VARIATION ORDER
PRESENTATION OUTLINE
I. INTRODUCTION
A. DPWH BOC alignment of objectives
II. DEFINITION
III. FORMS OF VARIATION ORDER
A. Variation Order
B. Change Order
C. Extra Work Order
IV. PROCEDURES FOR EVALUATION
A. Request for Prior Clearance/Authority to Issue Variation Order
B. Variation Proper
V. REFERENCES
A. Revised IRR of R.A 9184
B. Department Order No. 28, Series of 2015
C. Department Order No. 95 , Series of 2013
D. Department Order No. 52 , Series of 2012
E. Department Order No. 47, Series of 2012
F. Department Order No. 04, Series of 2012
G. Department Order No. 54 , Series of 2011
VARIATION ORDER
G. Department Order No. 28, Series of 2015
H. Condition of Contract
I. Federation International Des Ingenieurs-Conseils (FIDIC)
J. Loan Agreement from the lending institution
K. Exchange Notes
V. REQUIREMENTS/CHECKLIST OF DOCUMENTS PER D.O. NO. 52 SERIES OF 2012
VI. STANDARD FORMS FOR VARIATION ORDER
VII. LEVELS OF AUTHORITY
VIII.PANEL DISCUSSION
INTRODUCTION
ALIGNMENT TO DPWH OBJECTIVES
P DPWH OBJECTIVES I C N X BOC OBJECTIVES
projects
B Safe environment
C
Stakeholders
External
All new components of the new work item shall be fixed prices,
provided the same is acceptable to both the Government and the
contractor, and provided further that the direct unit costs of new
components shall be based on the contractor's estimate as validated
by the procuring entity concerned via documented canvass in
accordance with existing rules and regulations.
The direct cost of the new work item shall then be combined with the
mark-up factor (i.e., taxes and profit) used by the contractor in his
bid to determine the unit price of the new work item.
Procedures for Evaluation
The Two-Step Processing Procedure
The processing of variation orders consists of a two step
procedure wherein a request for prior clearance/authority to
issue Variation Order must first be submitted so that the
technical viability of the revisions can be studied including the
legal basis into which it is going to be anchored. If such clearance
is approved (D.O. 04, S. 2012), the Variation Order Proper may be
given its due course.
Request for Prior Clearance/Authority to
Issue Variation Order
The purpose of the request for prior clearance/authority to issue
Variation Order is to serve as an “annuncio” to the approving
official about the need for the additional works/variations. The
clearance should however not be taken as an outright approval
for the variation order. As this is considered to be a preliminary
stage of the procedure in the preparation of the variation order
proper, it consists of TENTATIVE INFORMATION AS TO COST and
contains the TECHNICAL JUSTIFICATION and LEGAL BASIS to
which reason, the variation order is being proposed.
Elements of Variation Order
A Variation Order should specify and include the following:
a. For work items which are exactly the same or similar to those
in the original contract, the applicable unit prices of work items
in the original contract shall be used.
REFERENCE FOR VARIATION ORDER
5. Republic Act (R.A.) No. 9184 and Its Implementing Rules and
Regulations Section 2, Annex E – Additional/Extra Work Costing
for Variation Orders:
b. For new work items that are not in the original contract, the
unit prices shall be based on the direct unit cost used in the
original contract (e.g. unit cost of cement, rebars, forms lumber,
labor rate, equipment rental, etc.).
All new components of the new work item shall be fixed prices,
provided the same is acceptable to both the Government and the
Contract, and provided further that the direct unit cost of new
components shall be based on the contractor’s estimate as
validated by the procuring entity concerned via documented
canvass in accordance with existing rules and regulations. The
direct cost of the new work item shall then be combined with
the mark-up factor used by the contractor in his bid to determine
the unit price of the new work item.
REFERENCES FOR VARIATION ORDER
D.O. No. 95, Series of 2013 – Reissuance of D.O. No. 9, Series of 2011
RE: Conduct of Pre-Procurement, Procurement, and Implementation
Activities for DPWH Foreign Assisted Civil Works Projects.
