Burj Al Arab: Project Management
Burj Al Arab: Project Management
Burj Al Arab: Project Management
BURJ AL ARAB
PROJECT MANAGEMENT
2
Project Description
The Burj Al Arab is a luxury hotel located in Dubai, United Arab Emirates.
It is the third largest tallest hotel in the world.
Burj Al Arab stands on an Artificial Island on Jumeriah beach.
From its concept to its execution it has no peer
A hub for finance, and tourism.
The Burj Al Arab is 321 meters high and built 280 meters out of the sea
on a man made island.
It is 56(from ground) story building.
The Burj is managed by the Jumeirah Group and built by Said Khalil
It was designed by Tom Wright of WS Atkins.
3
4
Project Objectives
Underwater Restaurant
Aquarium
Helipad near roof at a height of 210 meters above ground
60 reception desks on each floor
Rolls Royce’s for the guests
24 carat gold iPad
6
Key Factors
Former name Burj Al Arab
Cost 500,000,000 US $
Height 321 meters
Chief Architect Tom Wright
Structural Engineer Atkins
Design Dubai's urban transformation(sail of a boat)
Designed by Burj Al Arab was designed by multidisciplinary
consultancy Atkins, led by architect Tom Wright
Construction Contractor Murray & Roberts
Type Skyscraper
Floors 56
Construction start date 1994
Construction end date December 1999
7
Continued……
Achievable:
The building would need to become synonymous in setting, similar to
the way Sydney Opera House and Eiffel Tower.
Relevant:
It is relevant in this sense that they want to construct a building that
could become a hub of finance and tourism.
Time:
It took approximately 5 year of time to Built.
10
The duration of this project is about from 1994 to 1999 at the end of the
year.
We divided project life cycle in to three Phases
1. Initial Phase
2. Intermediate Phase
3. Final Phase
19
Project Phases
Establish
Project Selection
• The idea was to design such a hotel which have its own uniqueness to attract tourist
from all over the world.
• The main objective of this project is to make Dubai a hub of Service, tourism and
Trade
• To gain International recognition and culture identity
The approach is to first design an Artificial man made Island on which this hotel stands
23
Project Life Cycle
Establish
Confirm Definition
The Sponsor wants worlds most luxurious hotel in the world, The ground Prince of Dubai
wants that the building should be unique to attract tourist from all over the world
the cultural representative Risk of making a solid base for this huge
building
Attract the tourism
Risk of whether condition
Risk of condensation
Placement of rocks
tons of sand
10 km Steel reinforce rods
Digging for basement
Under water resultant
27
The Structural Designing
Steps Wise
Building construction
Use of Concrete and steel
29
Room Furnishings
Electrical Equipment
Fountains
Air condition
Aquarium
Bars and reentrants
Marble import from brazil
and Turkey
31
Organize Resources
The final deliverable Burj Al Arab project the world’s only 7 star luxury hotel in
1999.
Construction Duration
5 years to complete
2 years to built the Island
3 year to construct the building
Risk Management
BY MUHAMMAD HASEEB
35
Risk Identification/Category:
Technical Risks:
Logistical Risks:
Construction Risks:
Financial Risks:
Political Risks:
Geographical Risks:
36
Risk Register
NO. Major Problem RISK RESPONSE Probability Impact
(0.1) to (0.9)
2 Delay in project Building the Basement The structural Engineer 0.8 HIGH
will present a solution
Initial proposal was by rock which was easily available and supported the
existing technologies.
Architect-Wright however rejected the proposal because this would make
island too high and his concept was –sail rising from water-people close to
sea.
Then Nicholas experimented with pioneering concrete blocks- specially
designed to reduce impact of waves. Testing were done to ensure island
was safe-3 weeks of testing came up with positive results.
40
Continued …..
SOLUTION
As wave hit the block, water pass inside and turn
around in itself and hence force is dissipated and
hence battle for secure island is won.
Island only 7 and half meter above sea level was
ready in Nov 1995.
41
Construction of Basement
RISK
Removing a sand could be dangerous
SOLUTION
Nicholas Injected liquid cement into
the sand to seal off his steel wall from
below
43
Foundation
SOLUTION
Then, reinforced concrete foundation piles deep into sand
with concept of skin –friction were designed.
Skin friction:
Resistance that stops the slipping between sand
and surface of piles. When friction between them is equal
to impact, situation is handled
Longer the pile the greater the effect of skin friction is.
45
Construction of Building
RISK
The walls of the building are not strong enough to handle high winds and
earthquakes.
SOLUTION
They presented a solution a gigantic steel structure outside the main
building known as the an exoskeleton.
A series of vast diagonal trusses tied to huge steel bows to the concrete
core at the back of the building
46
47
Cost Management
BY HAFSA
48
Cost Estimation
Project Closure
BY MUHAMMAD WAQAR
57
Project Closure
Thank You