SUMMARY WEEKLY TASK

Date: 13/5/2019
Activity: Plotting MP data

• Receive MP sheet for site FT008 Section 214.5, Gua Musang, Kelantan and FT185 Section 79.5, Jalan Gua
Musang – Lojing, Kelantan.

MP Sheet FT185 Section 79.5, Jalan


Gua Musang – Lojing, Kelantan
Total no. of MP: 6

MP Sheet FT008 Section 214.5, Jalan


Gua Musang, Kelantan
Total no. of MP: 6
PUSB GRADUATE TRAINEE
BATCH 1 (INTAKE: DEC 2018)

Name Ummi Suraya Binti Md No of 19


Yatim Mustafa Week

Division GPC-Design Date ( 13/5/2019 – 17/5/2019)

SUMMARY WEEKLY TASK

Date: 14/5/2019
Activity: Prepared slide presentation for site FT003/143/050, Jalan Johor Bahru – Kuantan, Daerah Mersing
Johor
• Things need to be prepared were remedial work layout drawing, cross section drawing, bill of quantity and
slope analysis.

• Proposed method: stone pitching

• The slope failure is located at roadside of FT003 Section 143, Jalan Johor Bahru - Kuantan, Daerah Mersing,
Johor.

• The slope failure occurred when the soil becomes saturated and water takes the place of air between the
grains of soil.

• This will cause the earth in slope become a lot heavier and prone to movement.

Site photos
PUSB GRADUATE TRAINEE
BATCH 1 (INTAKE: DEC 2018)

Name Ummi Suraya Binti Md No of 19


Yatim Mustafa Week

Division GPC-Design Date ( 13/5/2019 – 17/5/2019)

SUMMARY WEEKLY TASK

PROPOSED STONE
PITCHING

Remedial work layout plan

Cross section drawing

Prepared by, Acknowledge by,

……………………………………………… ………………………………………………
(Ummi Suraya Binti Md Yatim (Ir. Mohd Shafawi Bin Ishak)
Mustafa)