PLANNING &
MONITORING
NEEDS SATISFACTION
refers to
predetermined
course/s of action
to achieve a
desired end/goal.
“Process of
identifying which
project needs can
be best met by
procuring products
and services
outside the project
organization and
should be
accomplished
during the project
planning
Government effort”
Procurement Policy Board – Technical Support Office
WHY PROCUREMENT
PLANNING
Ensures that the overall goal of a particular project will be
effectively and efficiently achieved.
Program /Service Work & Financial
Procurement Plan
Goals & Targets Plan
WFP
WFP
Secretariat
EUU PU/Secretariat
Finance Unit HOPE posts APP &
formulates Consolidates
validates approves APP submit to
PPMP to agency APP
GPPP
APPROVING
TECHNICAL BIDS AND AWARDS
WORKING GROUP AUTHORITY/HoPE
COMMITTEE (BAC)
24
Each end-user unit shall prepare the PPMP during the budget
preparation to support the cost estimates in the budget proposal.
Choose
Choose thethe
Compare the
Compare the
Best
Best
alternatives
alternatives Alternative
Alternative --
(consider
(consider the
the one
one that
that is
is
qualitative and
qualitative and
most
most beneficial
beneficial
quantitative
quantitative to
to the
the
factors)
factors) Procuring
Procuring
Entity
Entity
PPMP
Time
Extent/size
schedule
Procurement
Methods
Prepare Project
INDICATIVE PPMP TO INDICATIVE
Procurement APP
Management BASIS OF EARLY PROCUREMENT
Plan (PPMP)
ACTIVITIES (EPA)
Government Procurement Policy Board – Technical Support Office
RATION OF THE FINAL PPMP & APP
GAA, Corporate Budget or
Appropriation Ordinance is Approved HOPE/Approving
Body
BAC &
Secretariat
End-User
Unit
Approval of APP
by HOPE/
Budget Consolidation of oversight body
PPMPs to APP by
Office Finalize Project BAC Sec and
Procurement recommendation by
Management BAC of modality
Plans (PPMPs)
Provide
comments on
Indicative
PPMPs to end-
users
By month
Qty
Estimated
General
c Budget
Description
o
d
e
Q1 Q2 Q3 Q4
Downloadable at http://www.gppb.gov.ph/downloadables/SampleForms.html
cash (e.g. premiums for surety bond, bank fees and other
component.
Acquisition Cost
Operation Cost
Replacement/Repair Cost
Government Procurement Policy Board – Technical Support Office
DETERMINING THE ABC
If the sum of the different cost components is lower than the
Checking of Recommendation
procurement of procurement
methods methods by the BAC
Propose
procurement
methods (End-user)
Mode of Procurement
Sources of Funds
Consolidate
PPMP/s to BAC &
Updated/
BAC
Supplemental
APP Secretariat
Approve
Updated/
Supplemental HOPE
APP
1 2 3 4 5 6 7 8
Drop down lists (if using App) are available for Mode of
Government Procurement Policy Board – Technical Support Office
Early Procurement Activities (EPA)
Procurement Short of Award
3.1 EPA shall refer to the conduct of procurement activities, from posting of the procurement
opportunity, if required, until recommendation of the BAC to the HoPE as to the award
of the contract, for goods to be delivered, infrastructure projects to be implemented and
consulting services to be rendered in the following FY, pending approval of their
respective funding sources
3.2 Award of contract for Procurement Projects undertaken through EPA may be made only
upon:
3.2.1 approval and effectivity of their respective funding sources, to wit: (i) GAA; (ii)
Corporate Budget; (iii) Appropriations Ordinance; or (iv) loan agreement in the
case of FAPs; or
3.2.2 reenactment of the previous year’s budget which constitutes the current year’s
authorized budget, when authorized by the Constitution, law or rules.
4. BID VALIDITY
• PE may request the bidders to extend the validity of their bid securities beyond
one hundred twenty (120) calendar days, prior to their expiration, if the funding
source for the Procurement Project has yet to be approved and made effective.
• A change in the form of the bid security is allowed if this is made prior to the
expiration of the bid validity sought to be extended.
• If the bidder refuses to extend the bid validity, the PE shall reject the bid submitted
by said bidder.
