Design & Optimization of Bed Material Screening Machine For AFBC Boiler

This document summarizes the design and optimization of a bed material screening machine for an AFBC boiler. It describes the system introduction, comparison to other systems, and a prototype design that separates materials into 3 sizes simultaneously. Laboratory results show the prototype recovers 75% of rejected material, saving over Rs. 190,000 per year in material costs and Rs. 394,000 per year in labor costs. A fund requirement of Rs. 25,000 is provided to cover components like sheets, shafts, pipes, angles, fabrication, frames, bearings, wheels, meshes, rings and a bed material supply system.

Uploaded by

mansukh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
299 views11 pages

Design & Optimization of Bed Material Screening Machine For AFBC Boiler

This document summarizes the design and optimization of a bed material screening machine for an AFBC boiler. It describes the system introduction, comparison to other systems, and a prototype design that separates materials into 3 sizes simultaneously. Laboratory results show the prototype recovers 75% of rejected material, saving over Rs. 190,000 per year in material costs and Rs. 394,000 per year in labor costs. A fund requirement of Rs. 25,000 is provided to cover components like sheets, shafts, pipes, angles, fabrication, frames, bearings, wheels, meshes, rings and a bed material supply system.

Uploaded by

mansukh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 11

Design & Optimization of Bed Material

Screening Machine for AFBC Boiler

RASIK TAVDI H.
YADAV PARTH S.
ANTANI NISARG H.
MAHESHWARI CHIRAG N.
ANTANI PARTHIV N.

(B.E.-MECHANICAL-8TH SEMESTER)
SYSTEM INTRODUCTION
SYSTEM COMPERISON
Field view of both system
Solution : 3 size separated at a time.
PROTOTYPE ARCHITECTURE
Lab. Results for prototype

SIZE STANDA CHARGE REJECT


PARAME RD (REUSE)
TER SPECIFI
CATION

> 2.36 NIL 0.78 % 9.62 %


MM

2.36 – 2.00 5 – 10 % 0.19 % 0.70 %


MM

2.00 – 1.00 70 – 80 % 61.58 % 62.10 %


MM

1.00 – 0.85 0 – 10 % 11.78 % 12.20 %


MM

< 0.85 NIL 25.67 % 15.38 %


MM
COST ANALYSIS AFTER IMPLIMENT NEW SYSTEM

BED MATERIAL & COST SAVING LABOUR COST SAVING


CONSUMPTION PER MONTH = 25000 KG 1 LABOUR COST = 365 RS.

TOTAL PRICE = 75000 RS. (1 KG = 3 RS.) TOTAL COST = 365*5 = 1825 RS.

28.23% REJECTED = 7057.5 KG AFTER NEW SYSTEM :-

AFTER NEW SYSTEM :- PER SHIFT IF MINIMUM 1 LABOUR WORK


REDUCE

75 % MATERIAL RECOVER FROM COST SAVING = 365 RS.


REJECT = 5293.125 KG
PER DAY = 365*3 =1095 RS.
PRICE = 5293.125*3 = 15879.375 RS. (PER
MONTH SAVING) PER MONTH COST SAVING = 1095*30=32850 RS.

PER YEAR 190552.5 /- COST SAVING PER YEAR LABOUR COST SAVING =
32850*12=394200 RS.

TOTAL SAVING = 190552.5 + 394200 = 584752.5 /-


Sr. No Stages June July Aug.’ Sept.’18 Oct. ’18 Nov. ’18 Dec. ’18 Jan. ’19 Feb .’19
’18 ’18 18

1 Area selection

2 Problem
identification

3 Data – design
collection

4 Plant observation

5 Define possible
solution

6 Tentative design of
machine

7 Final dimensions

8 Prototype

9 Experiments &
Result discussion

10 Material Purchase

11 Assembly with belt


system

12 Final screening
Machine
FUND REQUIREMENT

Sr. No. Component Approximate Price

1. Sheets ,shaft, pipe and angle material. 6200/-

2. Fabrication. 4335/-

3. Structure frame (75 MM channel) 3130/-

4. Bearing. 2000/-

5. Wheel 500/-

6. 8 Mesh & 20Mesh 1500+1350=2850/-

7. Inner + outer rings 460/-

8. Bed material supply system 5525/-

TOTAL 25000/-