2.02 MM Agarwal

Download as pptx, pdf, or txt
Download as pptx, pdf, or txt
You are on page 1of 16

Semi high speed train Appropriate Track Heavy axle load train

Challenges & possible solutions for appropriate Track


technology for mixed traffic regime of Semi high speeds
& heavy axle loads BASED ON GLOBAL EXPERIENCE

By

M.M. Agarwal & K.K Miglani 1


1. Synopsis/Introduction

* IR are going ahead in a big way to introduce semi high speed trains which
should be cost effective & can be done expediously. On the same track,
the Railway are also planning to run heavy axle load trains to improve its
economy & make Railway self reliant.

* Track, being the basic infrastructure has to be updated/developed to


provide appropriate track technology as to ensure that it meets the
challenges of mixed traffic of semi high speed as well as of heavy axle
loads.

* The authors have made a detailed study of track standards required for
high speed trains/semi high speed trains as well as trains with heavy axle
loads on Indian Railways as well as of other developed railway system of
world such as Japan, Germany, France, USA etc.

* Based on experience gained by Global Railways including Indian


Railway the authors have made an effort to suggest appropriate Track
technology, to give best output to IR with safety, comfort & efficiency
for mixed traffic regime of Semi high speed & heavy axle load trains.
2
2. Methodology adopted to tackle the problem

* As there is hardly any literature available of running semi high


speed trains on IR as well as on world Railways. It is proposed to
make a study of high speed railway systems as well as of Semi-
high speed trains at global level including Indian railways & try
to get an idea of track standards for the same.
* Similarly, it is proposed to have a study of running heavy axle loads
trains on Global railways including Indian Railways & get an Idea
of track standards for the same.
* As track standards/specifications are bit different in moving semi-
high speed trains on one side & heavy axle load trains on other
side, it is a challenging job for Railway engineers to optimize the
track standards so as to move both types of traffic with
maximum efficiency.
* Finally taking an overall view, efforts have been made to suggest
appropriate track technology which can give optimum output in
mixed traffic regime of semi high speed & heavy axle loads
traffic.
3
3. High Speed trains on World Railways

* What is a high speed train: UIC defines a high speed train as


one that runs over 250 kmph. on dedicated tracks or at over 200
kmph. on upgraded conventional tracks.

* History of High Speed Railways


(i) The Construction of first high speed railways started in 1959 in
Japan of Tokaido-Osaka Section. Operations began on 1 Oct,
1964. This line is the world’s busiest high-speed rail line.

(ii) This revolutionary concept of high speed trains was caught on in


Europe in the 1980s ,followed by other countries like USA,
Russia & lately in China. In the last four decades, there has been
spectacular technological progress allowing speeds to be raised to
350 kmph.
(iii) High speed lines in the world exceeding 250 kmph. is about 30000
kms.
4
3.1 Track Structure used on High Speed Routes (HSR)

A study has been made of few high speed routes viz SNCF, Japanese
Railways, German Railways (DB), Spanish Railways Belgium Railways.
From study of these railways it is observed that most of the leading railways
operating at High speed use conventional track consisting rails fastened on
sleepers with elastic fastenings. The average Track structure being adopted
on High speed Railways is given in subsequently table.

3.2 High Speed Train on Indian Railways


(Mumbai-Ahmedabad High Speed rail corridor)
The Mumbai-Ahmedabad high-speed rail corridor for running of Bullet
trains is an approved high-speed rail corridor project connecting the cities of
Mumbai and Ahmedabad in India.
* MOU has been signed by the Govt. of India and Japan on 12 Dec, 2015.
* The project is estimated to cost 97,636 crore (US$ 15 billion).
Technical Features:
* Length of line : 508 kms; * Track gauge: 1,435 mm (4’ 8½”) Standard
Gauge
* Speed : 320 to 350 kmph; * Completion Time: 7 Years from 2019-2016
5
3.3 Other Features of Special Structures for High Speed Railway
1. Turnouts : When the speed on straight track is above 250 Kmph, High speed turnouts
with speed on curved track from 80 to 100 Kmph are warranted.

