 weeks
LF=9
Economic Value Management
• Measure of Economic value of the project as it
is executed.
• Economic Value Management (EVM) is a
management approach towards managing the
shareholder ‘value’ in an organization.
.
• Schedule – It shows the estimated time for
each activity
• Budget – It shows estimated cost of each
principal part of the project
• The comparison can be made either at a
specified milestone being reached or after
specified time periods
THE THREE QUESTIONS
Q.1 Is the project going to be finished by the
scheduled date ?
Q.2 Is the completed work going to meet the
stated specifications ?
Q.3 Is the work going to be done with the
estimated cost ?
The Trade Off
• It is sometimes desirable to make trade offs
among time, specifications and cost using the
financial model and other available
information.
Types of Reports
• Trouble Reports
• Progress Reports
• Financial Reports
TROUBLED REPORTS
• They report both on trouble that has already
happened and also anticipated future trouble
• There is a need to reach the appropriate manager
so that corrective action can be taken
• Any medium can be chosen
• Precision is sacrificed in the interest of speed
• If the matter reported is significant it is
documented to keep as a record
PROGRESS REPORTS
• These compare actual schedule and costs with
planned schedule and costs
• Overhead activities not directly involved with
the project can also be calculated similarly
• Variances associated with price, schedule
delays and similar factors can be identified
and measured quantitatively
FINANCIAL REPORTS
• These are actual reports of project costs that must
be prepared as a basis for progress payments
• These reports are less important for management
control purposes than the cost information
contained in progress reports
• They are carefully checked for their accuracy
• Approximate information that is available quickly
is more important to project management
Other related aspects
• Quantity of reports
• Percent complete
• Summarizing Progress
• Punch List
QUANTITY OF REPORTS
• Sometimes more than optimum numbers of
reports are prepared
• This incurs extra costs and spends extra time
• Sometimes important information is
overlooked
• Though this is not a serious problem because
managers normally know which reports or
section of reports are important
Project Execution