5. PROCUREMENT TIMELINES
EPA shall observe the mandatory timelines set forth in the 2016 RIRR of RA
9184:
from posting to recommendation of the BAC to the HoPE as to the award of
the contract
including the period for re-bidding which shall be within fifteen (15) days
after each declaration of failure of bidding, which may be extended up to
thirty (30) days upon approval of the HoPE
Government Procurement Policy Board – Technical Support Office
Early Procurement Activities (EPA)
GPPB CIRCULAR 06-2019 17 July 2019
Guidelines on the Implementation of Early Procurement Activities (EPA)
6.2. Upon approval of the APP and the commencement of the running of the period to
award the contract and complete the procurement process, the HoPE may approve
or disapprove the recommendation of the BAC.
Approval – HoPE shall issue the NOA to LCRB/HRRB, and thereafter sign the
contract.
Disapproval - HoPE shall notify the BAC and the bidder in writing of such
decision and the grounds thereof which shall be any of the grounds provided for
under Section 41, 2016 RIRR
Government Procurement Policy Board – Technical Support Office
Early Procurement Activities (EPA)
GPPB CIRCULAR 06-2019 17 July 2019
Guidelines on the Implementation of Early Procurement Activities (EPA)
7. AWARD OF CONTRACT
7.1. Notwithstanding the mandatory procurement timelines provided in Section 37 of RA No. 9184, Procurement
Projects (PP) undertaken through EPA may be awarded upon approval and effectivity of the GAA, reenacted
budget, appropriations ordinance, corporate budget or loan agreement, as the case may be.
7.2 If the amount authorized for a PP has been reduced, the PE may still make an award if the contract price to
be awarded is within the amount authorized in the GAA, reenacted budget, appropriations ordinance,
corporate budget, or loan agreement regardless of the posted ABC.
7.3. The HoPE shall not award any PP if the amount therefore has been withdrawn or in the event the amount
authorized is lower than the amount of contract to be awarded
7.4. In all instances, the HoPE has the authority to exercise the reservation clause under Section 41 of RA No.
9184, which grants the HoPE the right not to award the contract if, for any justifiable and reasonable ground,
the award of the contract will not redound to the benefit of the government.
7.5. Notwithstanding the approval and effectivity of the GAA/ budget/loan agreement, PEs shall not award
contracts for Projects requiring Special Allotment Release Order or Sub-Allotment Release Order until the
same has been issued, secured or released.
4.1.b
Update the PhiIGEPS posting of all Invitations to Bids and awarded
contracts pursuant to the GPRA(RA No. 9184) for transactions above
Php 1 million from January 1 to December 31, 2019, including Early
Procurement of FY 2020 Non - Common Use Supplies and Equipment
(Non - CSE) items. Agencies should track their status of compliance
through the PhiIGEPS microsite:
https://data.philgeps.gov.ph/pbbweb/pbbwebapp.aspx
SECTION I. INVITATION TO BID SECTION I. INVITATION TO BID SECTION II. INSTRUCTIONS TO BIDDERS
SECTION II. INSTRUCTIONS TO BIDDERS SECTION II. INSTRUCTIONS TO BIDDERS
SECTION III. BID DATA SHEET
SECTION III. BID DATA SHEET SECTION III. BID DATA SHEET SECTION IV. GENERAL CONDITIONS OF
CONTRACT
SECTION IV. GENERAL CONDITIONS OF SECTION IV. GENERAL CONDITIONS OF
CONTRACT (GCC) CONTRACT SECTION V. SPECIAL CONDITIONS OF
CONTRACT
SECTION V. SPECIAL CONDITIONS OF SECTION V. SPECIAL CONDITIONS OF
CONTRACT (SCC) CONTRACT SECTION VI. TERMS OF REFERENCE
SECTION VI. SCHEDULE OF SECTION VI. SPECIFICATIONS
REQUIREMENTS
SECTION VII. DRAWINGS
SECTION VII. TECHNICAL
SPECIFICATIONS SECTION VIII. BILL OF QUANTITIES
SECTION VII. BIDDING FORM
SECTION VIII. BIDDING FORMS SECTION IX. BIDDING FORMS SECTION VIII. APPENDICES
SECTION IX. FOREIGN-ASSISTED SECTION X. FOREIGN-ASSISTED
II. Instruction to Bidders EXAMPLE
A. General
1. Scope of Bid
1.1 The Procuring Entity named in the BDS, invites bids for the construction of Works, as
described in Section VI. Specifications.