* Turnout : Flatter switch entry; for reduction of lateral forces & increased passenger comfort .
Design Movable Nose Crossing for reduction of gap at crossing

2 Bridges : Bridges as well as bridge approaches are the vulnerable points, Strengthen the
existing bridge network with minimum disruption to traffic and cost effectiveness.

3. Tunnels : Tunnel cross sections on high speed lines will be guided by the aerodynamic
Phenomena in the tunnel; * To reduce this effect, tunnel hoods are specially
designed with pressure release shafts.
4. Grade Separation/ : Grade separation/Level Crossings:
Level Crossing Normally level crossing is not suitable for
high speed train operation

5. Tilting trains on : To overcome the limitation of speed on


Curves account of sharp curves particularly on
mixed traffic routes, where it is not possible
to cant the track, vehicles with tilting
suspension system having tilting mechanisms Figure 1: Tilting Train
can be used. 6
4. Semi high speed Railways
* What is Semi High Speed Trains
Semi high speed trains are generally those trains which run at operational speed of 160 to 200
kmph with an average speed of about 110 kmph.
* IR are one of few Railways in world, which are planning to run semi high speed trains in big way.
* India has recently (5th April 2016) inaugurated the semi high speed train Gatimaan Express which
is India’s first semi high speed train running at top speed of 160 km/h from Delhi to Agra.

* Efforts to increase speed to 160-200 kmph.


Indian Railways aims to increase the speed of passenger
trains to 160-200 km/h on dedicated conventional tracks.
They intend to improve their existing conventional lines
to handle speeds up to 160 km/h, and plan to go for
speed above 160 kmph after removing the constraints.

Figure 2 Gatimaan Express


* Track Structure:
RDSO has specified track structure for Semi high speed for speed upto 160
kmph & also for speed from 160 to 200 kmph as give in para 3.2 of main paper.

* Constraints to be renewed for introducing semi high speed trains faster than
160 kmph. for (i) Sharp Curves (ii) Turnouts (iii)Improvement of track
geometry: 7
5. Heavy Axle load trains

The phrase ‘Heavy Haul operation’ came into prominence with the first Heavy Haul
Conference held in Perth in Western Australia in 1978. A large number of heavy
haul trains are being operated in America, Australia, Africa, Europe, Brazil,
Scandinavia and UK for last 3 to 4 decades.

* Experience of world Railways for design & maintenance of Track structure


The problems faced by some of the important heavy haul systems in the world
railways, in Construction and operation with special reference to Indian
Railways were studied. The case studies are :

* Burlington Railways of North America: oldest Heavy Haul operated railway


constructed in the decade 1970-1980.

* Fortescue Railway of Western Australia world’s newest Heavy- Haul, railway

* Hamersley Railways of North West Australia for maintenance of Heavy Haul


Railway Lines.

* Based on experience of the world Railway ‘Track structure’ & problem


8
areas have been identified.
* Track Structure was studied & these are given in table subsequently

* Problem areas particularly about Formation, Rails, Sleepers, Ballast, Track


fittings, Points & crossing as well as track maintenance & their remedial
measures were assessed as given in para 4.2 of the paper.

5.1 Dedicated Freight Corridor (D.F.C) of IR

In order to cater for heavy axle load traffic, Indian Railways have taken an
ambitious project of dedicated freight corridor, where only heavy axle load
freight trains will run at a speed of 100 kmph
* Details of approved DFC Projects
Two projects approved as DFC projects are Western Corridor from Delhi to
Mumbai (Dadri-Rewari-Vadodara-Mumbai) and Eastern Corridor from Delhi
to Howrah (Khurja- Kanpur-Sonnagar-Howrah).