Additional scope of works refers to works outside but contiguous to the original
project limits. The approval of VO covering addition/deletion of works within
the original project limits and the additional scope of works shall still be in
accordance with Department Order No. 54, series of 2011. The cumulative
amount of the positive or additive VO shall not exceed ten percent (10%) of the
original contract price pursuant to the Implementing Rules and Regulations of
R.A. No. 9184.
This Order amends pertinent provisions of Department Order No. 54, series of
2011 and shall take effect immediately.
DEPARTMENT ORDER 04,
Series of 2012
SUBJECT : DELEGATING THE APPROVAL OF
PRIOR CLEARANCE FROM THE
SECRETARY TO ISSUE VARIATION
ORDERS OF LOCALLY-FUNDED CIVIL
WORKS PROJECTS
In line with our continuing effort to simplify operating procedures and expedite
the implementation of projects, approval of requests for prior clearance from
the Secretary to issue Variation Orders on locally-funded Civil Works projects
undertaken by Regional and District Engineering Offices, is hereby delegated to
Regional Directors.
This Order amends pertinent provisions of D.O. No. 12, series of 2009, and
takeseffect immediately.
D.O. 28, Series of 2015 – SPECIFIC GUIDELINES TO
MANAGE AND CONTROL VARIATION ORDERS FOR
DPWH INFRASTRUCTURE CONTRACTS
To reduce the incidence and improve the management of Variation Orders
(VOs) for infrastructure contracts undertaken by the DPWH, all concerned are
hereby directed to observe the following guidelines in relation to the provisions
of Annex E (Contract Implementation Guidelines for the Procurement of
Infrastructure Projects) of the Implementing Rules and Regulations(IRR) of
Republic Act (RA) No. 9184:
1. Executive Summary / This is where the Implementing Office explains the need
Memorandum request for the variation order which must be technically and
for clearance/authority legally justifiable. Likewise, the Implementing Office
must state in the Executive Summary/Memorandum
request for clearance/authority the approximate cost
and scope of work of the proposed variation order.
3. Design analysis & This is where the Bureau of Design requirements in the
Computations for the processing of Variation Order.
proposed variation
4. Copy of Complete set of The copy of complete set of approved plans is being
the approved plans (As- required to check if the quantities of all the items of
staked, Original, Revised and As-Built) work involved is correctly reflected in the Itemized Cost
of Revision.
5. Copy of approved The approved request for clearance/authority to issue
clearance/authority to variation order is being required as this is the proof of
issue the proposed compliance to the two-step procedure and that the
variation order approval involving the proposed variation order has
already been accepted in principle by the Secretary.
CHECKLIST OF REQUIREMENTS AS PER D.O. NO.52, SERIES OF 2012
12. Project Engineer’s Report/ The Project Engineer’s Report is being required in
Consultant Resident compliance with the provisions of the IRR-A of RA
Engineer’s Report 9184.
The Project Engineer’s Report therefore, must be
within the above mentioned guidelines which state
that if the Project Engineer finds the variation order
justifiable, he must prepare the proposed order and
submit same to the Director together with the
supporting documents.
CHECKLIST OF REQUIREMENTS AS PER D.O. NO.52, SERIES OF 2012
13. Itemized Cost of Revision It contains the detailed cost computation of all the
changes in the amount of the contract including the
previous changes that were approved in Variation
Orders, if there is any.
14. Straight-line Diagram The Straight Line Diagram should be in color code and reflect
showing the proposed the proposed works under the original/existing contract
works and the proposed works under the Variation Order with the
station limit.
15. Derivation of Time The derivation of proposed time extension, if there is any,
Extension for the for the should be based only on the items of work which is along the
proposed Variation Order critical path of the latest approved Construction Schedule (
PERT/CPM & BAR CHART).
(C.O./E.W.O.)
It is advised that to properly represent this requirement, the
contractor be made to submit a draft revision of the
PERT/CPM incorporating the necessary changes, so that the
effect in the contract with respect to the works, may be
appropriately derived based on reasoning.
16. Complete Contractual Data It contains all the necessary information including the
with Project Status Report contract cost, contract schedule, contract status, issues and
concerns and the corresponding actions being undertaken by
the Implementing Office.
