Box Pushing Technology Presentation
Box Pushing Technology Presentation
To reduce the frictional resistance, a thin film of Grease and thick gauge plastic
sheet is provided between the top of the thrustbed & Bottom of the Box.
A Glossy Epoxy layer is also provided to reduce friction on the top and prevent
the disturbance of the mass over box to least during progress of pushing
Where mass of embankment is less or the soil is of poor quality, drag sheet
system is also considered for least resistance of friction and disturbance of mass
above box.
Auxiliary beds are also provided for casting of the other segments with thin
film of grease and plastic and segments are then brought in alignment of
pushing as and when required as pushing progresses.
With the progress of jacking, the front unit with shield penetrates into
the embankment and there after excavation within the shield is done
either manually or mechanically and the excavated stuff is transported
outside the working area.
After the first segment advances to the end of the thrust bed, the second
segment is brought in alignment of the front Box & intermediate jacking
space is lift between the two.
The progress of pushing is kept continuous and the system of side shifting of
remaining box segments from Auxiliary bed and bring in pushing alignment is
adopted till total length is pushed.
Hydraulic Equipment
The entire Box Pushing system is matter of proper selection of Hydraulic
equipment, as tremendous driving force is required for pushing of medium to
large size of Boxes.
So for this, Number of Jack units are provided in series for distribution of
pushing load evenly on the face of the concrete, and all Jacks are operated
simultaneously with a common power pack, which supplies uniform flow of
pressure through network of Hydraulic pipes of required pressure capacity,
commencing from front unit to rear unit. Jacking force is applied in
sequence.
This way pushing cycles are repeated till total pushing is completed.
Precautions
Cutting edge of front shield is Guide channels to be provided in
fabricated with adequate the thrust bed to guide the segments
to ensure straight alignment
thickness of steel plate and the
front edges of the steel plate
are sharpened to facilitate The level of the boxes should be
penetration into the soil. continuously checked.