* Type of traffic &axle load: 25 tonne double stack container movement with
15000 tonne trailing loads: 30 tonne for bridges. (Completion Date: October
2019)
9
6. Appropriate Track technology for mixed traffic regime of
Semi high speed & heavy axle load
The studies of Track requirements to run High speed railways, semi high speed
railways as well as heavy axle load trains on IR and also for developed global
Railways viz Japan, Germany, France, & USA etc as well as UIC standards have
given certain ideas to adopt track standards/ specifications & other requirement
of track technology for mixed traffic

Studies Undertaken
The studies are basically for 3 types of traffic requirement
* High speed traffic: (This is done as there is very little global experience
of semi- high speed traffic)
* Semi high speed traffic mostly on IR.
* Heavy axle load traffic on world railways.
* Heavy axle load traffic on IR (Dedicated Freight Corridor)
Decision
Based on close analysis of studies undertaken for 4 types of traffic and taking an
overall practical, view Appropriate Track standards are suggested as given in
next Table
10
Track structure for Track structure for Track structure for Track structure for Recommended track structure for
high speed Railways Semi high speed heavy axle load trains of DFC IR
of World Railways. world

1. Rail About 60 kg/m 71 kg & 90 UTS 60to 68 km routes 60 kg 110 UTS 60 kg UIC rails
CWR
2. Sleepers Concrete sleepers Mono block PRC Mostly PSC Sleepers PSC Sleepers PSC sleepers
or Glass fibre sleepers Some places wooden
glasses sleepers
3. Sleeper Density 1660 to 1724 1660 nos per km. 1660 to 1800 nos. PSC 1660 Nos. 1660 sleeper per km
sleepers per km per km per km.

4. Fastenings- Double Leaf spring/TGV ERC clips mark III Special type of --- Double Elastic fastening
Elastic fastenings noble/Vossloh with rubber pad 6mm fastening
type with rubber pads thick

5. Ballast * Ballasted track 250/300 mm depth Hard stone ballast Machine Hard stone ballast having
with 30 to 40 mm with 150 mm sub with 300 mm crushed ballast cushion of 250-300 mm
ballast cusion or ballast cysguib iver 150 mm with 300 mm with 150 mm sub-ballast.
ballastless track syv-ballast ballast cushion
6. Minimum radius varying from 7250 m 6000 to 10000 m 1750 m 1750 mm
of curve 4000 m to 6500
m
7. Max. superelevation varying from 150 140 mm 180 mm -- 165 mm
(Cant) mm to 180 mm

8. Cant deficiency varying from 50 65 mm 100 -- 75 mm (In special cases


mm to 112 mm 100 mm)
9. Minimum vertical varying 20000 m 24000 m -- 4000 m
radius to 25000 m
10. Maximum 0.15 to 0.20 % 0.1 % or 1 in 1000 1 in 400 1 in 400
gradient 11
6.1 Fittings & Fastenings for Appropriate Track
Due to heavy axle load, there is possibility of heavy wear & tear on fitting & fastening as per global
experience.
* Fastening get loose very fast and thereby effecting track geometry.
* Rubber pads get damaged early. Heavy crushing of rubber pads as can be seen in figure on main
paper.
* Glued Insulated Joint start failing because either insulation
insulation gets broken or failure of glue which bonds the
joints.
In order to overcome these problems, the following remedies
are suggested
(i) Double elastic fastenings are recommended.
(ii) Develop better design of rail pads like ‘Three Point Pad’ as
seen in figure
(iii) Bonded Insulated Joints are worst effected & their design
to be further improved by looking after the problems in Figure 3 : Three Point Pad
current design, maintenance & operation

Points & Crossing:


* To be modernised to cater for higher speed of atleast 50 kmph & preferably 75 to 100 kmph.
* Thick web, fixed heel type, head hardened switches with flatter entry & cast mangense crossing.
* Indian Railways have already designed a new high speed turnout of 1:12 type which have
potential of 50 kmph as given in figure 6.1 of the paper.
12
6.2 Recommended Track structure to suit the requirement of mixed traffic

Track Items Recommended track structure


1. Formation Formation should be stable so as to take heavy load and also for semi-high speed of 160 to 200 kmph

60 kg UIC rails having 90 UTS are recommended which can be suitable for semi high speed (160 to 200
2. Rail kmph) as well as high axle load traffic up to 25 tonne axle load.

