Construction Contract: Chua, Condes, Maravilla, Pader, Tilendo
Construction Contract: Chua, Condes, Maravilla, Pader, Tilendo
1.1.Essential
Essential Time of Commencement &
Elements
Elementsof of Completion
Contract
Contract
The Contractor shall begin the work on the date of commencement. He shall carry
C OMPLE TION
PROGRESS &
the Work forward expeditiously with adequate forces and shall achieve Substantial
Completion within the Contract Time.
If the Contractor is delayed at any time in the progress of the Work by any act or neglect of
EX TENS IONS
DELAY &
the Owner or the Architect, or any other reasons, the Contract Time shall be extended by
Change Order for the length of the delay actually and directly caused by such occurrences.
Any claim for extension of time shall be made in writing to the Architect not more than ten
days after the commencement of the delay; otherwise it shall be waived.
Extension of time provided for the completion of the Work shall be the Contractor’s sole
remedy for delay.
The Owner may seek recovery for actual damages suffered due to delays of the Contractor;
Contract Sum 09
C ompl etion
Payments &
and, including authorized adjustments thereto, is the total amount
payable by the Owner to the Contractor for the performance of
the Work under the Contract Documents.
Schedule of Values 09
C ompl etion
Payments &
Contractor shall submit to the Owner and the Architect for
approval a schedule of values which in the aggregate equals the
total Contract Sum, divided so as to facilitate payments to
Subcontractors. This schedule, when approved by the Architect
and Owner, shall be used to monitor the progress of the Work and
to compute the amounts of the various payments requisitioned on
the Certificates For Payment.
Applications for Payment 09
At least twenty-five (25) days before the date for each progress
C ompl etion
Payments &
payment established in the Owner-Contractor Agreement, the
Contractor shall submit to the Architect an itemized Application
for Payment. Applications for payment must include (add and/or
deduct) adjustments to the Lump Sum of the Contract resulting
from work performed under approved Change Orders and shall
be shown separately on the application for previous and current
periods.
Certificates for Payment 09
The Architect will, within seven days, after the receipt of the
C ompl etion
Payments &
Contractor’s Application for Payment, either issue a Certificate for
Payment to the Owner, with a copy to the Contractor, for such
amount as the Architect determines is properly due, or notify the
Contractor in writing his reasons for withholding a Certificate.
Progress Payments 09
After the architect has issued a Certificate for Payment, the Owner
C ompl etion
Payments &
shall make payment in the manner and within the time provided in
the Contract Documents. The Owner shall make payments on
account of the Contract provided therein, as follows:
(a) On or about the twenty-eight (28th) day of each month 90% of the value of
each line item incorporated in the Work up to the first day of that month;
(b) Thirty (30) days after final completion of the Work, a final payment of the entire
balance due the Contractor.
Payments Withheld 09
The Architect may decline to certify payment and may withhold his Certificate in
C ompl etion
Payments &
whole or in part, to the extent necessary reasonably to protect the Owner, if in his
opinion he is unable to make representations to the Owner. If the Architect is
unable to make representations to the Owner, he will notify the Contractor. If the
Contractor and the Architect cannot agree on a revised amount, the Architect will
promptly issue a Certificate for Payment for the amount for which he is able to
make such representations to the Owner.
Payments Withheld 09
C ompl etion
Payments &
2 third party claims filed or reasonable evidence indicating probable filing of such claims
3 failure of the Contractor to make payments properly to Subcontractors or for labor,
materials or equipment
4 reasonable evidence that the Work cannot be completed for the unpaid balance of the
Contract sum
5 damage to the Owner or another Contractor
6 reasonable evidence that the Work will not be completed within the Contract Time
7 failure to carry out the Work in accordance with the Contract Documents
Substantial Completion 09
Upon Substantial Completion of the work or designated portion thereof and upon
C ompl etion
Payments &
application by the Contractor and certification by the Architect, the Owner shall
make payment, reflecting adjustment in retainage, if any, for such Work or portion
thereof, as provided in the Contract Documents. The Owner, when all the Work is
substantially complete, shall pay to the Contractor the balance due the
Contractor pursuant to the Contract.
Final Completion & Payment 09
Upon receipt and approval of written notice that the Work is ready for final
C ompl etion
Payments &
inspection and acceptance and upon receipt of a final Application for Payment,
the Architect will promptly make such inspection and, when he finds the Work
acceptable under the Contract Documents and the Contract fully performed, he
will promptly issue a final Certificate for Payment stating that to the best of his
knowledge, information and belief, and on the basis of his observations and
inspections, the Work has been completed in accordance with the terms and
conditions of the Contract Documents and that the entire balance found to be
due the Contractor, and noted in said final Certificate, is due and payable.
As Built Drawings 09
The Contractor shall red mark blue line prints of the project
C ompl etion
Payments &
indicating all changes to the drawings and submit them to the
architect or engineer prior to submitting final request for
payment. Where coordination drawings have been prepared
in CAD format, the Contractor shall also submit these CAD
files.
Operating & Maintenance
09
Manuals
Prior to invoicing for final payment, the Contractor shall submit
C ompl etion
Payments &
to the Owner Operating & Maintenance manuals and copies
of all approved submittals in the following formats: three hard-
copy sets of O&Ms and submittals in binders and electronic
copies of all O&Ms in a format acceptable to the Owner.
10 The Contractor shall be he Contractor shall take all
responsible for initiating, necessary precautions for
maintaining and supervising the safety of, and shall
Protection of Persons
2 AUTO LIABILITY
5 ENVIRONMENTAL LIABILITY
Insurance 11
expiration.
Insurance 11
SUBCONTRACTOR INSURANCE
Contractor shall require each of Contractor’s Subcontractors
to procure and maintain, until the completion of that
Subcontractor’s Work. It shall be the responsibility of Contractor
to ensure that all his Subcontractors comply with all of the
insurance requirements contained herein relating to such
subcontractors.
Insurance 11
MISCELLANEOUS PROVISIONS
- Neither the procurement nor the maintenance of any
insurance by Owner or Contractor shall in any way be
construed or deemed to limit, discharge, waive or release
Contractor from any obligation under the Contract, nor to limit
the liability of Contractor for any act or omission.
- Owner and Contractor waive all rights against each other for
damages caused by fire or other perils to the extent covered
by insurance provided
Changes in the Work/Substitutions 12
Manager, will have authority to order minor changes in the Work not
involving an adjustment in the Contract Sum or an extension of the
Contract Time and not inconsistent with the intent of the Contract
Documents. Such changes shall be effected by written order, and shall
be binding on the owner and the contractor. The contractor shall carry
out such written orders promptly.
Changes in the Work/Substitutions 12
Acceptance of Defective or
Non-Confi rmi ng Work
f the Owner prefers to accept defective or non-
conforming Work, the Owner may do so instead
of requiring its removal and correction, in which
case a Change Order will be issued to reflect a
reduction in the Contract Sum where
appropriate and equitable.
Termination of the Contract
14
TERMINATION BY THE CONTRACTOR
1) If the Work is stopped for a period of sixty
days under an order of any court or other
public authority having jurisdiction
2) If the Work should be stopped for a period
of thirty days by the Contractor because the
Architect has not issued a Certificate for
Payment or because the Owner has not
made payment