FINAL
FINAL
CRASHING,UPDATING,
RESOURCE ALLOCATION
Presented By : Deepika
Pooja
Shivang
Shifali
Gagandeep
Arvinder
Project Crashing
The process of accelerating a project is referred
as crashing.
Crashing a project relates to resource
commitment; the more resources expended, the
faster the project will finish.
There are several reasons to crash a project:
Initial schedule was too optimistic
Market needs change and the project is in demand
earlier than anticipated
The project has slipped considerably behind schedule
There are contractual late penalties
Project Crashing
Principal methods for crashing are:
Improving existing resources’ productivity
Changing work methods
Increasing the quantity of resources
Increasing the quantity of resources is the most
commonly used method for project crashing.
There are 2 approaches:
Working current resources for longer hours
(overtime, weekend work, etc.)
Adding more personnel
Project Crashing
Normal Activity
Normal
cost
Normal
time
Time-Cost Tradeoff
Min total cost = Total project cost
optimal project
time Indirect cost
Direct cost
time
Project Crashing
In analyzing crash options, the goal is to find the
point at which time and cost trade-offs are
optimized.
2 4
12
8
7
1 4
12
3 6
4 5 4
4
Time Cost data
R400 3 6
4 5 4
4 R200
R3000
R200
R500 R7000
2 4
8 12 R700
To….. 7
1 4
Project 7
duration = 31 6
R400 3
Additional cost = 4 5 4
R2000 4 R200
R3000
R200
UPDATING PROJECT
• Can be done in 2 ways
– Use the revised time estimate of incomplete activities
and calculate from initial event the earliest completion
time and the latest completion time of each event in the
usual manner to know the Project completion time.
– Change the complete work to zero duration and
represent all the activities already finished by an arrow
called the Elapsed time arrow. Events in the revised
network are renumbered.
• The network for a project is shown below. A review of the project after 15
days reveals that
– Activities 1-2, 1-3, 2-3, 2-4 and 3-4 are completed.
– Activities 3-5 and 4-6 are in progress and need 2 and 4 days more
resp.
– The revised estimate shows that activity 8-9 will take only 8 days but
activity 7-9 will need 10 days.
• Draw the new network after updating the Project and determine the
Critical path.
3
8
24 10 34
0 6
4 8 9
1
24 34
0
9
2
7 7 14 19 8
3 5 5 7
7 15 26
Network at the start of the Project Review at the end of 15th day
7 8 3-5(13-15) 2 In Progress
7 14 19
3 5 5 7 4-6(14-16) 4 In Progress
7 15 26
5-7(15-17) 5 Not started
2
3 7
4
13
14
16
19
New critical path
15
3 13 19
1-2-3-4-14-16-18-
12
3
8 19
27 8 35
0 6
4 18 19
1
0 9
27 35 Project duration
2
10 increased by 1
7
(Finished 3-5) 8 15 2 17 22
day to 35 days
13
3 15 5 17
15
7 18 25
Network at the start of the Project Review at the end of 15th day
Activity Time reqd. Activity
(Days) Status
3 7 13 3 16
2 4 6 1-2 0 completed
12
3 13 16
1-3 0 completed
3
8 2-3 0 completed
24 10 34
0 6 2-4 0 completed
4 8 9
1 24 34
0 3-4 0 completed
2 9
3-5(10-15) 2 In Progress
7 7 14 19 8 4-6(10-16) 4 In Progress
3 5 5 7
7 15 26 5-7(15-17) 5 Not started
7-9(17-19)
12
10
Not started
Not started
8-9(18-19) 8 Not started
Updated Network after day 15 of the Project
19
New critical path
12
16
19 1-10-16-18-19
4 8
27 8 35
18 19
1
0 15
10
15 27 35
Project duration
0 15
2
9
10 increased by 1
17 22
15
18 5 17
25
day to 35 days
Resource Allocation Problem
A shortcoming of most scheduling procedures is
that they do not address the issues of resource
utilization and availability.
Critical path:A-C-F-H-K
Resource Leveling Example
Critical path:A-C-F-H-K
Resource Leveling Example
Activity Duration Total Float Resource Hours Total Resources
Needed Per Week Required
A 5 0 6 30
B 4 1 2 8
C 5 0 4 20
D 6 3 3 18
E 6 1 3 18
F 6 0 2 12
G 4 3 4 16
H 7 0 3 21
I 5 3 4 20
J 3 5 2 6
K 5 0 5 25
Total 194
Resource Leveling Example
Resource Leveling Example
On day 10 the required resource hours is 10
If project is budgetted for up to 10 resource
units per day, then it is acceptable.
C, D, and E are all scheduled on this day and
have require 4, 3, and 3 hours respectively
Which activity should be adjusted?
C is on the critical path
E has 1 day slack
D has 3 days of slack (we can split the
activity)
Resource Leveling Example
Resource Loading Chart
Another way to create a visual diagram of
resource management problem is to use resource-
loading charts.
Resource conflicts can be seen in the resource-
loading charts.
They are used to display the amount of resources
required as a function of time on a graph.
Each activity’s resource requirements are
represented as a block (resource requirement over
time).
Resource Loading Chart
Resource limit is set at 8 hourly units per day.
Display the amount of resources required as a function of time.
4 B 5 5 D 9 9 E 11
Res = 2 Res = 7 Res = 3
1. Start with a
0 A 4 network diagram
Res = 6 11 F 12
Res = 6
4 C 7
Res = 2
Resource Loading Chart
Activity Resource Duration ES Slack LF
A 6 4 0 0 4
B 2 1 4 0 5
C 2 3 4 4 11
D 7 4 5 0 9
E 3 2 9 0 11
F 6 1 11 0 12
2. Produce a table that shows the
duration, early start, late finish,
slack, and resource(s) required for
each activity.
Resource Loading Chart
3. Draw an initial loading chart with
8 each activity scheduled at its ES.
Resources
6
Resource
4 imbalance
A D F
B
2 E
C
2 4 6 8 10 12 14
Project Days
Resource Loading Chart
4. Rearrange activities within their slack
to create a more level profile. Splitting
8 C creates a more level project.
Resources
4 C
A D F
B
2 E
C
2 4 6 8 10 12 14
Project Days
Resource Loading Chart