3. Sleeper Prestressed concrete (PSC) sleepers are recommended. The sleeper density should be 1660 sleeper per km.

Ballasted track is recommended with hard stone ballast having full ballast cushion of 250 mm to 300 mm
4. Ballast with 150 mm sub ballast. IF necessary, work hardening to be done to improve quality of ballast.

(i) Double elastic fastenings are recommended.


(ii) To carry heavy axle load & to avoid failure of rubber pad, develop better design of rail pads like
5. Fitting & Fastenings ‘Three Point Pad’
(iii) Bonded Insulated Joints due to heavy axle loads these joints are worst effected & their design to
be further improved by looking after the problems in current design, maintenance & operation

To be modernised to cater for higher speed of atleast 50 kmph & preferably 75 kmph to 100 kmph.
6. Points & Crossing Indian Railways have already designed a new high speed turnout of 1:12 type which have potential of 50
kmph

7. Maximum Curvature For comfort & safety it should not be sharper than 1° (1750 m)

8.Maximum In order to provide proper comfort to traveling public as well as to provide safety to passengers/goods,
superelevation maximum superelevation of 150 mm is recommended.

A very smooth vertical curve is necessary for semi high speed railway to provide maximum comfort to
9. Vertical Curve passengers. The minimum vertical radius recommended is 4000 m for safe & smooth ride.

Considering comfort of passengers & safety of passenger/goods, max. gradient recommended is 1 in 400.
10. Ruling Gradient 13
6.3 Recommended Maintenance & Other Features
Track Maintenance:
* Track has to be maintained mechanically by a fleet of modern track machines.
* Regular monitoring of track is required by sophisticated/modern track recording car
* Isolated track defects should be attended by off-track tampers.

Rail Grinding: Due to heavy loads rail develops defect like Rapid rail wear & excessive
wear of rail on curves. Reprofiling should be done by Rail Grinding machine for
prolonging rail life as well to prevent defects in rail head.

Track Transition areas (Bridge approaches, Level crossings & special track works)

* Due to differential settlement, extra track stiffness and differential damping track
Components gets damaged quite early.
* Extra track maintenance is required of these difficult locations

Bridges: Bridges should be designed for heavier loading. Quality of bridge construction
and maintenance requires to be improved.
Level Crossings:
- No Unmanned level crossing
- Manned level crossing should be avoided. However, in unavoidable circumstances, it
must be interlocked with signals. 14
Fencing: For speed higher than 160 kmph fencing of the entire section may
become necessary. For speed upto 160 kmph, fencing can be need based in the
vicinity of the habilitation and in approach of major bridges, level crossings etc.
Improvement in Rolling Stock
LHB coaches are cleared for regular operation upto a maximum speed of 160
kmph. However for higher speed all the coaches will have to be air conditioned
to avoid dust ingress and air blast.
TALGO Coaches : Trains on conventional rail-
roads have been the fore-runners for Higher-Speed
Trains” in Spain, France, Switzerland and Russia.,
* Talgo coaches with their lower weight generate
lower centrifugal forces and can run faster.
* Talgo coaches trains are one of the possible
alternatives for running semi-high trains on IR.
Tilting trains: To overcome the limitation of speed
on account of tight curves vehicles with tilting Figure 4: Talgo Coaches Train
suspension system can be used.
- For mixed traffic requirement, tilting trains are not recommended for IR due to
practical problems based on Global experience.
15
7. Summarising

Based on experience of Global Railways including


Indian Railways for, (i) high speed routes (ii) semi-high
speed routes (iii) Heavy axle load routes including DFC.
Appropriate Track-technology has been suggested,
consisting of track standards, track maintenance etc
which is likely to meet the challenge of mixed traffic
regime of running of semi high speed trains as well as
heavy axle load trains.

THANKS
16

You might also like