1.2 The name, identification, and number of lots specific to this bidding are provided in the BDS.
The contracting strategy and basis of evaluation of lots is described in ITB Clause 27.
1.3 The successful Bidder will be expected to complete the Works by the intended completion date
specified in SCC Clause 1.17.
2. Source of Funds
The Procuring Entity has a budget or received funds from the Funding Source named in the BDS,
and in the amount indicated in the BDS. It intends to apply part of the funds received for the
Project, as defined in the BDS, to cover eligible payments under the Contract for the Works
1) Upon delivery, the Goods shall undergo preliminary physical inspection by the Inspection Team of the PROCURING ENTITY to ascertain the
physical condition and acceptability of the Goods.
2) The supplier shall promptly replace the equivalent quantity of Goods taken as samples without cost to the PROCURING ENTITY.
3) Minimum number of sample units required for each test analysis of delivered medicines shall be based on the PFDA Circular 2014-014 and
succeeding approved amendment.
4) Pending FDA analysis, said products should not be distributed to end-users nor shall it be used until such time it is cleared by FDA laboratory
testing.
5) If FDA inspection or results of laboratory analysis show major violations, the entire product line of the drug is temporarily suspended from
accreditation, regardless of the batch or lot in question.
6) All health commodities with failed FDA Test Analysis shall immediately be pulled out by the suppliers from the DOH warehouse or from the
warehouse of the DOH Service Provider within five (5) working days upon receipt of FDA test results from the Supply Chain & Management
Office (SCMO) of the DOH.
Failure to comply within the prescribed time shall compel the SCMO to have the subject commodities pulled out by the third party logistics service
provider of the DOH with the hauling and freight fees chargeable against the concerned supplier/company. In observance of the above-mentioned
timeline, please coordinate with the SCMO of the DOH.
INTRODUCTION TO
SPECIFICATIONS
WRITING
• PERFORMANCE SPECS
• FUNCTIONAL SPECS
• PHYSICAL DESCRIPTION/DESIGN SPECS
a service to be performed,
a material or product to be supplied or
works to be constructed
states the NEEDS TO BE SATISFIED by the procurement,
defines what PE WISHES TO BUY; and
defines what the BIDDER IS EXPECTED TO SUPPLY OR
PERFORM.
76
TECHNICAL SPECIIFCATIONS REQUIREMENTS
GOODS
Specifications
CONSULTING SERVICES
77
Government Procurement Policy Board – Technical Support Office
INTRODUCTION TO
SPECIFICATIONS WRITING
What is “Technical Specification”?
Communicates to the prospective supplier, contractor or service
provider what the Procuring Entity REQUIRES;
permits competition.
80
INTRODUCTION TO
SPECIFICATIONS WRITING
ACCURATE
CLEAR
LOGICAL
CONSISTENT
83
INTRODUCTION TO
SPECIFICATIONS WRITING
CHARACTERISTICS OF EFFECTIVE TECHNICAL
SPECIFICATIONS:
NON-RESTRICTIVE
84
GENERAL PRINCIPLES IN
PREPARING SPECIFICATIONS
DON’T REINVENT THE WHEEL
85
GENERAL PRINCIPLES IN
PREPARING SPECIFICATIONS
SPECIFICATION CHECKLIST
Does it describe exactly the intended requirements of
the Procuring Entity?
Does it describe the needs in terms of required function
and/or performance?
Does it indicate the end usage?
Is it clear and understandable?
Does it encourage competition?
Do you have the means you need to verify compliance?
88
EXAMPLE
EXAMPLE
GENERAL PRINCIPLES IN
PREPARING SPECIFICATIONS
Use of Standards: eq. International Organization for Standardization
Information gathering
Needs Analysis
Writing specifications
Identification of Based on the needs
PE’s needs, i.e. list What is available analysis and
of functions, on the market as information
performances, and an input to the gathering, the
technical specifications/TOR
specification/TOR.
characteristics are elaborated. It is
needed to be good practice to
included in the engage a specialist
Specification/TOR to review and
proof-read before
finalizing.
92
INTRODUCTION TO
SPECIFICATIONS WRITING
Sources of Technical Specifications:
Typical sources for compilation of Technical Specifications are previous records of successful
procurement supplemented by market research through:
2. Specifications issued by the relevant government agency (DTI for Goods, DOH for
drugs & Medicines, DPWH for works etc.)
6. The Internet and online resources like on-line catalogues (use with care to avoid
copying restrictive specifications from a brand or single source thereby frustrating
competition).