CHECKLIST OF REQUIREMENTS AS PER D.O. NO.52, SERIES OF 2012
17. Detailed Unit Cost Analysis DUPA of original items of work and new items of work
for new items of work. in a variation order will be used in the verification is
such figures reflected in the DUPA are the same
figures used in the proposed new unit price in
accordance with the contract requirement.
18. Approved Price Basis in adjusting the unit cost of items of work under
Adjustment/Escalation (if the original contract.
there’s any)
19. Obligation Request The Certificate of Availability of Funds is being required if
(ObR)/Certificate of Availability there is fund to finance the additional work. It must be issued
of Funds (CAF) by the Dept. of Budget Officer and must be to the least,
equal to the amount of the proposed variation order. There
are cases that the funds for the proposed variation order is
insufficient and only an additional certification is being
submitted issued by the Planning Service that the Funds to
complete the amount of the Variation Order is programmed
in the infrastructure budget of the Department.
20. Copy of previously approved Copy of previously approved Variation Order and Time Extension
Time Extension and Variation is being required to check the computation of the revised
Order (if there’s any) contract amount and time. Although these were already
required during the processing of request for Prior
Clearance/Authority to Issue Variation Order, it is likewise
required in the processing of the variation order proper as an
attachment to prove that it was made as basis in the review of
the figures previously mentioned.
CHECKLIST OF REQUIREMENTS AS PER D.O. NO.52, SERIES OF 2012
21. If with additional cost, Additional Performance Bond is required per IRR-A of RA 9184
Performance Security which states that the contractor shall post an additional
(duly verified by SAC) performance security in accordance with the following schedule
to cover any cumulative increase of more than ten per cent over
the original value of the contract as a result of amendments due
to variation orders.
22. Latest income tax and These documents are being required to determine if the
business tax returns duly contractor is religiously paying his obligations to BIR.
stamped and received by the
BIR and duly validated with
the tax payments made
thereon. Tax Clearance from
the BIR to prove full and
timely payments of taxes.
23. Certification under oath As additional support to Item 22
stating that the Contractor is
free and clean of all Tax
Liabilities to the Government
24. One set certified true copy of For file/Reference in the future
all the documents submitted
for accounting’s copy
STANDARD FORMS USED IN VARIATION ORDER
VARIATION ORDER
Republic of the Philippines
Department of Public works and Highways
Implementing Office
Project/Location :
To : Name of Contractor
You are hereby directed to make herein described changes from the plans and specifications of the following described work not included in the plans and specifications:
CHANGE REQUESTED BY :
(Work to be performed at agreed price.)
ITEMIZED QUANTITIES AND COST OF REVISION IS SHOWN ON THE ATTACHED BILL OF QUANTITIES AND COST ESTIMATE
We the undersigned Contractors have given careful consideration to the change proposed Difference in Cost due to this Change : PhP (+) or (-)
and hereby agree, if this proposal is approved that we will provide all equipment, furnish all Net Cost of Previous Change :
materials except as maybe otherwise be noted and perform all services necessary for work Total Cost of Change :
above specified and will accept as full payment thereto the prices shown on the second Original Contract Amount : PhP
page of the attached sheet. Estimated Revised Contract Amount : PhP
Percentage Change in Original Contract Value (+) or (-) :
CONTRACTOR :
District Engineer/
NOTE: This Variation Order is not effective until approved. Regional Director
Undersecretary
Secretary
ITEMIZED COST OF REVISION
(Proposed Variation Order No. __)
Project : ______________________
Location : ______________________
Contractor : ______________________
TOTAL AMOUNT
Project Engineer Chief, Planning & Design Section/ Chief, Construction Section
Conforme:
Contractor
LEVELS OF AUTHORITY
LEVELS OF AUTHORITY
D.O. No. 54, Series of 2011 – Revised Limits of Responsibilities and
Authorities of Concerned DPWH Offices and Official in the Conduct of Pre-
Procurement, Procurement, and Implementation Activities for DPWH
Locally – Funded Civil Works Projects.