Ranto Manullang KDTP - 2008

The document discusses heat exchangers and boilers. It describes different types of heat exchangers including shell and tube, air cooler/fin fan, and plate and frame. It covers inspection and testing procedures for heat exchangers. It also provides an overview of boilers, describing fire tube and water tube boilers. Specific details are given about PT Badak NGL's water tube boilers, including manufacturer, type, capacity, pressure rating and quantity. Inspection requirements for boilers are also mentioned.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPT, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
213 views33 pages

Ranto Manullang KDTP - 2008

The document discusses heat exchangers and boilers. It describes different types of heat exchangers including shell and tube, air cooler/fin fan, and plate and frame. It covers inspection and testing procedures for heat exchangers. It also provides an overview of boilers, describing fire tube and water tube boilers. Specific details are given about PT Badak NGL's water tube boilers, including manufacturer, type, capacity, pressure rating and quantity. Inspection requirements for boilers are also mentioned.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPT, PDF, TXT or read online on Scribd
You are on page 1/ 33

RANTO MANULLANG

KDTP - 2008
AGENDA
HEAT EXCHANGER
 Type & Parts of Heat Exchanger
 Inspection of Heat Exchanger
 Testing of Heat Exchanger

BOILER
 Boiler in general
 PT Badak’s Boiler
 Inspection Requirement

www.badaklng.co.id
Heat Exchanger

SHELL & TUBE

www.badaklng.co.id
Heat Exchanger
AIR COOLER / FIN FAN

www.badaklng.co.id
Heat Exchanger
PLATE & FRAME

www.badaklng.co.id
Heat Exchanger
Shell & Tube

TUBE BUNDLE
FLOATING HEAD
SHELL
CHANNEL BOX
END COVER
FRONT COVER

www.badaklng.co.id
BASIC COMPONENT

www.badaklng.co.id
Heat Exchanger
 Types of Shell & Tubes
Heat Exchangers based
on TEMA

www.badaklng.co.id
www.badaklng.co.id
www.badaklng.co.id
Inspection of Heat Exchangers
 During On line
 Wall thickness
 Visual Check for any leakage from nozzle
drain, vents and welds.
 Visual check insulation and CUI
 During Off Line
 Visual check on disassembled parts of
Heat Exchanger.
 Testing the Heat Exchangers

www.badaklng.co.id
Shell & Tube Type
 Common Problems
 Tube leak  plug or re-tube
 Plugged/blocked tubes  clean
 Erosion on the tubesheet, divider plates,
floating head  repair by welding or by
epoxy
 Scale on internal shell and tube bundle 
clean.
 Vibration on high velocity stream 
redesign, plugged the future leak tubes.
 Inspection Program
 Regularly shutdown, disassembled,
internally inspected and tested.

www.badaklng.co.id
Air Cooler
 Common Problems
 Scale on external tubes or fins 
regularly clean.
 Leak on roll joint of tube to tubesheet 
reroll or plug.
 Erosion on header box  replace plate or
reinforced externally.
 Inspection Program
 Visual inspection

www.badaklng.co.id
Plate and Frame
 Common Problems
 Gasket defect between element 
retighten or replace
 Inspection Program
 Testing regularly.

www.badaklng.co.id
HEAT EXCHANGER TESTING

 Water Pass Test


 Hydrostatic Leak Test
 Pneumatic Leak Test
 Operating Leak Test

www.badaklng.co.id
Water Pass test
 Leak test on Divider Plate toTubesheet of Shell
and Tube Heat Exchanger
TUBE SHEET
 Performed:
TUBE
 After Opening Cover
TUBE
 Prior to closing Cover
DIVIDER PLATE

TUBE

TUBE

www.badaklng.co.id
Water Pass test

www.badaklng.co.id
Hydrostatic & Pneumatic Leak Test

Hydrostatic Pneumatic
Media Utility Water Nitrogen
Temperature < 50 0C < 50 0C
Press.Test 1.5 x Opr Pres 1.1 x Opr Pres
Press Direct Step by Step
Increment

www.badaklng.co.id
Hydrostatic & Pneumatic Leak Test
 General Requirement
 Inlet Supply
 Venting
 Drain
 PSV
 Pressure Indicator (PI)
 Temperature Indicator (If Required)
 PSV Requirement
 Setting PSV = 1.1 x Test Pressure
 Example :
 Pressure Test = 30 kg/cm2.
 Set of PSV = 33 kg/cm2.
 Pressure Indicator Requirement
 Calibration Date is still valid
 In good condition
 Max Scale of PI use is in range of 1.5 - 2 2 x Test pressure
 Example :
 Pressure Test = 20 kg/cm2.
 Max Scale of PI = 30 – 40 kg/cm2.