93
SPECIFICATIONS WRITING FOR
THE PROCUREMENT OF GOODS
1. Design specifications
2. Performance specifications
3. Functional specifications
95
SPECIFICATIONS WRITING:
PROCUREMENT OF GOODS
Design Specifications:
96
SPECIFICATIONS WRITING:
PROCUREMENT OF GOODS
Design Specifications:
• Typically, supplement performance and functional
specifications which are more suited for open
competition but may miss other specific requirements
of the PE which are then added through design
specifications like weight, size, color, etc.
Design Specifications:
100
SPECIFICATIONS WRITING:
PROCUREMENT OF GOODS
Performance Specifications:
Emphasize the OUTPUT performance needed from the
procured product rather than its design and structure and are
therefore easier to compile.
Do not specifically direct the bidder on the technical and
design details of the item to be delivered.
EXAMPLE: Performance specification for photocopier/label printer --- can produce
60 copies per minute and does not specify the technology or process used [ink jet
or dry process(xerography)] since such processes can be proprietary to each
manufacturer. Each supplier is then free to propose the most suitable solution to
achieve this requested performance/output.
101
SPECIFICATIONS WRITING:
PROCUREMENT OF GOODS
Functional Specifications:
102
SPECIFICATIONS WRITING:
PROCUREMENT OF GOODS
A car that can carry 6 persons safely across unpaved roads in all weather
conditions.
Possible cars that you know What are generic design specs to consider??
Jeep Wrangler Rubicon. ... Engine:
Land Rover Range Rover. ... Type of transmission:
Mercedes-Benz G-Class. ... [Off-road technology [Terrain response [Land Rover]]
Nissan Frontier PRO-4X. ... Suspension:
Nissan Xterra PRO-4X. ... Wind speed:
Toyota 4Runner Trail. ... Load Capacity:
Toyota Land Cruiser. ... Wheels:
Toyota Tacoma TRD. Driver Assistance:
etc-----
Design: Interior
Design: Exterior
Color:
103
SPECIFICATION-- PURCHASE OF VEHICLE
108
Drugs and Medicines
109
Page 1 of 2
The following should be legibly stamped on top or cover of the kit, and box:
Date of Manufacture: _____________
Date of Expiry:__________________
112
Gram Stain Kit Estimate Number of Kits
PURCHASER’S SPECIFICATION Things to Consider
A. Basic Content:
1) Crystal violet
2) Iodine
1. Historical Data
3) Decolorlizer
4) Safranin
2. Number of Test per Kit
B. Approximate number of [Test/kit Vs. Volume]??
Shelf Life: Supplies must be fresh commercial stock with total shelf life of
twenty four (24) months from the date of manufacturer but not less than
eighteen (18) months from the date of delivery.
Neoprene gloves
117
• Purpose
Wrist Brace/Ankle Brace • Design/make
• Size
• Strap
• Cuff
• Fits …
118
Wheelchair • Usage: Purpose/who uses
• Weight
• Capacity
• Manual/motorized/electric
• Armrest
• Wheels
• Protector
• Headrest
• Tilt/reclining
• Seat
• Folding
• ….
119
OXIMETER
• WHO uses: newborn,adult?
• TYPE:
• SIZE:
• DISPLAY:
• COLOR:
• …
WRIST PULSE
OXIMETER
120
Wheelchair • Use/purpose/who uses
• Weight
• Manual/motorized/electric
• Armrest
• Wheels
• Protector
• Headrest
• Tilt/reclining
• Seat
• Folding
• ….
126
SPECIFICATION– Wheel Chair
Functional Performance Design
Transport the infirm Transport sick Category:
person with mobility Size:
issues Accessories:
(Celebral palsy, Head Weight:
Injury & Spinal Cord Wheels:
Injury..) Manual:
etc
Transport elderly
129
SPECIFICATIONS WRITING:
PROCUREMENT OF GOODS
The differences in the nature of services, compared to
goods or works, have implications on the specifications,
which should cover such aspects as:
Detailed description of the services to be provided;
Time, duration, and place of service provision;
Required response times for service provision;
Required documentation in form of deliverables
and/or progress reports;
Detailed procedures and responsibilities for
supervision, acceptance of deliverables and
completion of the contract.
