Critical Path Method
Critical Path Method
Method
Background and History
Developed in the 1950s by the US Navy
Originally, the critical path method considered
only logical
dependencies between terminal elements
Since then, it has been expanded to allow for the
inclusion of resources related to each activity,
through processes called activity-based resource
assignments and resource leveling.
Critical Path Method for the construction industry
Non-computer approach
John Fondahl
Phase I
- Create time estimates for each
operation
-Determine earliest possible start date,
earliest possible finish date , latest start &
finish
- Determine “free float” and “total float”
- Revised after completion of Phase III
Phase II
-Establish time-cost relationship
Establish scheduling variations
- Determine most favorable balance
between time-cost
-Normal Start – normal time, least cost
-All-Crash Start – least time, higher cost
Phase III
THE CPM APPROACH
DEFINITION
Float (slack)
- amount of time that a task can be
delayed without causing a delay to:
-subsequent tasks (free float)
-project completion date (total float)
Critical path
- is the sequence of activities which add up to
the longest overall duration. It is the shortest
time possible to complete the project. Any
delay of an activity on the critical path
directly impacts the planned project
completion date (there is no float on the
critical path). A project can have several,
parallel, near critical paths. An additional
parallel path through the network with the
total durations shorter than the critical path
is called a sub-critical or non-critical path.
Critical activity
– activity with zero float
Resource leveling
– iterative process of assigning crews to
activities in order to
calculate their duration
ACTIVITY IDENTITY BOX
Precedence Diagramming
Method (PDM)
Critical Path Analysis is an effective and
powerful method of assessing:
Tasks which must be carried out
Where parallel activity can be carried out
The shortest time in which a project can be
completed
Resources needed to achieve a project
The sequence of activities, scheduling, and
timings involved
Task priorities
SUMMARY
PDM
-is a visual representation technique that
depicts the activities involved in a project.
Precedence Diagrams are also known as
Project Network Diagrams. In this article,
both terms are used interchangeably.
PDM basic
Communicate:
The visual representation makes it easier for you
to communicate the flow of project execution
or the project activity flow.
No restrains
ADVANTAGES
Complicate manual calculation
DISADVANTAGES
Earliest Start Time –(ES)
Earliest Finish Time – (EF)
Latest Start Time- (LS)
Latest Finish Time- (LF)
Duration- (D)
Total Float- (TF)
PDM NOTATION
Finish-Start:
In this dependency, an activity cannot start
before a previous activity has ended
Start-Start:
In this dependency, there is a defined
relationship between the start of activities.
PRECEDENCE RELATIONSHIP
◦ Finish-Finish:
In this dependency, there is a defined
relationship between the end dates of
activities.
◦ Start-Finish:
In this dependency, there is a defined
relationship between the start of one activity
and the end date of a successor activity. This
dependency is rarely used.
PRECEDENCE RELATIONSHIP
LEAD
-Lead is the time that an activity precedes
the start or finish of the successor.
LAD
- Lag is the time that an activity follows or
delayed from the start or finish of its
predecessor
PERT
Identify the specific activities and milestones.
Determine the proper sequence of the
activities.
Construct a network diagram.
Estimate the time required for each activity.
Determine the critical path.
Update the PERT chart as the project
progresses.
PERT
Program Evaluation and Review
Technique (PERT), nodes, PERT event,
predecessor event, successor event, PERT
activity, Optimistic time, Pessimistic time,
Most likely time, Expected time, Critical
Path, Lead time, Lag time, Slack.
KEYWORDS
The main objective of PERT is to facilitate
decision making and to reduce both the
time and cost required to complete a
project.
OBJECTIVE
PERT is intended for very large-scale,
one-time, non-routine, complex projects
with a high degree of intertask
dependency, projects which require a
series of activities, some of which must be
performed sequentially and others that
can be performed in parallel with other
activities.
FIELD OF APPLICATION
PERT planning involves the following steps
that are described below.
1. Identify the specific activities and milestones.
The activities are the tasks required to complete
a project. The milestones are the events marking
the beginning and the end of one or more
activities. It is helpful to list the tasks in a table
that in later steps can be expanded to include
information on sequence and duration.