www.badaklng.co.id
Hydrostatic & Pneumatic Leak Test
 Persyaratan pelaksanaan
 PI shall be clearly shown and monitored
 Leak at connecting pipes, nozzles & test
rings are not allowed
 For Pneumatic test, pressure shall be
increase and decrease gradually
 After test pressure is reached the inlet
supply shall be blocked
 Test duration = Extent of Inspection

www.badaklng.co.id
Hydrostatic & Pneumatic Leak Test
 Shell Side Test
 Search any tube leak
 Check gasket tightness between bundle – shell
 Check any leak from weld and nozzle of shell
side
PI
PS
VENT V
Test
Ring
= close
= open

DRAIN
SUPPLY

www.badaklng.co.id
Hydrostatic & Pneumatic Leak Test
 Tube Side Test
 Check gasket tightness between Channel – Cover
 Check gasket tightness between Channel – Bundle
 Check gasket tightness between Bundle – Floating Head
 Recheck any tube leak suspicious
PI
VENT
PS
V

= close
= open

DRAIN
SUPPLY
www.badaklng.co.id
BOILER
 Boiler is an equipment which produces
steam by heating water, and the steam
is utilized outside this equipment.
 Two types of Boilers
 Fire Tubes Boiler
 Water Tubes Boiler

www.badaklng.co.id
Fire Tube Boiler

www.badaklng.co.id
Water Tube Boiler

PT BADAK’S BOILER :
• WATER TUBE TYPE
• WITH ECONOMIZER
(PRELIMINARY HEAT)
• WITH SUPERHEATER

www.badaklng.co.id
PT BADAK NGL’S BOILERS

Manufacturer : Mitsubishi Heavy Industry (MHI)


Tipe : VU-60
Capacity : 294.8 Ton/hr
MAWP : 72 kg/cm2
Quantity : 11 ea  31-F-01 ~ 31-F-11
www.badaklng.co.id
PT BADAK NGL’S BOILERS

Manufacturer : Babcock & Wilcox (BW)


Tipe : SB-22
Capacity : 379 Ton/hr
MAWP : 1050 psi
Quantity : 10 ea  31-F-21 ~ 31-F-30
www.badaklng.co.id
Module I Boilers
HEADE
R S/H
S/H TOP
RISER TUBES TIMUR & BARAT BENDING
SEBELAH ATAS & BARAT
HEADER TIMUR
SEBELAH ATAS

STEA
M
BANK TUBES BAGIAN BARAT
WALL TUBES & TIMUR
DRUM
ATAS
AATASATAS B
A
G
B
.
A
A
G
. S/H
B S/H
FRON REA
T R BANK/GENERATOR
TUBES

S/H 300 mm DARI BENDING BAWAH


INLET&OUTLET ECONOMIZER
BAG. ATAS
S/H BOTTOM
BENDING D
B C
A
BENDING
BELAKANG

FURNACE UPPER WALL


TUBES

WALL TUBES WALL TUBES


FRONT REAR ECONOMIZER BAG.
BAWAH
FURNACE LOWER WALL
TUBES BANK TUBES
BELAKANG
WALL TUBE
BAWAH

B
A
MUD
BOTTOM FEEDER G
DRU
o TUBES .
B M
BANK TUBES OD 2.5" 200 mm DARIMUD
DRUM & SWAGE

HEADER TIMUR & BARAT SEBELAH


BAWAH

www.badaklng.co.id
Module I Boilers

www.badaklng.co.id
Module II Boilers
SUPERHEATER OUTLET
SATURATED
HEADER
STEAM
SUPERHEATER INLET
WALL TUBES TOP
HEADER
HEADER
RISER
TUBES STEA
M
o o o o o o
TOP WALL TUBES DRU
TOP WALL TUBES SECTION B M
SECTION A

BANK/GENERATOR
TUBES
S/H S/H
FRON REA
T R

SUPERHEATER
TUBES
MUD
BANK / GENERATOR
DRU TUBES TUBES
M END

INLET
ECONO H.
MIZER ECO.
OUTLET
H. ECO.
WALL TUBES WALL TUBES
FRONT REAR

BOTTOM WALL
BOTTOM WALL
TUBES
TUBES
SECTION A
o o o o SECTION
o B o
WALL TUBES REAR HEADER
WALL TUBES HEADER BOTTOM FEEDER BOTTOM
WALL TUBES FRONT HEADER
BOTTOM TUBES BOTTOM

www.badaklng.co.id
PTB Boiler Inspection
 Extend of Inspection
 Refer the Regulation, Code and Standard
such as NBIC and API RP 573.
 Inspection Frequency
 Refer to Government Regulation.
 Indonesian Government requires 2 years
of Inspection Interval (UU UAP 1930)

www.badaklng.co.id
Extend of Inspection
 Visual Inspection
 Flaw check using MT & UT on weld joints of
 Steam Drum & Mud Drum
 Superheater Headers
 Thickness check of critical parts
 Steam Drum and Mud Drum
 Superheater tubes system
 Wall tubes
 External Piping
 Hydrostatic Test
 Leak test
 Steam Test

www.badaklng.co.id