130
SPECIFICATIONS WRITING:
PROCUREMENT OF GOODS
• Services are specified through a document called “DESCRIPTION OF
SERVICES” or a terms of reference for the services required. It contains:
1. Background information on why the services are needed and by
whom and where;
2. Overall Objectives of the Services;
3. Detailed list of the Tasks to be performed, applicable standards for
workmanship (including ISO 9001) and materials used;
4. Frequency of provision of the Services, response time and duration of
the services;
5. Performance measurement and KPIs;
6. Reporting requirements and other deliverables like data etc.;
7. Safety and Insurance requirements.
8. Etc.
131
SPECIFICATIONS WRITING:
PROCUREMENT OF GOODS
Key Performance Indicators (KPI)
132
SPECIFICATIONS WRITING:
PROCUREMENT OF GOODS
SERVICES:
Internet Services – 100 mbps, >95% availability, MRTG to monitor & measure traffic load on
network links, Response time
Janitorial Services – satisfactory services, stability, resources, housekeeping plan, etc
Security Services - satisfactory services, stability, resources, security plan, etc
Trucking & Hauling -
Warehousing & Storage
Lease of Office Space
Lease of Venue
Media Placement
Data Center Maintenance
Air conditioners Maintenance
Vehicle Maintenance
ISP
IT services
133
EXAMPLE
EXAMPLE
SPECIFICATIONS WRITING
FOR THE PROCUREMENT OF
INFRASTRUCTURE PROJECTS
141
SPECIFICATIONS WRITING:
PROCUREMENT OF INFRASTRUCTURE
PROJECTS
• When the PE opts to shift the design responsibility to the
contractor like in:
1. Design and Build contracts (2-stage where
contractor proposes preliminary design- Annex G of
the 2016 RIRR)
2. PPP contracts like BOOT, BOT etc.
3. Design, Supply and Installation of electromechanical
plant
4. Turn-key contracts
142
SPECIFICATIONS WRITING:
PROCUREMENT OF INFRASTRUCTURE
PROJECTS
Then the PE describes its requirements in the form of
“performance specifications”.
• Example an elementary school with 12 classrooms (30
students each) and 200 sq. meters of headmaster/teachers
quarters and two 100 sq. meters spaces for PC and language
laboratories.
All classrooms to be built in accordance with Department of
Education’s (DepEd) standards for space/student, ventilation
and natural light requirements with prescribed number of
bathrooms and playgrounds. Additionally, energy efficiency
requirements may be added etc.
143
SPECIFICATIONS WRITING:
PROCUREMENT OF INFRASTRUCTURE
PROJECTS
• Commonly-used for Design, Supply and Installation of power
plants and turn-key contracts based on a “conceptual design”.
Here the PE specifies desired requirements in terms of
performance specifications like:
1. A combined cycle power plant of minimum 250 Mega watt
Net power output under continuous operation at ambient site
conditions with guaranteed availability of min 92% of the
time.
2. Then specifies to the bidders the ambient conditions like
altitude, max and min ambient temperatures at site, the
quality of water for steam generation, the calorific value and
characteristics of the heavy fuel used to fire the boiler etc.
144
SPECIFICATIONS WRITING:
PROCUREMENT OF INFRASTRUCTURE
Each bidder then proposes its own design PROJECTS
to guarantee
the minimum output and required power station
availability and produces Functional Guarantees to
meet these required parameters plus the fuel
consumption figures at the guaranteed min output.
The PE then evaluates the bids based on such figures
and guarantees using Life Cycle Bid Evaluation
method.
LCC methodologies calculate costs by assessing the following:
investment costs (e.g. purchase price and associated costs),
operating costs (e.g. energy consumption), maintenance costs
(e.g. service charges, replacement), and end-of-life costs (e.g.
decommissioning and disposal). 145
SPECIFICATIONS WRITING
FOR THE PROCUREMENT OF
CONSULTING SERVICES
147
SPECIFICATIONS WRITING:
PROCUREMENT OF CONSULTING
B. Specific Information to be included in TOR SERVICES
1. Background
• Why is this assignment being undertaken?
• How does it fit into the Project?
• What is the history of the Project/sector/problem to be
solved?
• Who will finance this assignment? Persons drafting TOR
should be familiar with the country, sector and type of work.
2. Objectives
• What does the PE wants to achieve from the assignment?
• What should be the end-product?
148
SPECIFICATIONS WRITING:
PROCUREMENT OF CONSULTING
3. Scope of Work SERVICES
• What specific areas should be covered by the consultant?
