Network Planning Diagram
Network Planning Diagram
THE NETWORK
FUNDAMANTALS,
PLANNIG AND
SCHEDULING
THE NETWORK FUNDAMENTALS
a b
A B A
1 2 3
AOA
AON
ELEMENTS OF NETWORK DIAGRAMMING
A B
• Work B cannot start until after work A is completed
A
C
• C cannot start until both A and B are completed.
A B
• A must be completed before either B or C can start
C
A B
• Both A and C must be completed before
either B or D can start.
C D
A C
• Both A and B must be completed before C can start.
D depends only an B and A. X is called a dummy.
X
B D
A C
• D depends on A and B. C depends on A only.
Y • Y is a dummy.
B D
Principle in
Networking or Arrow
Diagram
Principle No. 1
That everything in the network or arrow diagram must have meaning.
Excavation
Making Forms
Pour Footing slab
3
Order and deliver cement Pour pedestal
Figure 5-5
In figure 5-5, pouring of footing slab and pedestal,
depends upon the completion of the two activities that
enter into their common starting point. Hence, it is
impossible to pour concrete on footing slab or pedestal
until after making both forms and delivery of cement
have been completed.
Staking
Secure bldg. permit
Batter Boards
5
Order and deliver cement Pour pedestal
Figure 5-6
Principle No. 2
That an Activity has a single definite starting point and a single definite ending point.
B
3
A
1 2
4
C
Principle No. 4
Dummy Activity
Duration of an Activity- time it takes an activity to be
finished.
Path- 1-2-4-6 or 1-3-5-6
c
a 2 4
f
Start 1 dummy
d
b 3 5 6
e g
EXAMPLE
Activity Precedes Expected time days
a c,b 4
c d 12
d i 2
b i 5
e f 3
f j 8
i j 12
j end 9
g h 1
h k 3
k end 15
PATH
a,c,d,i,j = 4+12+2+12+9 = 39
a, b,i,j = 4+5+12+9 =30
e, f, j =3+8+9 =20
g, h, k = 1+3+15= 19
WHAT IS PLANNING & SCHEDULING
Following Considerations
The Logic of its sequence must be reviewed for correctness.