2. Determine the proper sequence of the
activities. This step may be combined with the
activity identification step since the activity
sequence is evident for some tasks. Other tasks
may require more analysis to determine the
exact order in which they must be performed.
DESCRIPTION
3. Construct a network diagram. Using the
activity sequence information, a network
diagram can be drawn showing the
sequence of the serial and parallel
activities. Each activity represents a node
in the network, and the arrows represent
the relation between activities. Software
packages simplify this step by
automatically converting tabular activity
information into a network diagram.
DESCRIPTION
4. Estimate the time required for each activity. Weeks are a
commonly used unit of time for activity completion, but any
consistent unit of time can be used. A distinguishing feature of
PERT is its ability to deal with uncertainty in activity completion
time. For each activity, the model usually includes three time
estimates:
Optimistic time – generally the shortest time in which the
activity can be completed. It is common practice to specify
optimistic time to be three standards deviations from the mean
so that there is a approximately a 1% chance that the activity will
be completed within the optimistic time.
Most likely time – the completion time having the highest
probability. Note that this time is different from the expected
time.
Pessimistic time – the longest time that an activity might
require. Three standard deviations from the mean is commonly
used for the pessimistic time.
DESCRIPTION
PERT assumes a beta probability distribution for the time
estimates. For a beta distribution, the expected time for
each activity can be approximated using the following
weighted average:
Expected time = ( Optimistic + 4 x Most likely +
Pessimistic ) / 6
This expected time may be displayed on the network
diagram.
To calculate the variance for each activity completion time,
if three standard deviation times were selected for the
optimistic and pessimistic times, then there are six
standard deviations between them, so the variance is given
by:
[ ( Pessimistic - Optimistic ) / 6 ]
DESCRIPTION
5. Determine the critical path. The critical path is
determined by adding the times for the activities in
each sequence and determining the longest path in
the project. The critical path determines the total
calendar time required for the project. If activities
outside the critical path speed up oe slow down
(within limits), the total project time does not
change. The amount of time that a non – critical path
activity can be delayed without the project is referred
to as a slack time. If the critical path is not
immediately obvious, it may be helpful to determine
the following four quantities foe each activity:
ES – Earliest Start time EF - Earliest Finish time
LS – Latest Start time LF - Latest Finish time
DESCRIPTION
These times are calculated using the expected
time for the relevant activities. The earliest start
and finish times of each activity are determined
by working forward through the network and
determining the earliest time at which an activity
can start and finish considering its predecessors
activities. The latest start and finish times are
the latest times that an activity can start and
finish without delaying the project. LS and LF are
found by working backward through the network.
The difference in the latest and earliest finish of
each activity is that activity’s slack. The critical
path then is the path through the network in
which none of the activities have slack.
DESCRIPTION
The variance in the project completion time can
be calculated by summing the variances in the
completion times of the activities in the critical
path. Given this variance, one can calculate the
probability that the project will be completed by
the certain date assuming a normal probability
distribution for the critical path. The normal
distribution assumption holds if the number of
activities in the path is large enough for the
central limit theorem to be applied. Since the
critical path determines the completion date of
the project, the project can be accelerated by
adding the resources required to decrease the
time for the activities in the critical path. Such a
shortening of the project sometimes is referred
to as project crashing.
Update the PERT chart as the project
progresses. Make adjustments in the
PERT chart as the project progresses. As
the project unfolds, the estimated times
can be replaced with actual times. In
cases where there are delays, additional
resources may be needed to stay on
schedule and the PERT chart may be
modified to reflect the new situation.
PERT is useful because it provides the
following information:
Expected project completion time;
Probability of completion before a specified
date;
BENIFITS
In the following example, the Project
manager knows the succession of the
project activities and the optimistic,
pessimistic and most likely time (in
weeks) for the following activities:
SAMPLE.CASE STUDY
ASSOCIATED NETWORK
The earliest start time, earliest finish
time, latest start time and latest finish
time for each activity are calculated in the
following table:
……………….