• How much detail is required in each area?
• Which other related areas should also be covered?
• How many phases of work and alternatives should be considered?
• What are the limits of the assignment?
4. Training
• What skills should the consultant transfer to the PE’s staff?
• What structured training program should be part of the assignment?
149
SPECIFICATIONS WRITING:
PROCUREMENT OF CONSULTING
SERVICES
5. Time Schedule and Reports
• What are the required starting and completion dates
of the assignment?
• When do certain phases have to be started and
completed?
• When are the consultant’s reports (inception,
progress, final) due for review?
• Which drawings, specifications, bidding documents,
data bases, etc. should be part of the reports?
150
SPECIFICATIONS WRITING:
PROCUREMENT OF CONSULTING
6. SERVICES
Information, Local Services, Personnel and Facilities To Be
Provided by the PE
• Which previously completed reports and documents are readily
available to the consultant?
• Where is the office space for the consultant's use during the
assignment (if any)?
• Which office services (telephone, fax, copying, internet, etc.) will
be provided to the consultant (if any)?
• How will transportation be provided (if any)?
• Who will be assigned from the PE's staff to work under the
direction of the consultant (if any)?
151
EXAMPLE: TERMS OF REFERENCE
1. Introduction/Background/Rationale
2. Objectives
3. Scope of services/ work – services to be performed
4. Expected deliverables/outputs
5. Estimated duration of project
6. Project site, if applicable
7. Implementation arrangement + responsibilities + reporting and communication protocols
8. Required qualification of consultant(s) – firm, key personnel
9. Shortlisting criteria based on Section 24.5.3
10. Technical evaluation criteria based on Section 33.2.2
11. ABC
12. Proposed terms of payment
13. Proposed mode of procurement & evaluation procedure
14. Justification for other procurement mode than public bidding
15. Proprietary Rights & Ownership
16. Data Privacy Act of 2012 Compliance & Non-Disclosure Agreement
LINKAGES CONNECTIONS
Reproduce Guidelines [No of copies (hard & soft) , type of paper etc] 10
CONDUCT OF RESEARCH STUDY ON ………………….
Objective(s): Determine .. Evaluate… Assess.. Establish .. Measure..
Gauge
SOW DELIVERABLES TOP
Inception report, Final Work Plan 15%
Develop research protocol Research Protocol including research design and sampling 10%
design, survey instrument
Obtain technical review Technical review results & revised protocol 10%
Obtain research ethics clearance ERC (ethics research committee) clearance & final 5%
(with human pax) research protocol
Pre-test survey instrument Sampling frame, test results, final survey instrument 10%
Prepare for data collection Enumerators & Supervisors manuals/guide 10%
Analyze data collection based on Draft data analysis 10%
plan of analysis
Present initial findings to .. Presentation materials, issues raised & suggestion 10%
Finalize research findings & Final research paper, executive summary, policy paper, 10%
prepare for publication publication copy [no of copies & make]; monitoring tool
Help disseminate results; present Presentation materials; Copies for distribution [No.; make 10%
in a forum, & to the ExeCom [type of paper, binding, color..]
COA – GUIDE ON AUDIT OF
PROCUREMENT (GAP)
3.2. Annual Procurement Plan (APP) – the requisite document
that the agency must prepare to reflect the entire procurement
activity (i.e., goods, services, civil works to be procured) that it
plans to undertake within the calendar year. This document
contains the following information:
3. Suspension of Officials
5. Project Delays
6. Project Failures
Defined as:
Note:
Latest version of PMR shows separate lists of Completed (top portion) and On-going Procurement Activities (bottom portion)
Downloadable at http://www.gppb.gov.ph/downloadables/SampleForms.html
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
PMR
1) Submission to the GPPB (Section 12.2 of IRR of RA 9184)
and 2) posting in the procuring entity's website of its
approved Procurement Monitoring Report within 14 calendar
days after each semester, following the form and format
downloadable from the GPPB website (Section 1.2 of the IRR
of EO 662)
Government Procurement Policy Board – Technical Support Office
5 RIGHTS IN PUBLIC
PROCUREMENT
Value
Value for
for Money
Money Source
Time/
Quantit
Deliver y
y
- obtaining better quality of PROCUREM
goods or services in more ENT
suitable quantities, just in
time when needed, from
better suppliers at prices that
continue to improve.