Project Info and Key Achievements: Line Ministry Grant (Artf/Ida) Disb. Ratio: Timeline DO/IS/Risk CPPR Advice (Mar 2019)
Project Info and Key Achievements: Line Ministry Grant (Artf/Ida) Disb. Ratio: Timeline DO/IS/Risk CPPR Advice (Mar 2019)
Project Info and Key Achievements: Line Ministry Grant (Artf/Ida) Disb. Ratio: Timeline DO/IS/Risk CPPR Advice (Mar 2019)
Issue 1. Slow progress in completion of schools - more than 50% of ongoing projects are below 50% of physical progress,
making it difficult for MRRD to meet the disbursement conditions this year. MRRD also needs to speed up the recruitment of
engineers to strengthen the supervision.
Action/Ask: MRRD is conducting an analysis of reasons for the slow progress. MRRD is also proposing to combine NCB
projects with CDC-led construction. The proposal is being reviewed by the Bank to gauge its legal and financial implications.
Issue 2. Due to slow progress on finalizing the implementation manuals for the soft components of the project, MOE has not
been able to commence certain activities. Especially, the lagging component is Teacher Training. However, work towards
achieving the DLIs for 2019 is largely on track.
Action/Ask: A high level attention by MOF is needed to expedite the recruitment process.